Lichter v. Bowaters Southern Paper Corporation

148 A.2d 671, 51 Del. 492, 1 Storey 492, 1959 Del. LEXIS 112
CourtSupreme Court of Delaware
DecidedFebruary 26, 1959
Docket21 and 30, 1958
StatusPublished
Cited by3 cases

This text of 148 A.2d 671 (Lichter v. Bowaters Southern Paper Corporation) is published on Counsel Stack Legal Research, covering Supreme Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lichter v. Bowaters Southern Paper Corporation, 148 A.2d 671, 51 Del. 492, 1 Storey 492, 1959 Del. LEXIS 112 (Del. 1959).

Opinion

Southerland, C. J.:

This case grows out of the construction of a large paper mill at Calhoun, Tennessee.

Plaintiff, Southern Fireproofing Company (“Southern”), was the subcontractor for the masonry work. Defendant, Bowaters Southern Paper Corporation, was the owner. The general contractor was Fraser, Brace & Roane-Anderson (“Fabroan”). Fabroan acted, however, as Bowaters’ agent in the matter. Southern’s contract for the masonry work was executed by Fabroan as Bowaters’ agent. J. E. Sirrine Company (“Sirrine”) was the architect and engineer.

Southern’s contract with Fabroan was signed on March 13, 1953. It incorporated by reference the general contract and the plans, specifications and conditions under which the work was to be performed.

There was a delay on the completion of the masonry work— fifteen weeks, as found by the trial judge. Southern says it was twenty-one weeks, but the point is immaterial here.

After the completion of the work, Southern and Bowaters were unable to agree on the amount due Southern. Southern brought suit in the court below, claiming damages for numerous alleged breaches of contract by Bowaters and for extras. Bowaters denied any liability, and counterclaimed for damages for alleged breaches of contract by Southern, including delay.

The case was tried by the court without a jury on oral testimony and documentary evidence. The court filed an opinion con *496 taining a series of findings of fact. The larger part of Southern’s claim was rejected, hut with respect to certain items it was allowed, with interest. Both parties appeal.

Many of the issues resolved by the court’s opinion are not raised here. Southern’s appeal presents four questions and Bowaters’ cross-appeal two others.

Southern’s Appeal

1. The principal item of damages asserted by Southern is a claim for $95,447.15 based upon unwarranted delays and interferences with the performance of the work alleged to have been caused hy Bowaters or Sirrine.

The trial court found that Southern had failed to prove its case, and rejected the claim. Southern in its brief asserts that there is ample evidence to justify a finding in its favor, and that there is no evidence to the contrary.

A reading of the testimony and documents supplied in the appendix to Bowaters’ brief shows beyond any doubt that the evidence offered by Bowaters tended to show that the delay in the completion of the masonry work was the fault of Southern itself. Plainly, the issue of delay was a question of fact. The trial judge found it against Southern; there was competent evidence to sustain his finding; and it will not be disturbed here. Turner v. Vineyard, 46 Del. 138, 80 A. 2d 177; Mulco Products, Inc. v. Black, 50 Del. 246, 127 A. 2d 851.

Southern does not seem to question this rule; its contention on the point, as we understood it from the oral argument, is this;

During the course of the trial Bowaters withdrew that part of its counterclaim alleging damages by reason of delays caused by Southern; such withdrawal, Southern argues, had the effect of removing from the court’s consideration the evidence offered by Bowaters in support of its counterclaims for Southern’s delay. Therefore, says Southern, the only evidence on the issue of delay was the evidence offered by Southern.

*497 The fallacy of this contention is obvious. Bowaters’ evidence was offered not only in support of its counterclaim but also in support of its answer, which expressly alleged that the delay in the completion of the masonry work was solely Southern’s fault. The judge had all the evidence before him, and resolved the conflict against Southern. That is the end of the matter.

A special point is made about the question of “access openings” as a cause of delay caused by Bowaters. Access openings are openings required to be left in the exterior walls for the admission of heavy machinery, so that such machinery may not have to be disassembled outside of the walls and reassembled inside. The cost of such openings the trial court found to be an extra. Southern argues that this was a finding of unnecessary delay caused by Bowaters which the court should have found to be a compelling illustration of Bowaters’ delay and from which the court should have inferred that all delays were the fault of Bowaters.

The conclusion does not follow. The court found in Southern’s favor that the access openings were not covered by the plans and specifications, but obviously also found that Southern’s claim for delay on that account was not proved.

2. The second question raised by Southern on the briefs concerns the legal consequences of delay under the terms of the contract if it be assumed that such delay was caused by Fabroan. How this can be an issue here we do not understand. Southern admits it made no contention below that Fabroan caused the delay. Therefore Southern cannot raise the point here. Stephenson v. Commonwealth & Southern Corporation, 19 Del. Ch. 447, 168 A. 211.

It is quite true that the trial court did consider this question. Bowaters expressly pleaded as a defense to the charge of delay an article of the contract providing that if Southern should be delayed in the prosecution of the work by act or neglect of Fabroan, the time for performance by Southern would on request be extended, and that such extension would dis *498 charge Fabroan from any liability by reason of the delay. The court below considered the validity of this provision and sustained it, although it was not strictly necessary for it to do so, because, as above stated, the issue of Fabroan’s responsibility for delay was not in the case.

Certainly that issue is not before us, and the validity of the contract provision referred to is therefore not before us.

3. The third question here concerns a claim of Southern for $6402.18 overhead and profit on premium overtime wages paid by Southern to its workmen.

The contract provides as follows:

“Fabroan, if it deems necessary, may direct the Subcontractor to work overtime and if so instructed the Subcontractor will work said overtime and, provided that the Subcontractor is not in default in any of the provisions herein, Fabroan will pay the Subcontractor for the actual additional wages paid at rates which have been approved by Fabroan, plus taxes imposed by law on such additional wages, plus compensation and liability insurance on said additional wages when required by law to be paid by the Sub-contractor.”

Bowaters paid Southern in accordance with the contract, but refused to pay overhead or profit. Southern argues that the contractual provision above quoted cannot be availed of by Bowaters (1) because the contract contemplated a normal workweek of forty hours, and in this case, because of Bowaters’ delays, overtime became “the rule of the job”; and (2) because conversations between representatives of Southern and Bowaters prior to the execution of the contract indicated that overtime would be negligible.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cooper v. Ross & Roberts, Inc.
505 A.2d 1305 (Superior Court of Delaware, 1986)
Mertes v. Mertes
350 F. Supp. 472 (D. Delaware, 1972)
Kuhn Construction Company v. State
248 A.2d 612 (Superior Court of Delaware, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
148 A.2d 671, 51 Del. 492, 1 Storey 492, 1959 Del. LEXIS 112, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lichter-v-bowaters-southern-paper-corporation-del-1959.