L.F. Pace Construction, Inc. v. State, No. Cv 960337366s (Jan. 7, 1997)

1997 Conn. Super. Ct. 147, 18 Conn. L. Rptr. 293
CourtConnecticut Superior Court
DecidedJanuary 7, 1997
DocketNo. CV 960337366S
StatusUnpublished

This text of 1997 Conn. Super. Ct. 147 (L.F. Pace Construction, Inc. v. State, No. Cv 960337366s (Jan. 7, 1997)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L.F. Pace Construction, Inc. v. State, No. Cv 960337366s (Jan. 7, 1997), 1997 Conn. Super. Ct. 147, 18 Conn. L. Rptr. 293 (Colo. Ct. App. 1997).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION Procedural Posture

The plaintiff, L. F. Pace Construction, Inc. (Pace), brought the present action against the Department of Public Works (DPW) following the termination of a contract to construct an addition to Memorial Hall at the campus of Western Connecticut State University (WESCON), a state run educational institution. The action seeks, inter alia, a declaratory judgment declaring the termination of that contract for cause null and void because such termination was accomplished without affording plaintiff (Pace) a pre-termination hearing in violation of its due process rights as guaranteed under Article First, section 10 of the Connecticut Constitution. DPW filed a motion to dismiss this action on the grounds that this court lacked subject matter jurisdiction inasmuch as the action was barred by the doctrine of sovereign immunity and Pace had no constitutionally protected property interest in said contract. That motion was denied by the this court in a memorandum of decision dated November 18, 1996.1 An evidentiary hearing which is the subject of this memorandum followed to determine if in fact the plaintiff was given all the process it was due under the aforementioned section of our constitution. The court here concludes after a full hearing on that subject that it was not afforded due process for the reasons hereinafter set forth.

Operative Facts

Pace was first alerted to any serious concerns over its performance of the contract in question in September, 1995 as a result a conversation with the project coordinator (Dunn) He told Lawrence Pace "they" meaning the University officials and the architect were meeting with a view toward getting rid of Pace apparently due the many construction delays which had occurred.2 In fact, according the Nancy Griffin, the Director of Student Life at the University, the University was dissatisfied with Pace's performance from the inception of the contract as a result of the various delays and inconveniences suffered by the University which were believed to be the fault of Pace.

On March 1, 1996 DPW's bureau chief sent Pace a letter3 formally expressing DPW's concerns over the construction delays and Pace's failure to comply with various sections of the contract specifications, and in particular, with the compression CT Page 149 specifications of a concrete slab which was poured in December, 1995. This letter also warned that if all issues were not resolved to the complete satisfaction of DPW by March 10, 1996 the contract "shall be terminated".

Several days later Pace responded to the March 1st letter4 requesting a meeting to discuss these claims which it disputed. Pursuant to this request a meeting was arranged by telephone but the date was subsequently changed to March 19th. Except for the content of the March 1st letter itself, Pace was not otherwise informed of the purpose of meeting on March 19th nor was it given any advance agenda of the meeting despite the opportunity to do so as evidenced by a DPW fax message on MAR 15, 1996.5 More importantly, there was absolutely no indication in any prior communication between the parties that the March 19th meeting was to serve as a pre-termination hearing. Although DPW throughout this hearing, has characterized the March 19th meeting as a pre-termination hearing, Pace was under the impression its purpose was to merely resolve the matters referred to in the March 1st letter.

The meeting was held in the commissioner's office and was informal. In addition to the attorneys representing each party,6 present at the meeting was the commissioner, DPW's bureau chief, project coordinator and architect, two university representatives, Lawrence and Mark Pace, the principal officers of the plaintiff corporation and Pace's project engineer. There was no agenda distributed at the meeting nor any structure to it. It began with the commissioner informing the group assembled that he would not be able to devote too much time to this meeting as he had other appointments scheduled. He then asked Lawrence Pace to speak to the issues since he had requested the meeting

Taking the commissioner's opening caveat into consideration, Lawrence Pace touched briefly on all of the matters discussed in the March 1st letter, but the bulk of the discussion revolved around the failure of the concrete slab to meet compression specifications and the need for its removal. Pace's project engineer attempted to explain why the tests showing non compliance were invalid and referred to other tests that disputed DPW's claims. The commissioner invited Pace to furnish him with written documentation of its claim regarding the faulty testing procedures from the concrete supplier which Pace did two days later. There was apparently little or no response from the DPW staff members present at the meeting to Pace's denials or CT Page 150 explanations. No one was assigned to take notes of the meeting nor was any stenographic or tape recorded record made of the meeting. The entire meeting lasted about 30 minutes.

As the meeting ended, the commissioner assured Pace that he would "get back to them" and the Pace representatives left the room. The commissioner asked the representatives of the university and DPW's architect, the two parties Pace believed were plotting to remove it from the project, to remain. In Pace's absence a short meeting ensued between these people and the commissioner. No record was made of this meeting nor was Pace ever informed of the nature of this meeting.

On the day before the March 19th meeting DPW's project coordinator (Dunn) sent Pace a letter indicating DPW's conclusions regarding concrete test results and their recommendation that the slab be removed and a removal plan be submitted by a qualified structural engineer. Attached to this letter were copies of letters from DPW's architectural consultants and its project engineer presumably supporting DPW's recommendations. Pace did not receive this letter (or the attachments) until after the March 19th meeting.7 Consequently, Pace was unaware of DPW's latest position on the concrete issue prior to the March 19th meeting.

Following the meeting Pace received a letter dated March 26th from the commissioner referencing the contract violations spelled out in the March 1st letter and informing Pace that the O G test results (which were favorable to Pace) "proved to be unacceptable". He further indicated that after review of all relevant documents he concluded that the concrete slab had to be removed and directed Pace to remove the slab and submit a removal plan as well as a completion schedule by April 8, 1996 and that Pace's failure to so comply would result in DPW ". . . exercising all contractual and statutory rights and remedies up to and including termination. . . ." This letter was unclear as to the nature or source of the proof of unacceptability of the O G test results. Nor did the commissioner offer Pace an opportunity to refute this "proof."8 Furthermore, the time frame within which Pace was to submit a removal plan certified by a structural engineer was arrived at unilaterally without any consultation with Pace who was to secure the services of such person.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Goldberg v. Kelly
397 U.S. 254 (Supreme Court, 1970)
Rosado v. Wyman
397 U.S. 397 (Supreme Court, 1970)
Wisconsin v. Constantineau
400 U.S. 433 (Supreme Court, 1971)
Mathews v. Eldridge
424 U.S. 319 (Supreme Court, 1976)
Cleveland Board of Education v. Loudermill
470 U.S. 532 (Supreme Court, 1985)
Hartford Accident & Indemnity Co. v. Williamson
216 A.2d 635 (Supreme Court of Connecticut, 1966)
Sentner v. Board of Trustees of Regional Community Colleges
439 A.2d 1033 (Supreme Court of Connecticut, 1981)
State v. Robinson
567 A.2d 1173 (Supreme Court of Connecticut, 1989)
Tedesco v. City of Stamford
610 A.2d 574 (Supreme Court of Connecticut, 1992)
Hunt v. Prior
673 A.2d 514 (Supreme Court of Connecticut, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
1997 Conn. Super. Ct. 147, 18 Conn. L. Rptr. 293, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lf-pace-construction-inc-v-state-no-cv-960337366s-jan-7-1997-connsuperct-1997.