Libby Rod & Gun Club v. Moraski

519 F. Supp. 643, 17 ERC 1631, 11 Envtl. L. Rep. (Envtl. Law Inst.) 21003, 17 ERC (BNA) 1631, 1981 U.S. Dist. LEXIS 18075
CourtDistrict Court, D. Montana
DecidedJuly 30, 1981
DocketCV-78-40-M
StatusPublished
Cited by6 cases

This text of 519 F. Supp. 643 (Libby Rod & Gun Club v. Moraski) is published on Counsel Stack Legal Research, covering District Court, D. Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Libby Rod & Gun Club v. Moraski, 519 F. Supp. 643, 17 ERC 1631, 11 Envtl. L. Rep. (Envtl. Law Inst.) 21003, 17 ERC (BNA) 1631, 1981 U.S. Dist. LEXIS 18075 (D. Mont. 1981).

Opinion

MEMORANDUM and ORDER

WILLIAM D. MURRAY, Senior District Judge.

I. BACKGROUND

This is another in a continuing series of attempts by the U. S. Army Corps of Engineers (Corps) to proceed with construction of a reregulating dam some ten miles downstream from the main Libby Dam in northwestern Montana, as part of a project referred to as the “Libby Additional Units and Reregulating Dam” (LAURD) project. This court enjoined construction of LAURD in 1978, finding that the project had not been authorized by Congress and that the defendants had failed to comply with certain NEPA requirements. 1 The Court of Appeals, treating the appeal on the authorization issue as a final appeal on the merits, affirmed this court’s finding that the reregulating dam had not been authorized by Congress, and reversed the injunction as applied to installation of four additional turbines in the main Libby Dam. 2 594 F.2d *645 742, 747. The court found it unnecessary to reach the NEPA issues, leaving further determination of those issues to this court “when and if the reregulation dam is authorized .... ” Id.

In the fall of 1980, this court again was compelled to enjoin the Corps from proceeding with activities in furtherance of its construction of the proposed — but unauthorized — reregulating dam. In September, 1980, the Corps undertook an exploratory drilling project in the vicinity of the reregulating dam. At a hearing on October 17, 1980, the court ordered that all drilling activities cease.

II. MOTION TO DISSOLVE THE INJUNCTION

Defendants now ask this court to dissolve the injunction prohibiting construction of the reregulating dam, basing their motion on Rule 60(b), F.R.Civ.P., and the inherent power of the district courts to modify injunctions in light of changed circumstances. U. S. v. Swift & Co., 286 U.S. 106, 52 S.Ct. 460, 76 L.Ed. 999 (1932). Defendants advance two arguments in support of their motion: First, that the deficiencies in the Environmental Impact Statement, upon which the court based its NEPA rulings, have been remedied; and second, that the determination that LAURD was not authorized by Congress is no longer valid because, according to a recent U. S. Supreme Court decision, the plaintiffs lacked standing to raise that issue. Both arguments must be rejected and the motion to dissolve denied.

The first argument advanced by defendants will not be considered. The court’s determination on defendants’ second argument makes any discussion of the NEPA issues unnecessary. Further consideration of the NEPA issues would be required only if Congress authorizes the dam, which it has not. See, 594 F.2d at 747.

Defendants’ second argument involves the recent Supreme Court decision in California v. Sierra Club,- U.S. -, 101 S.Ct. 1775, 68 L.Ed.2d 1011 (1981). Defendants argue that were this action brought today, the Sierra Club decision would compel the court to rule that plaintiffs would not have standing to question whether LAURD had been authorized by Congress. Defendants therefore contend that they are entitled to relief from the injunction under Rule 60(b), F.R.Civ.P. There are three major reasons why this argument must be rejected: 1) California v. Sierra Club, - U.S. -, 101 S.Ct. 1775, 68 L.Ed.2d 101 (1981), is not directly controlling; 2) Even if it were, the determination by the Ninth Circuit Court of Appeals that the dam is not authorized by Congress, and its affirmance of the district court’s determination that the plaintiffs had standing to raise that issue, are final judgments and stand as res judicata; and 3) defendants have failed to carry their burden of demonstrating any of the grounds for relief set forth in Rule 60(b)(5), F.R.Civ.P.

A. California v. Sierra Club is not controlling.

The court in California v. Sierra Club, Id., held that private parties have no private *646 right of action under Section 10 of the Rivers and Harbors Appropriations Act of 1899, 33 U.S.C. § 403, to question whether certain water projects have been áuthorized by Congress. Section 10 was not, however, relied on by this court or the appeals court to establish standing in this action. The question of standing was addressed partially under the rubric of Sierra Club v. Morton, 405 U.S. 727, 92 S.Ct. 1361, 31 L.Ed.2d 636 (1972), and partially under 33 U.S.C. § 401. See, Libby Rod & Gun Club v. Poteat, 457 F.Supp. 1177, 1182 (D.Mont. 1978). Thus, while it is clear that the recent decision in California v. Sierra Club, supra, would probably affect plaintiffs’ standing to maintain this action were it filed today, it is not entirely clear that the suit could not be maintained. Furthermore, as seen by the discussion in Parts II B and C below, whether or not California v. Sierra Club would be controlling on the issue of plaintiffs’ standing is irrelevant.

B. Res Judicata.

The final judgment on the merits entered by the Court of Appeals in Libby Rod & Gun Club v. Poteat, 594 F.2d 742 (9th Cir. 1979) established two things: First, that Congress had not authorized the reregulating dam; and second, that plaintiffs had standing to challenge construction of the dam. Neither of those rulings were appealed by defendants and now stand as res judicata to preclude defendants from relitigating them. See, Commissioner v. Sunnen, 333 U.S. 591, 597, 68 S.Ct. 715, 719, 92 L.Ed. 898 (1948).

It is also clear that the “res judicata consequences of a final, unappealed judgment on the merits [are not] altered by the fact that the judgment may have . . . rested on a legal principle subsequently overruled in another case.” Federated Dept. Stores Inc. v. Moitie, - U.S. -, 101 S.Ct. 2424, 69 L.Ed.2d 103 (1981), (citations omitted). Such a ruling is based on the long-recognized principle that “[p]ublie policy dictates that there be an end of litigation; that those who have contested an issue shall be bound by the result of the contest, and that matters once tried shall be forever settled as between the parties.” Baldwin v. Traveling Men’s Association, 283 U.S. 522, 525, 51 S.Ct. 517, 518, 75 L.Ed. 1244 (1931).

Defendants are bound by res judicata, both as to the authorization issue and as to plaintiffs’ standing to raise that issue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maulding v. Hardman
847 P.2d 292 (Montana Supreme Court, 1993)
Koch Ex Rel. Koch v. Billings School District No. 2
833 P.2d 181 (Montana Supreme Court, 1992)
Doe v. Trumbull County Children Services Board
502 N.E.2d 605 (Ohio Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
519 F. Supp. 643, 17 ERC 1631, 11 Envtl. L. Rep. (Envtl. Law Inst.) 21003, 17 ERC (BNA) 1631, 1981 U.S. Dist. LEXIS 18075, Counsel Stack Legal Research, https://law.counselstack.com/opinion/libby-rod-gun-club-v-moraski-mtd-1981.