L.F. Pace Cons. v. Dept. of Public Works, No. Cv96-0337366-S (Nov. 18, 1996)

1996 Conn. Super. Ct. 10029, 18 Conn. L. Rptr. 225
CourtConnecticut Superior Court
DecidedNovember 18, 1996
DocketNo. CV96-0337366-S
StatusUnpublished

This text of 1996 Conn. Super. Ct. 10029 (L.F. Pace Cons. v. Dept. of Public Works, No. Cv96-0337366-S (Nov. 18, 1996)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L.F. Pace Cons. v. Dept. of Public Works, No. Cv96-0337366-S (Nov. 18, 1996), 1996 Conn. Super. Ct. 10029, 18 Conn. L. Rptr. 225 (Colo. Ct. App. 1996).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION This action arises out of a contractual dispute between the plaintiff (Pace), the accepted bidder on a contract to construct an addition to a state building on the campus of Western Connecticut State University in Danbury and the State Department of Public Works (DPW). Pace has brought the instant action seeking a temporary and permanent injunction and declaratory relief against the defendant DPW for what it claims was an unjustified termination of said contract for cause.

The operative facts as gleaned from the pleadings, affidavits and exhibits in support of the motion to dismiss are that in September, 1995 Pace was awarded a contract to construct an additions and alterations to Memorial Hall on the campus of Western Connecticut State University, a state run educational institution. On or about December 12, 1995 as part of the construction process Pace poured a concrete waffle slab for the first floor of said multiple story building. According to contract specifications this slab was to attain a compression weight of 4,000 p.s.i. within 28 days of being poured. However, subsequent tests disclosed that these specifications were not completely attained possibly due to incomplete curing because of severe weather conditions. Meetings were held to resolve this problem without success and on March 26, 1996 DPW demanded that all deficiencies be corrected forthwith. Not being satisfied with Pace's response, on April 9, 1996, DPW notified Pace that the CT Page 10030 contract was terminated for cause citing three provisions in the default section of the contract. The default section in question also contained a provision authorizing termination without cause at "the convenience of" DPW. However, DPW elected not to terminate the contract for its convenience but for cause under three specific default provisions. No hearing or other formalized proceedings were held prior to termination. Pace subsequently brought the instant action for injunctive and declaratory relief.

Defendant has filed this motion to dismiss claiming the doctrine of sovereign immunity bars plaintiff's action which it characterizes as nothing more than an ordinary breach of contract dispute which does not give rise of any constitutionally protected property interest in this contract. Therefore sec.4-611 of the CGS is the only vehicle by which plaintiff can avoid the bar of sovereign immunity. Consequently the court is without subject matter jurisdiction to entertain this action.

Pace argues that the termination of the contract for cause violated a property interest in the continuation of said contract which is protected by Article First, section 102 of the Connecticut Constitution and that the defense of sovereign immunity is therefore not a bar to such actions or the extraordinary remedies it seeks to enforce its rights thereunder. The plaintiff further alleges in its complaint and here argues that the effect of such termination "for cause" will permanently and irreparably injure its ability to successfully bid and/or obtain future state construction contracts, the company's life blood, and consequently the remedies available under 4-61 are totally inadequate. While the defendant concedes that sovereign immunity may not bar actions against the state where a constitutionally protected property right is implicated, it steadfastly maintains that the contract in question does not rise to that level. Consequently, Pace's only remedy is under section 4-61 which does not permit the extraordinary relief plaintiff seeks.

Because of the latter mentioned arguments the issue of the appropriateness of the remedies is raised. The court addresses that issue first as it is the simplest to address. Suffice it to say that it is well settled that in a constitutional democracy the doctrine of sovereign immunity will not bar suits against the sovereign where its officials have acted in excess of their authority. Doe v. Heintz, 204 Conn. 17, 31 (1987). "The absolute bar of actions against the state has been modified by statute and CT Page 10031 by judicial decisions. Krozser v. New Haven, 212 Conn. 415, 420-21; cert. den. 493 U.S. 1036, 110 SCt 757; 107 Led 2nd, [L.Ed.2d], 774 (1989). The plaintiff claims that this is precisely what this suit is about and the court agrees.

With regard to defendant's claim that both injunctive and declaratory relief are inappropriate, our supreme court has held to the contrary. In the recent case of Savage v. Aronson,214 Conn. 256 (1990) the court said:

"We have excepted declaratory and injunctive relief from the sovereign immunity doctrine on the ground that a court may fashion these remedies in such a manner as to minimize disruption of government and to afford an opportunity for voluntary compliance with the judgment." Id. 266.

It is therefore clear that under certain circumstances both a law suit against the state can be brought inspite of the doctrine of sovereign immunity and the remedies of injunction and declaratory judgment are not barred by that doctrine.

The remaining and more difficult issue in this case is whether the termination of a construction contract with a state agency gives rise to a constitutionally protected property interest in its continuation, where the state chooses to terminate it for cause and where the effects of such termination upon the contractor will have significant lasting effects upon the contractor far beyond the immediate financial detriment? If it does, then the court has subject matter jurisdiction of this case.

Defendant's motion in effect challenges plaintiff's standing to raise the question of due process under Article First, sec 10 in the context of governmental construction contract disputes. Therefore, in order for plaintiff to prevail on this challenge it must allege a colorable claim of injury to an interest which isarguably regulated by statute or protected by Article First,sec. 10. Reitzer v. Board of Trustees of State Colleges, 2 Conn. App. 196,200 (1984) citing Data Processing Service v. Camp, 397 U.S. 150,153 (1969) and Ducharme v. Putnam, 161 Conn. 135, 139 (1971). The plaintiff has successfully accomplished that task.

Before explaining the rationale for this conclusion, the court finds it necessary to express the following caveat: it is not the intention of this court to nor should this decision be CT Page 10032 interpreted as constitutionalizing every contract with a governmental agency.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Perry v. Sindermann
408 U.S. 593 (Supreme Court, 1972)
Sidney Bleeker v. Michael Dukakis
665 F.2d 401 (First Circuit, 1981)
Ducharme v. City of Putnam
285 A.2d 318 (Supreme Court of Connecticut, 1971)
Retzer v. Board of Trustees of State Colleges
477 A.2d 129 (Connecticut Appellate Court, 1984)
Doe v. Heintz
526 A.2d 1318 (Supreme Court of Connecticut, 1987)
Krozser v. City of New Haven
562 A.2d 1080 (Supreme Court of Connecticut, 1989)
Savage v. Aronson
571 A.2d 696 (Supreme Court of Connecticut, 1990)
Fennell v. City of Hartford
681 A.2d 934 (Supreme Court of Connecticut, 1996)
Unger v. National Residents Matching Program
928 F.2d 1392 (Third Circuit, 1991)
Krozser v. Connecticut
493 U.S. 1036 (Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
1996 Conn. Super. Ct. 10029, 18 Conn. L. Rptr. 225, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lf-pace-cons-v-dept-of-public-works-no-cv96-0337366-s-nov-18-connsuperct-1996.