Liborio III, L.P. v. Artesian Water Company, Inc.

CourtSupreme Court of Delaware
DecidedOctober 11, 2023
Docket85, 2023
StatusPublished

This text of Liborio III, L.P. v. Artesian Water Company, Inc. (Liborio III, L.P. v. Artesian Water Company, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Liborio III, L.P. v. Artesian Water Company, Inc., (Del. 2023).

Opinion

IN THE SUPREME COURT OF THE STATE OF DELAWARE

LIBORIO III, L.P., § § No. 85, 2023 Plaintiff Below, Appellant, § § Court Below: Superior Court v. § of the State of Delaware § ARTESIAN WATER COMPANY, § C.A. No. N22C-06-109 INC., § § Defendant Below, Appellee. § §

Submitted: September 20, 2023 Decided: October 11, 2023

Before SEITZ, Chief Justice; VALIHURA, and GRIFFITHS, Justices.

ORDER

This 11th day of October 2023, after consideration of the parties’ briefs, and the

record below, it appears to the Court that:

(1) This is an appeal of Superior Court decision granting Defendant Below-

Appellee’s motion to dismiss. Plaintiff Below-Appellant filed suit in the Superior Court

seeking relief in connection with several contracts governing the supply of water to a

community in Bowers Beach, Delaware. Appellant, Liborio III, L.P. (“Liborio”) brought

claims for breach of contract and for fraud. The Superior Court dismissed both.

(2) This case also involves the Delaware Public Service Commission (“PSC”)

which regulates the activities of the Appellee, Artesian Water Company, Inc. (“Artesian”).

In addition to the contracts entered into between Artesian and Liborio, an order promulgated by the PSC factored in the trial court’s analysis, with a particular focus on

that order’s effect on certain contracts.

(3) The Superior Court examined the allegations in the complaint and those

agreements fairly incorporated into the complaint.1 It found no breach. Upon examining

Liborio’s fraud claim, the court held that the pleading lacked the requisite level of

particularity. We agree with the trial court that Liborio failed to satisfy the pleading

requirements with respect to the fraud claim.

(4) The breach of contract claim, though, presents a thornier question as there is

an unresolved factual discrepancy in the record concerning the timing of the first agreement

between the parties. As to the contract claim, we remand the matter to the Superior Court

to resolve this discrepancy and to determine whether its resolution of that issue affects the

court’s decision.

I. RELEVANT FACTUAL AND PROCEDURAL BACKGROUND2

A. The Contracts Between the Parties

(5) Liborio is a limited partnership organized under the laws of the State of

1 The Superior Court stated that “[t]he only water services agreement included in the Complaint is the Phase II Water Service Agreement.” Liborio III, L.P. v. Artersan Water Co., Inc., 2023 WL 1981824, at *3 n.17 (Del. Super. Feb. 14, 2023) (hereinafter, “Opinion”). It further stated that it would “analysis [sic] only the Service Territory Agreement, the Phase II Water Services Agreement, and the Phase III Water Services Agreement.” Id. The trial court opinion’s caption incorrectly spells “Artesian,” as “Artersan,” which is reflected in the Westlaw citation. 2 The facts, except as otherwise noted, are taken from the Superior Court’s Opinion. See Liborio, 2023 WL 1981824, at *1–4. Because this is an appeal of a motion to dismiss, “[t]his Court will ‘view the complaint in the light most favorable to the nonmoving party, accepting as true its well-pled allegations and drawing all reasonable inferences that logically flow from those allegations.’” Windsor I, LLC v. CWCap. 2 Delaware. It owns a land development in Bowers Beach, Delaware called Bowers

Landing. Bowers Landing is a community consisting of 184 single-family lots. Bowers

Landing receives its water from a single provider: Artesian. As the trial court described

it, “the entirety of [Bowers Landing] is located within Artesian’s water service

monopoly.”3

(6) To memorialize the supply of water to Bowers Landing, Liborio and Artesian

entered into a service territory agreement (the “Service Territory Agreement”) on July 30,

2002. Under the Service Territory Agreement, Artesian received exclusive rights to supply

Bowers Landing’s water supply. Further, the Service Territory Agreement provides that

there would be future water service agreements between Artesian and Liborio, broken up

into phases as Liborio develops specific lots being serviced. Several provisions of the

Service Territory Agreement are relevant. One such provision provides for a refund to

Liborio from Artesian (the “Refund Provision”). It states:

Upon completion of each phase’s installation, the final actual cost of the mains and hydrants will be computed and said cost, less the 15% overheads, shall be refundable to Owner at the rate of 15% of the net billings for water service and public fire protection for a period of twenty (20) years. Refunds shall be provided on a yearly basis.4

The Service Territory Agreement also provides for payment in phases (the “Payment

Provision”):

Owner agrees to pay Artesian the nonrefundable sum of Seventy-Five

Asset Mgmt. LLC, 238 A.3d 863, 871 (Del. 2020) (quoting Deuley v. DynCorp Int’l, Inc., 8 A.3d 1156, 1160 (Del. 2010)). 3 Liborio, 2023 WL 1981824, at *1. 4 A16 (Service Territory Agreement ¶ 3).

3 Thousand Dollars ($75,000) for the Owner’s share of the design and construction of the feeder main to the Development’s entrance at Skeeter Neck Road and Dune Drive. The main contribution shall be payable as follows: Twenty-Five Thousand Dollars ($25,000) to be paid with the water service agreement for the first phase of water main construction, and Twenty- Five Thousand Dollars ($25,000) to be paid with the water service agreements for Phase 2 and Phase 3 respectively as these agreements are executed.5

(7) Later, Liborio and Artesian executed the first water service agreement (the

“Phase I Water Services Agreement”) contemplated by the Service Territory Agreement.

However, the timing of the Phase I Water Services Agreement’s execution is the source of

the discrepancy in the record that needs to be resolved. The Superior Court was under the

impression that the Phase I Water Services Agreement was executed in 2004. 6 However,

the Appellant states, in its opening and reply briefs, that the Phase I Water Services

Agreement was executed in 2007: “[a]s alleged in the Complaint, on December 3, 2007,

some twenty months after the enactment of PSC Order No. 6873, which eliminated refunds,

the parties entered into the first phase-specific Agreement for Artesian to provide water

service for Phase 1, 54 lots in Bower’s Landing.”7 The Appellee does not refer to the date

5 A15 (Service Territory Agreement ¶ 2). 6 Liborio, 2023 WL 1981824, at *1 (stating that “[o]n July 30, 2002, Liborio and Artesian entered into a service territory agreement (the ‘Service Territory Agreement’) . . . [t]wo years after the Service Territory Agreement was executed the parties entered into their first water services agreement for the Phase I development of Bower’s Landing.”) See also id. at *9 (implying that the Phase I Water Services Agreement was executed before 2006 by stating that “[i]n April 2006, between the execution of the Phase I and Phase II Water Services Agreements, the PSC enacted Order No. 6873 . . . .”) 7 Opening Br. at 4. See also Reply Br. at 3 (“[c]onsequently, when the parties entered into an agreement in 2007 to provide water service for 54 lots in Phase 1, Artesian agreed that PSC Order No. 6873 was not applicable and Liborio would be entitled to ‘refunds’ for twenty years, as provided agreed [sic] in the 2002 agreement.”).

4 of the Phase I Water Services Agreement, and neither party includes the Phase I Water

Services Agreement in its appendix.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

White v. Panic
783 A.2d 543 (Supreme Court of Delaware, 2001)
Gatz v. Ponsoldt
925 A.2d 1265 (Supreme Court of Delaware, 2007)
Estate of Osborn Ex Rel. Osborn v. Kemp
991 A.2d 1153 (Supreme Court of Delaware, 2010)
Eagle Industries, Inc. v. DeVilbiss Health Care, Inc.
702 A.2d 1228 (Supreme Court of Delaware, 1997)
Deuley v. DynCorp International, Inc.
8 A.3d 1156 (Supreme Court of Delaware, 2010)
DiFebo v. Board of Adjustment of
132 A.3d 1154 (Supreme Court of Delaware, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Liborio III, L.P. v. Artesian Water Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/liborio-iii-lp-v-artesian-water-company-inc-del-2023.