Lewis v. New York Municipal Railway Corp.

109 Misc. 685
CourtNew York Supreme Court
DecidedJuly 1, 1919
StatusPublished
Cited by1 cases

This text of 109 Misc. 685 (Lewis v. New York Municipal Railway Corp.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lewis v. New York Municipal Railway Corp., 109 Misc. 685 (N.Y. Super. Ct. 1919).

Opinion

Kelby, J.

The action is to foreclose a lien. The defendant Conners Bros. Company on the 15th day of November, 1915, entered into a contract in writing with the New York Municipal Railway Corporation to construct concrete foundations and to erect thereon approximately two and two-tenths miles of a two-track elevated railroad structure known as section 2 of the Jamaica line, commencing at a point on Jamaica avenue, nea!r Walnut street, and running thence easterly [686]*686along Jamaica avenue, in the borough of Queens to Cliffside avenue, formerly Grant avenue. The work to be done under said contract was divided into five items. Item 1 was for the foundation excavation, and item 2 was for the construction of concrete foundations for piers or columns. On January 12, 1916, • plaintiff, Frederick N". Lewis, entered into a contract in writing with the Conners Bros. Company, Incorporated, by the terms of which plaintiff undertook-to perform items 1 and 2 of the said contract made by Conners Company with the railroad company for the agreed unit price of one dollar and twenty cents for each cubic yard of excavation and five dollars and ninety cents for each cubic yard of concrete masonry. Plaintiff entered upon the performance of the last-named contract and actually continued work down to and including May 29, 1916. On the 1st day of June, 1916, the plaintiff formally notified the Conners Bros. Construction Company that they elected to rescind the said contract. This was in conformance with a previous letter by the plaintiff to the said defendant, dated May twenty-ninth, wherein he stated an intention to abrogate the contract. The express ground -of rescission was that the work that he was being required to do was at variance with the contract, contract drawings, and certain other set -of drawings, entitled 66 Supplemental Drawings,” showing existing conditions above; the specific ground being that the contract and drawings above referred to showed the location of columns behind existing curbs, while the defendant and the railroad company were insisting upon the columns being erected in front of existing curbs, except in a few instances, where proposed curb lines have been shown in the contract drawings. The lien filed herein was bonded and discharged of record.

The plaintiff now sues on a quantum meruit after rescission, because of the alleged breach of the contract [687]*687by Conners Bros. Company, Incorporated, and he has adduced evidence showing the reasonable value of the work performed to be $7,526.70. The defendant Conners Bros, set up a counterclaim, alleging that the plaintiff breached his contract, and setting up damages of $35,000. The sole question then is: Which party breached the contract?

The contract of the plaintiff with Conners Bros, provides that he will “ furnish all materials and labor and tools * * * necessary * * * for the performance * * * all the excavation, masonry work, and incidentals, as set forth in items 1 and 2 in the contract ” between the railway company and Conners Bros., and further provides it shall be done “ according to the specifications and plans set forth and referred to in said contract, and which said plans and specifications, so far as they relate to said items 1 and 2, are hereby made part of this agreement,” and again, “All necessary lines, locations and grades * * * will be furnished * * * by the engineer of the New York Municipal Railway Corporation, under whose direction and to whose satisfaction the work is to be performed.”

The main contract between the railway company and Conners Bros, provides that “ a description of the work to be done is set forth, and the requirements, provisions, and details and specifications are stated in the printed form of contract and in the drawings therein referred to;” and at page 3 of the same contract it is provided that the contractor “ shall complete the works * * * in accordance with this contract and specifications and drawings herein mentioned: * * # Provided, however, that the said drawings may from time to time be altered or modified as hereinafter provided.” There is a further provision on page 5, subdivision 7, which gives the company the right, during the progress of the work, to amplify [688]*688the plans and to add explanatory specifications and drawings; and subdivision 8 on the same page: “ The company further reserves the right to alter in any way in which it may deem necessary the drawings aforesaid in part or altogether at any time during the progress of the work, without constituting any ground for any claim by the contractor for payment or allowance for damages or extra service on any basis other than that provided for in the schedule of prices for items of the different classes of construction involved in such changes or alterations. All work thus occasioned is not susceptible of classification under the schedule of prices than as otherwise provided herein.” At page 25, subdivision 2, is found the following: (2) The precise location, dimensions and other characteristics of the works are more fully stated in the specifications forming a part of this contract and on the detail drawings and plans hereinafter mentioned.” And at page 27: (1) The drawings referred to in this contract and specifications are divided into two general classes: Contract drawings C2901 to C2914, inclusive. The second class comprises drawings showing the details of elevated construction and are numbered as follows: Standard drawings, C886, C2538, A46, A523-1, A683, A684. In the contract drawings themselves, C2902 to C2910, both inclusive, are designated as alignment plans, and C2911 is designated as typical cross-section and details.” The alignment plans above mentioned—■ that is, C2902 to C2910, both inclusive — are drawn to scale, and they show either existing curb ” or proposed curb lines;” the curb line without any notation being existing curb line.

An inspection of these alignment plans shows that there were but few proposed changes in the curb line. The engineer of the railway, however, stated that he knew that there was going to be a substantial change in the curb line, but that he did not know whether the [689]*689general contractor knew of this change of curb line by the city or not. It seems to me clear that the alignment plans were intended to and did show the existing curb along the work. C2911, denominated ‘ ‘ a typical cross-section and details,” contained two half sections showing the type of construction with columns on curbs, and another half section showing type of construction with columns in street, and a general note on said plan reads as follows: “ Information to be supplied later as to which cols, are on curb and which are in street.” The distance from the center of the street to the center of the column is indicated by the word “ varies,” and this latter is with relation to columns on curbs. The half section with columns in street, the distance from the center of the column to the center of the street is indicated as thirteen feet, plus or minus. It appears from the evidence that the American Bridge Company was given the order for the steel on behalf of the contractor, and that the contractor authorized the railway company to deduct from his contract price the amount to be paid for said steel, and that on December 24, 1915, said company had received and commenced to fabricate the form of steel construction for piers on the curb. On September 29, 1915, the railway company furnished plans C5051 to C5071, inclusive, which are denominated

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lewis v. New York Municipality Railway Corp.
189 A.D. 904 (Appellate Division of the Supreme Court of New York, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
109 Misc. 685, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lewis-v-new-york-municipal-railway-corp-nysupct-1919.