Libby Creek Logging, Inc. v. Johnson

358 P.2d 491, 225 Or. 336, 1960 Ore. LEXIS 709
CourtOregon Supreme Court
DecidedDecember 30, 1960
StatusPublished
Cited by23 cases

This text of 358 P.2d 491 (Libby Creek Logging, Inc. v. Johnson) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Libby Creek Logging, Inc. v. Johnson, 358 P.2d 491, 225 Or. 336, 1960 Ore. LEXIS 709 (Or. 1960).

Opinion

HOWELL, J.

(Pro Tempore)

Plaintiff brought an action at law against the defendant upon a promissory note. The defendant, in its answer, admitted the execution of the note and alleged three further and separate defenses including a counterclaim for fraud. The jury awarded the defendant the amount demanded in the counterclaim and plaintiff appeals.

The plaintiff owned certain timberland in Curry county and, after some negotiations, entered into a *338 written contract to sell the timber to defendant. The final contract provided that the defendant was to pay $18,500 for “all logs removed np to and including 1,000,000 board feet” and $18.50 per thousand for all logs removed over and above one million board feet. The defendant paid $15,000 of the $18,500 in cash and gave plaintiff a promissory note for the balance of $3,500. The note is the subject of this action.

The defendant contends the plaintiff represented the timber had been cruised and that there was at least one million feet of merchantable timber on the property. When defendant logged the property it yielded only 504,250 board feet of logs.

Plaintiff’s brief states that two questions are presented for decision on this appeal. (1) Does the contract require the payment of $18,500 for all the logs removed up to and including one million board feet regardless of the amount actually logged, or is the contract ambiguous and, in effect, a timber cutting contract at $18.50 per thousand board feet for the amount actually logged? (2) Was the contract induced by fraudulent representations about the amount of timber on the property?

As plaintiff’s first assignment of error it claims the trial court erred in overruling an objection to the introduction of any evidence relating to the defendant’s first, second and third answer and counterclaim on the ground that none of them stated facts sufficient to constitute a defense.

The first affirmative answer alleged the contract is ambiguous and should be interpreted as a timber cutting contract based upon a price of $18.50 per thousand board feet of logs and not as a sale in gross for $18,500 for all logs removed up to and including one *339 million board feet. Defendant attached a copy of the agreement and incorporated it by reference.

The trial court found that the contract was ambiguous and submitted the construction of the contract to the jury as a question of fact. Exception was taken to this instruction and forms the basis for plaintiff’s fourth assignment of error. We shall consider these two assignments together as both raise the question of ambiguity of the contract.

If the provisions of the contract are plain and unambiguous, it is the function of the court to interpret the contract and declare its legal effect. Morey, Administratrix v. Redifer et al., 204 Or 194, 264 P2d 418, 282 P2d 1062; Columbia Co. v. Ross Island Co., 145 Or 96, 25 P2d 911; Wallace v. American Life Ins. Co., 111 Or 510, 225 P 192, 227 P 465.

If the language of the contract is ambiguous, or if technical words, terms of art, or local phrases are used, evidence showing the meaning or interpretation of the contract may be admitted. In such event, the jury should determine the intention of the parties. Dorsey v. Oregon Motor Stages, 183 Or 494, 194 P2d 967; Turner v. Jackson, 139 Or 539, 4 P2d 925, 11 P2d 1048 ; Salem King’s Products Co. v. Ramp, 100 Or 329, 196 P 401; Henry v. Harker, 61 Or 276, 118 P 205, 122 P 298; Longfellow v. Huffman, 55 Or 481, 104 P 961.

It is not necessary to set forth the agreement in full. While the contract mentions the vendor shall pay the taxes; that the timber shall be logged in a good workmanlike manner; the agreement cannot be assigned ; and the vendee shall render an accounting each month, these provisions were pertinent to the logging to be accomplished at $18.50 per thousand for all timber over one million board feet.

We believe that the following provision clearly *340 and unequivocally sets forth the intention of the parties as to the first million board feet of logs:

“* * * said payment of eighteen thousand five hundred dollars ($18,500) previously agreed to, constitutes full and complete payment for all logs removed up to and including 1,000,000 board feet.”

The contract is subject to only one interpretation. It constitutes an agreement to sell all the timber on the property up to and including one million board feet for $18,500. It is not a cutting contract for logs at $18.50 per thousand. Had the parties intended a per-thousand price for the first “up to and including one million board feet” as they did for the excess over one million, they could have stated it in the same simple terms.

While the first affirmative answer and defense alleged the contract was ambiguous, the defendant attached and incorporated a copy of the contract to the answer. The contract attached prevails over the allegations as to its legal effect. Kelley et ux. v. Mallory et ux., 202 Or 690, 697, 277 P2d 767; Strong et al. v. Moore et al., 118 Or 649, 245 P 505; Young v. Evans, 104 Or 619, 208 P 741. As the contract on its face did not support the allegation of ambiguity, the objection challenging the sufficiency of this defense should have been sustained.

For the same reasons the trial court should not have submitted the interpretation of the contract to the jury.

The plaintiff’s objection to the evidence on the second and third affirmative defense and counterclaim for fraud is not tenable. The objection appears to be based upon a claim that damages were not alleged. The counterclaim is in three separate counts and incorporates by reference certain paragraphs of the second *341 further and separate answer and defense. The defendant’s pleading in all three defenses falls short of being a model but the plaintiff did not demur or move against them prior to trial. We conclude that the defendant’s answer and counterclaim did allege a counterclaim for fraud including the element of damages.

Plaintiff’s next assignment of error is that the court should have required the defendant to elect to stand upon the defense of ambiguity alleged in the first separate answer or the defense of fraud. As we have concluded, the contract was not ambiguous, and we need not determine whether defendant could have been forced to elect between these two defenses if the contract had been ambiguous.

The last assignment of error is based upon the refusal of the trial court to grant a nonsuit against defendant’s counterclaim for the reason the defendant did not prove the allegations of fraud.

The counterclaim alleges, in substance, that the plaintiff misrepresented the amount of the timber upon the land and the boundary lines of the tract involved.

The elements of actionable fraud are well settled and it is not necessary to repeat them here. See Musgrave et ux. v. Lucas et ux.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hall Street Associates, L.L.C. v. Mattel, Inc.
145 F. Supp. 2d 1211 (D. Oregon, 2001)
Walker v. Woodworth
982 P.2d 1282 (Court of Appeals of Oregon, 1999)
Farmers Insurance v. Munson
930 P.2d 878 (Court of Appeals of Oregon, 1996)
Abercrombie v. Hayden Corp.
883 P.2d 845 (Oregon Supreme Court, 1994)
Carlson v. Reservation Ranch
848 P.2d 616 (Court of Appeals of Oregon, 1993)
Stayton Cooperative Telephone Co. v. Lockheed Electronic Co.
717 P.2d 1283 (Court of Appeals of Oregon, 1986)
Oregon Bank v. Nautilus Crane & Equipment Corp.
683 P.2d 95 (Court of Appeals of Oregon, 1984)
Wright v. Transamerica Title Insurance
628 P.2d 785 (Court of Appeals of Oregon, 1981)
White v. Reger
618 P.2d 1304 (Court of Appeals of Oregon, 1980)
Busto v. MANUFACTURERS LIFE INSURANCE COMPANY
556 P.2d 96 (Oregon Supreme Court, 1976)
Chambers v. SCHOOL DIST. NO. 40, WASCO CTY.
540 P.2d 1026 (Court of Appeals of Oregon, 1975)
Oregon, State Highway Com'n v. DeLong Corp.
495 P.2d 1215 (Court of Appeals of Oregon, 1972)
Rolfe v. Northwest Cattle & Resources, Inc.
491 P.2d 195 (Oregon Supreme Court, 1971)
May v. Chicago Insurance Company
490 P.2d 150 (Oregon Supreme Court, 1971)
Johnson v. Northwest Acceptance Corporation
485 P.2d 12 (Oregon Supreme Court, 1971)
Hilburn v. Brodhead
444 P.2d 971 (New Mexico Supreme Court, 1968)
Finchum v. Lyons
428 P.2d 890 (Oregon Supreme Court, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
358 P.2d 491, 225 Or. 336, 1960 Ore. LEXIS 709, Counsel Stack Legal Research, https://law.counselstack.com/opinion/libby-creek-logging-inc-v-johnson-or-1960.