Lewis Wu v. Capital One NA

617 F. App'x 214
CourtCourt of Appeals for the Third Circuit
DecidedJune 11, 2015
Docket14-3719
StatusUnpublished

This text of 617 F. App'x 214 (Lewis Wu v. Capital One NA) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lewis Wu v. Capital One NA, 617 F. App'x 214 (3d Cir. 2015).

Opinion

OPINION *

BARRY, Circuit Judge.

Lewis and Rachel Wu appeal from an order of the District Court granting summary judgment in favor of defendants Capital One, N.A. and Chevy Chase Bank F.S.B. (“the Bank”) on appellants’ tort and contract claims relating to a mortgage loan extended by the Bank. 1 We will affirm.

I.

In 2006, appellants took out a loan from the Bank in the amount of $5,795,418 to buy, and build a home on, property in Alpine, New Jersey. Of that amount, $2,495,418 was allocated for the purchase of the property. The remainder, $8.3 million, was to be disbursed periodically for construction once certain “acceptance conditions” were satisfied, among them the Bank’s acceptance of a construction contract and contractor and an appraisal “showing an ‘as-completed’ value equal to or exceeding” the amount of the loan. (App.243a.) Additionally, the loan could not be in default. Whether these conditions were met was within the Bank’s “sole discretion.” (Id.)

Although these and the other requisites for appellants to proceed from the first (or “acquisition”) phase of the loan to the second (or “construction”) phase were to be satisfied by, at the latest, 180 days from the March 1, 2006 closing, and construction was to be completed within 12 months after that, appellants did not submit a proposed construction contract until August 30, 2007 — nearly 18 months after the closing. The proposed contract provided an 18-to-24-month time frame for construction, and an estimated construction cost of approximately $4.5 million — $1.2 million more than what the loan budgeted for construction. Despite these and other deficiencies in the proposed contract, the Bank proceeded to obtain two appraisals for the project. It accepted the lower of the two, which estimated the project’s “as completed” value at $7.45 million. This figure resulted in a loan-to-value (“LTV”) ratio of 77.8%.

After receiving the appraisals, the Bank informed appellants that for it to proceed with the project, they would have to verify assets in the amount of $3,873,525. Appellants failed to do so, and on October 9, 2007, the Bank informed them that the loan had “expired” on October 1, and that their mortgage payment would not be applied until an extension was- processed. An agreement extending the construction deadline by a year was subsequently executed.

The extra year proved futile, however, as appellants did not build the house. On October 9, 2008, the Bank informed them that the loan was in default “because the construction term ... [had] matured and *217 [had] not converted to permanent financing or been paid in full.” (App 528a.) The Bank originally demanded full repayment within 30 days, but ultimately allowed appellants another, more limited, extension • until October 1, 2009. This time, however, the extension was limited to repayment of the loan; the Bank refused to fund the construction.

Appellants’ loan was secured by a mortgage on the Alpine property and their residence in Norwood, New Jersey. The mortgage stated that it secured the repayment of the loan and the performance of appellants’ “covenants and agreements” under both the mortgage and the note evidencing the loan. (App.264a.) Additionally, a “Cross-Collateralization Rider” provided that the properties would be treated “as a single property” for purposes of collateral for the note. (App.290a.) A separate “Deed of Trust Rider” provided that if appellants reduced the outstanding principal balance to $4,740,892 within 90 days of the loan entering the permanent phase, the Bank would release the lien on the Norwood property. The parties agree that the amount of the reduction reflected the value of the Norwood property at the time of the loan closing.

In negotiating the second extension with the Bank — after failing to convince it to fund construction if he “downsized” to the original $3.3 million figure — Lewis Wu requested it release the lien on the Norwood property. He asserted that that lien was only intended to secure the construction portion of the loan, which by that point would not be disbursed. The Bank declined, countering that the Norwood property was encumbered in lieu of its requiring an approximately $1 million additional cash down payment at closing, and until that amount was paid, the property would not be released. Wu did convince it to waive its prepayment penalty if he made timely payments and paid off the loan by October 1, 2009.

Appellants stopped making payments on the loan in late 2009, and in April 2011, the Bank filed a foreclosure action in state court. On May 16, 2012, summary judgment was entered in the Bank’s favor. 2 On August 8, 2012, appellants filed this action, asserting claims for breach of contract, fraud, and credit slander, and seeking reformation of the mortgage. The District Court granted the Bank’s motion for summary judgment. This appeal followed.

II. 3

Appellants argue that their contract claims should have survived summary judgment because the Bank exercised the discretion granted to it under the loan documents in bad faith. They also assert that their fraud claim relies on statements of fact, not law, and that their fraud and credit slander claims were not preempted by the Fair Credit Reporting Act, 15 U.S.C. §§ 1681-1681x (“FCRA”). We reject the first two arguments, and decline to reach the third.

A.

A breach of contract claim requires proof that the defendant failed to perform as required under the contract. Murphy *218 v. Implicito, 392 N.J.Super. 245, 920 A.2d 678, 689 (App.Div.2007). Here,' appellants supplied no evidence of a breach by the Bank, rendering summary judgment in its favor appropriate. In re Ikon Office Solutions, Inc., 277 F.3d 658, 666 (3d Cir.2002) (if non-movant fails to establish essential element of claim on which it bears the burden of proof, “there is no issue as to a genuine issue of a material fact and thus the moving party is entitled to judgment as a matter of law”). Each of the challenged positions the Bank took—its $10 million appraisal requirement, $3.8 million asset verification demand, refusal to fund construction, and refusal to release the Norwood lien—finds support in the loan documents.

First, as a condition to funding construction, the loan documents allowed the Bank to require an appraisal indicating a project value “equal to or exceeding” the loan amount; the decision of whether that condition was satisfied was in its “sole discretion.” (App. 243a; see also App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federal Deposit Insurance Corporation, as Receiver for the First National Bank of Toms River, New Jersey v. Lawrence E. Bathgate, II Novasau Associates, a New Jersey Limited Partnership New Nas, Inc. T. Pamela Bathgate 54 Buena Vista Associates, a New Jersey Limited Partnership Tuscol Development, Inc., a New Jersey Corporation Old Monmouth Associates, a New Jersey Partnership Airport Associates, a New Jersey Partnership Gerald A. Gura the Club at West Deptford, a Limited Partnership, a New Jersey Limited Partnership State of New Jersey Columbia Savings and Loan Association Asset Recovery Management, Inc. William Bowman Associates, Inc. National Westminster Bank Nj, Successor to First Jersey National Bank/south. Lawrence E. Bathgate, II Novasau Associates New Nas, Inc. 54 Buena Vista Associates, a New Jersey Limited Partnership Tuscol Development, Inc., a New Jersey Corporation Old Monmouth Associates, a New Jersey Partnership, Third-Party v. William Barlow John C. Fellows, Jr. Ebert L. Hall Joseph P. Iaria David E. Johnson, Jr. Irene F. Kramer Jacqueline F. Pappas John F. Russo Leonard G. Lomell Office of the Comptroller of the Currency John McDougal Third-Party Federal Deposit Insurance Corporation, as Receiver for the First National Bank of Toms River v. Nla Associates Limited Partnership, a New Jersey Limited Partnership Lgp-I Limited Partnership, a New Jersey Limited Partnership Lgp-I Capital Corp., a New Jersey Corporation New Nas, Inc. Lawrence E. Bathgate, II Alan B. Landis Novasau Associates, a Limited Partnership, a New Jersey Limited Partnership. Lawrence Bathgate, II Novasau Associates, Limited Partnership New Nas, Inc. 54 Buena Vista Associates Tuscol Development, Inc. And Old Monmouth Associates (The Bathgate Defendants)
27 F.3d 850 (First Circuit, 1994)
United States v. Hoffecker
530 F.3d 137 (Third Circuit, 2008)
Murphy v. Implicito
920 A.2d 678 (New Jersey Superior Court App Division, 2007)
Sons of Thunder, Inc. v. Borden, Inc.
690 A.2d 575 (Supreme Court of New Jersey, 1997)
Wilson v. Amerada Hess Corp.
773 A.2d 1121 (Supreme Court of New Jersey, 2001)
Daibo v. Kirsch
720 A.2d 994 (New Jersey Superior Court App Division, 1998)
Gennari v. Weichert Co. Realtors
691 A.2d 350 (Supreme Court of New Jersey, 1997)
St. Pius X House of Retreats v. CAMDEN DIOCESE NJ
443 A.2d 1052 (Supreme Court of New Jersey, 1982)
Blunt v. Lower Merion School District
767 F.3d 247 (Third Circuit, 2014)
Biederman v. Mitsubishi Motors Credit of America, Inc.
753 A.2d 1251 (New Jersey Superior Court App Division, 2000)
Suarez v. Eastern International College
50 A.3d 75 (New Jersey Superior Court App Division, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
617 F. App'x 214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lewis-wu-v-capital-one-na-ca3-2015.