Liberty Mutual Insurance Company v. Murphy

CourtDistrict Court, D. Maryland
DecidedJune 10, 2022
Docket1:20-cv-01961
StatusUnknown

This text of Liberty Mutual Insurance Company v. Murphy (Liberty Mutual Insurance Company v. Murphy) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Liberty Mutual Insurance Company v. Murphy, (D. Md. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

* LIBERTY MUTUAL INSURANCE CO. *

Plaintiff, *

v. * Civil Action No.: 1:20-cv-01961-SAG

JESSE J. MURPHY, et al., *

Defendants. *

* * * * * * * * * * * * *

MEMORANDUM OPINION

Liberty Mutual Insurance Co. (“Plaintiff”) sued J.M. Murphy Enterprises, Inc. (“J.M. Murphy”) and Jesse J. Murphy (collectively, “Defendants”), asserting a breach of contract claim involving a construction contract and related surety bonds issued by Developers Surety and Indemnity Company (“Developers”).1 ECF 17 ¶¶ 45-51. Defendants have filed a Motion to Dismiss the Complaint (“Motion”), ECF 23. The issues have been fully briefed, ECF 24, ECF 27, ECF 41, and no hearing is necessary. See Local Rule 105.6 (D. Md. 2021). For the following reasons, Defendants’ Motion will be denied. I. BACKGROUND The following facts are derived from the Amended Complaint, ECF 17, and are taken as true for purposes of evaluating Defendants’ Motion. On August 11, 2016, Developers, as surety, issued Payment and Performance Bonds No. 506266P (“the Bonds”) in connection with J.M. Murphy’s contract with HASCON, LLC

1 Plaintiff is the administrator and assignee of Developers, by virtue of a reinsurance agreement between the two entities. ECF 17 ¶ 1. (“Hascon”) to furnish and install concrete at the Maryland State Police Flight Training Facility at Martin State Airport (“the Project”). ECF 17 ¶¶ 6-7, 14-15; see also ECF 1-2 at 1. The Bonds named J.M. Murphy as principal and Hascon as obligee, and guaranteed J.M. Murphy’s completion of—and the payment of all labor, materials, equipment, and supplies used in

connection with—the Project. Id. As partial consideration, Defendants executed an indemnification agreement in favor of Developers (“Indemnification Agreement”) providing that they would be jointly and severally liable for certain of Developers’ specified losses in connection with the Bonds. Id. ¶ 8. As relevant here, the Indemnification Agreement extended to losses incurred by Developers as a result of claims, demands, suits, or settlements against the Bonds, as well as legal fees, costs, and other expenses associated with the investigation or defense of actual or potential claims. Id. ¶¶ 8-11. The Indemnification Agreement further provided that if it deemed necessary to protect itself against liability, Developers may demand a collateral reserve from Defendants. Id. ¶ 12. Plaintiff alleges that Defendants subsequently defaulted on obligations in the Project,

causing Developers to incur three categories of indemnified monetary losses. First, Developers satisfied several claims against the Payment Bond by subcontractors and suppliers, including: (i) a $17,650.37 payment to Neff Rental, LLC (“Neff”) on April 12, 2017; (ii) a $11,134.41 payment to Barker Steel Mid-Atlantic, LLC (“Barker Steel”) on April 12, 2017;2 (iii) a $8,361.82 payment

2 Notably, the Amended Complaint alleges that Developers paid Barker Steel $11,341.11, whereas the Demand Letter reflected a payment of $11,134.41. Compare ECF 17 ¶ 25 with ECF 1-3 at 2. This roughly $206 discrepancy has resulted in inconsistencies regarding the amounts of alleged damages. Compare ECF 41 at 3 (alleging that Developers paid $83,653.33 in claims) with ECF 1-3 at 2 (alleging that Developers paid $83,446.60 in claims). Moreover, although the Amended Complaint and Demand Letter both estimate total damages to be $109,300.90, this Court calculated the sum total in the Amended Complaint, given the higher alleged payment to Barker Steel, to be $109,507.60. Although ultimately, these discrepancies may need to be resolved to assess damages, they are not instantly material to this Court’s jurisdictional analysis. to Schuster Concrete Ready Mix, LLC (“Schuster”) on April 12, 2017; (iv) a $16,200 payment to Maryland Concrete Foundations, Inc. (“Maryland Concrete”) on August 8, 2017; and (v) a $30,100 payment to Merritt Development Consultants, Inc. (“Merritt”) on August 24, 2017. Id. ¶¶ 21-31. Developers also obtained a $10,000 credit from Hascon as part of a negotiated settlement

agreement regarding the Performance Bond, id. ¶ 20, resulting in Developers’ net payments for claims on the Bonds totaling roughly $73,446.60. Second, Developers spent $11,273.56 on Guardian Group, Inc. (“Guardian”), a surety claims consulting company that investigated claims against the Bonds. ECF 17 ¶ 33. Specifically, Developers paid Guardian Group: (i) $5,432.56 on February 8, 2017; (ii) $5,725.50 on March 22, 2017; and (iii) $115.50 on April 20, 2017. ECF 23- 1 (Ex. A, payments to Guardian Group, Inc.). Third and finally, Developers paid $24,580.74 in attorneys’ fees to Briglia McLaughlin, PLLC in the following increments: (i) $10,029.70 on March 30, 2017; (ii) $7,414.26 on May 4, 2017; (iii) $3,008.60 on July 19, 2017; (iv) $2,951.96 on October 24, 2017; and (v) $1,176.22 on February 13, 2018. See ECF 17 ¶ 35; see also ECF 23-2 (Ex. B, payments from Developers to Briglia McLaughlin, PLLC).

On April 2, 2020, Developers issued Defendants a written demand letter (“Demand Letter”) seeking immediate collateral in the amount of $109,300.90, which represented the $73,446.60 in claim payments and $35,854.30 in consulting and legal fees paid by Developers described above. ECF 17 ¶ 38; see also ECF 1-3. The Demand Letter stated that Developers would proceed with a lawsuit against Defendants if they did not respond by April 17, 2020. ECF 1-3. Defendants did not provide the requested collateral. ECF 17 ¶ 40. Roughly three weeks later, on April 24, 2020, Chief Judge Mary Ellen Barbera of the Maryland Court of Appeals issued an emergency administrative order (“Emergency Order”) in light of the COVID-19 pandemic, which tolled limitations periods in Maryland state court. ECF 17-2. Specifically, the Emergency Order provided that: all statutory and rules deadlines related to the initiation of matters required to be filed in a Maryland state trial or appellate court, including statutes of limitations, shall be tolled or suspended, as applicable, effective March 16, 2020, by the number of days that the courts are closed to the public due to the COVID-19 emergency . . .

Id. at 2. The Maryland Court of Appeals revised the Emergency Order on June 3, 2020, to clarify that for purposes of the statute of limitations, deadlines are tolled or suspended from “March 16, 2020 through July 20, 2020.” ECF 17-3. Plaintiff filed suit in this Court on July 2, 2020, invoking federal diversity jurisdiction and alleging damages “in excess of $109,300.90, together with interest, costs, and the additional attorneys’ fees and expenses incurred in bringing this action.” ECF 17 ¶ 51. Defendants moved to dismiss, asserting that because only $43,535.77 of Plaintiff’s alleged damages were timely, the action failed to satisfy the $75,000 amount-in-controversy required to invoke federal diversity jurisdiction. ECF 18; ECF 23. After review, this Court determined that the constitutional validity of the Emergency Order may be determinative of Defendants’ Motion. See ECF 34. Because the issue presented a substantial, unresolved question of state law, this Court certified the following question to the Maryland Court of Appeals: Did the Maryland Court of Appeals act within its enabling authority under, inter alia, the State Constitution and the State Declaration of Rights when its April 24, 2020 Administrative Order tolled Maryland’s statutes of limitation in response to the COVID-19 pandemic?

ECF 37; see also ECF 34 at 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
McBurney v. Cuccinelli
616 F.3d 393 (Fourth Circuit, 2010)
McBurney v. Young
133 S. Ct. 1709 (Supreme Court, 2013)
United States Ex Rel. Vuyyuru v. Jadhav
555 F.3d 337 (Fourth Circuit, 2009)
Hanscome v. Perry
542 A.2d 421 (Court of Special Appeals of Maryland, 1988)
Abadian v. Lee
117 F. Supp. 2d 481 (D. Maryland, 2000)
Gordon Goines v. Valley Community Services Board
822 F.3d 159 (Fourth Circuit, 2016)
Birmingham v. PNC Bank, N.A. (In Re Birmingham)
846 F.3d 88 (Fourth Circuit, 2017)
Michael Willner v. James Dimon
849 F.3d 93 (Fourth Circuit, 2017)
Cain v. Midland Funding
475 Md. 4 (Court of Appeals of Maryland, 2021)
Edwards v. City of Goldsboro
178 F.3d 231 (Fourth Circuit, 1999)
Liberty Mutual Insurance v. Triangle Industries, Inc.
957 F.2d 1153 (Fourth Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Liberty Mutual Insurance Company v. Murphy, Counsel Stack Legal Research, https://law.counselstack.com/opinion/liberty-mutual-insurance-company-v-murphy-mdd-2022.