Lichter v. Westinghouse Electric Mfg. Co.

140 F.2d 597, 1944 U.S. App. LEXIS 3994
CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 8, 1944
DocketNo. 9599
StatusPublished
Cited by1 cases

This text of 140 F.2d 597 (Lichter v. Westinghouse Electric Mfg. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lichter v. Westinghouse Electric Mfg. Co., 140 F.2d 597, 1944 U.S. App. LEXIS 3994 (6th Cir. 1944).

Opinion

McALLISTER, Circuit Judge.

Appellant company submitted a written offer to do the masonry work for the Fluorescent Lamp Plant which the Westinghouse Company was building at Fair-mount, West Virginia, for $78,000. The offer was accepted and a written contract entered into between the parties. The construction work was subsequently completed and paid for. Thereafter, appellant company claimed that, by virtue of an agreement, resting partly in parol and partly integrated in the above-mentioned written contract, it. was also entitled to do the masonry work on an adjoining Glass.Plant. When the Westinghouse Company, itself, carried out this latter work, appellant company sued for loss of profits resulting from alleged breach of contract.

On the trial, appellant company sought to introduce evidence of a parol agreement entered into between the parties prior to-the execution of the written contract for-the Lamp Plant. By this parol agreement, it was claimed that Westinghouse, in consideration of appellant company’s reduction of price from that which was first submitted for the construction work in the Lamp Plant, agreed that appellant company would also have thé masonry contract in-seven other buildings, at the same prices, per masonry unit as governed the Lamp Plant. These additional buildings were shown in outline on a plot-plan. layout, which was submitted to appellant company by the Westinghouse Company, and included the proposed Glass Plant. The cost of the Glass Plant, based on the masonry-units, required, would amount to $87,688.82, according to the claim of appellant company. The district court ruled evidence of such purported oral contract inadmissible as being in violation of the Parol Evidence Rule. Because of the holding, appellant-company was unable to prove the alleged' contract for the Glass Plant and, accordingly, failed in establishing its claim to-damages for breach of such contract.

On appeal, it is the contention of appellant company that there was one over-all oral contract- between the parties for the, masonry construction work in the Lamp-Plant, the Glass Plant, and the adjoining-buildings; that only part of the oral agreement — that • relating to the Lamp Plant— [599]*599was subsequently reduced to writing; that the Glass Plant agreement remained an oral contract, although the prices agreed upon for the masonry units in all the buildings were expressly integrated in the written Lamp Plant contract; and that the Glass Plant agreement could, therefore, be proved by parol evidence.

It appears that the parties carried on negotiations for some time before the written contract was executed. An offer in writing was submitted by appellant company to the Westinghouse Company, March 28, 1941, in which appellant company proposed to furnish all labor, tools, machinery, equipment, and materials necessary for the completion of the masonry work in the Fluorescent Lamp Plant, in accordance with the specifications, for the lump sum of $78,000. The offer further set forth that certain designated unit prices for masonry work “shall govern for additions or deductions to the work shown on the plans herein referred to or for work in adjoining buildings on the same property.” (Italics supplied.) It was also set forth in the offer that the Westinghouse Company should have the right to “increase or decrease the quantities shown at the unit price quoted.”

On April 8, 1941, the written contract was submitted to appellant company, and thereafter, on May 16, 1941, executed. It, like the offer, provided that the work on the Lamp Plant would be completed for the sum of $78,000; that unit prices set forth in the contract “shall govern for additions or deductions to the work shown on the plans herein referred to or for work in adjoining buildings on the same property.” (Italics supplied.) The Glass Plant was one of the adjoining buildings on the same property.

Testimony on behalf of appellant company with regard to the Glass Plant contract, was limited by the trial court to proof that appellant company originally proposed to do the masonry work on the Lamp Plant for $86,737; that the amount was reduced to $78,000 by appellant company; that the officials of both companies discussed the Glass Plant in connection with the reduction in price of approximately $8,000 in the proposal to do the work in the Lamp Plant; and that as a result of the proposal to do such work for $78,000, instead of $86,737, the written contract, herein referred to, was executed.

On the trial, counsel for appellant company offered evidence to prove that the Westinghouse Company, in order to induce appellant company to cut its price for the masonry work in the Glass Plant from $86,-737 to $78,000, orally promised appellant company the contract for the masonry work in the Glass Plant and in six other buildings adjoining the Lamp Plant, and that the parties further agreed that the unit prices for the masonry work (prices which appellant company would receive for supplying materials, and erecting the various tile partitions and brick-tile walls) would be the same for the Glass Plant as those in the Lamp Plant contract. Appellant company also offered in evidence a letter received from Westinghouse ■ subsequent to the execution of the Lamp Plant contract, reciting that the Glass Plant was to be of the same construction and contain the same number of units as the Lamp Plant. This proffered evidence was ruled inadmissible, as were all parol statements with reference to the Glass Plant, which were alleged to have been made by officials of Westinghouse before the execution of the contract for the Lamp Plant. Furthermore, proof was offered, and rejected, that Westinghouse officials had ordered appellant company to bind prices for the purchase of tile and brick to be used in the Glass Plant and the other adjoining building ; that such orders were thereupon given by appellant company; that about 5 days after the execution of the Lamp Plant contract, appellant company inquired when the masonry work would commence in the Glass Plant; and that the Westinghouse Company thereupon advised appellant company, by letter, that the brick work would not start until approximately six months thereafter.. Subsequent to the contract for the Lamp Plant, appellant company was given the contracts for six of the other buildings, but was refused the Glass Plant contract.

Appellant company contends that the written contract was incomplete on its face and that oral statements and negotiations were admissible to prove that part of the agreement not expressed by the writing. That is the issue.

Turning, then, to an examination of the contract, we find that, in the first paragraph, appellant company agreed to supply the materials and do the masonry work in the Lamp Plant according to the plans and specifications, at a stated price. At[600]*600tached to the contract was a rider to Article I, stating that certain unit prices should govern “for additions or deductions to work shown on the plans herein referred to or for work in adjoining buildings on the same property.” There is no other reference in the written contract to the work in the adjoining buildings, but a plot plan, showing in outline the Lamp Plant and several other buildings, including the Glass Plant, is referred to and made a part of the contract. This rider provision, therefore, bound appellant company on the extras to the masonry work in the adjoining buildings at a specified price, and bound Westinghouse to pay for the work that was done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
140 F.2d 597, 1944 U.S. App. LEXIS 3994, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lichter-v-westinghouse-electric-mfg-co-ca6-1944.