Lewis v. Huyser

870 P.2d 95, 264 Mont. 141, 51 State Rptr. 192, 1994 Mont. LEXIS 53
CourtMontana Supreme Court
DecidedMarch 15, 1994
Docket93-396
StatusPublished
Cited by1 cases

This text of 870 P.2d 95 (Lewis v. Huyser) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lewis v. Huyser, 870 P.2d 95, 264 Mont. 141, 51 State Rptr. 192, 1994 Mont. LEXIS 53 (Mo. 1994).

Opinion

*142 JUSTICE HUNT

delivered the Opinion of the Court.

Plaintiff/appellant, Dick Lewis, appeals from a judgment of the Eighteenth Judicial District Court, Gallatin County, finding that his actions in refusing to continue the contract were a breach of the parties’ construction contract and awarding respondent, Biggerstaff Construction, its costs, disbursements, attorney fees, and ordering release of its posted bond on the subject property.

Affirmed and remanded for a determination and award of respondents’ additional attorney fees on this appeal.

The dispositive issue is whether appellant breached his contract with respondent Biggerstaff Construction when he refused to continue work because of his belief that the work required of him would be in violation of Montana building codes, and his further belief that the parties’ contract was unlawful.

Appellant Lewis is a licensed electrical contractor with his principal place of business in Big Sky, Gallatin County, Montana. Respondent Biggerstaff is a building contractor whose principal place of business is also in Big Sky. John Malpeli, Jr., is a developer of the property, San Marino Subdivision, at issue in this case. Denise, Anthony, Barbara, and Aimee Huyser are the current record owners of the San Marino Subdivision. The subdivision consists of eight residential lots, upon which Malpeli developed eight single-family log residences with common areas. The units in San Marino Subdivision are not commercial buildings or buildings to house five or more families.

In 1989, Malpeli contracted with respondent to construct the homes. Respondent proceeded with construction of the units as needed by Malpeli, with several units under construction at one time. Later in 1989, respondent and appellant entered into a real estate improvement contract in which appellant was to provide electrical supplies and perform the electrical services on the units. Appellant’s tasks included completing the “rough-in” phase of the electric wiring and ordering an inspection from the state electrical inspector when the wiring was completed. The rough-in phase consists of installing all of a building’s meter services, wiring, and electrical boxes and circuits before installation of insulation and interior walls. As the electrical contractor, appellant had the option of ordering a preliminary inspection of the rough-in phase of the wiring. Respondent and appellant agreed that their contract price was $5302. From 1989 to *143 early 1990, appellant completed electrical work on four of the units. In March 1990, appellant began work on the fifth unit.

On about May 7, 1990, respondent’s construction supervisor was asked by the purchaser of unit three to remove kitchen cabinets being stored there for later placement in unit five. In so doing, the construction supervisor hung the cabinets in unit five after installing tongue and groove boards and covering a portion of the wiring, despite appellant’s warning not to do so.

Portions of the wiring in the first four units which appellant had completed also had been covered, but the electrical inspector had not required that all the wiring be visible upon inspection of the rough-in wiling.

Appellant discussed the boards covering the wiring in unit five with several of respondent’s employees. The employees suggested to appellant that the work in unit five remain covered until the state electrical inspector was ready to view the work. Appellant did not accept this proposal and refused to proceed with the job until respondent’s employees removed all the wallboards covering the wiring in unit five. Appellant contended that if they did not remove the wall-boards, he could lose his electrical contractor’s license because the action was illegal. For several days and nights, appellant checked to see if respondent’s employees had removed the wallboards covering the rough-in wiring, but they had not.

On May 12, 1990, appellant met with respondent and another of respondent’s employees at respondent’s office. Appellant had not contacted the state electrical inspector prior to this meeting. At the meeting, appellant became agitated and complained that the covered wires in unit five had jeopardized his electrical contractor’s license. Respondent informed appellant that some of the wallboards had been removed. Respondent testified that throughout the meeting he attempted, without success, to work out a resolution with appellant in order to get him to finish the job. However, when appellant told respondent that he already had contacted an attorney about a construction lien for the work he had completed, respondent informed appellant that he should leave his office. Before leaving the office, appellant presented a prepared bill to respondent for the services he had provided on the project, stating that he had completed about 55 percent of the wiring for unit five and that he was through with the project.

Appellant did not return to the job. He contacted the state electrical inspector to inform him of the conflict and to discuss the situation. *144 The inspector told appellant that the covered wiring would not jeopardize the inspection or appellant’s electrical contractor’s license.

Respondent gave appellant several weeks to cool down, but appellant did not return. Respondent then hired a substitute electrical contractor to finish the job. In order to complete the job, the substitute electrical contractor was required to determine where all the wires ended, locate dead shorts, supply the fixtures which appellant had retained, and complete the wiring. Their bill to respondent to complete work on unit five and the remaining units was $5344, or $42 more than the total of respondent’s original contract with appellant.

On May 16, 1990, after appellant left the project, he filed a notice of right to claim lien with the Gallatin County Clerk and Recorder for electrical services and electrical fixtures he had provided for unit five. The amount of the lien was $2916.10. Appellant testified that he had installed meter services to the unit as early as two months prior to May 12, 1990. The construction lien statutes required appellant to file his lien no later than 20 days after he first provided services or supplies. Appellant mailed the notice to Malpeli more than 20 days after he had begun work on the project.

On December 5, 1990, and May 7, 1992, respondent posted two substitute bonds to replace and release appellant’s lien on the subject property, totaling one and one-half times the amount of the lien.

On May 3, 1993, the District Court found that appellant breached the parties’ contract without justification because appellant left the project after the electrical inspector had informed him that if no other problems existed, appellant could complete the rough-in and the inspector would not order a compliance, and would approve it. In addition, the court found that nothing had prevented appellant from completing the rough-in and calling for an inspection of the wiring, other than his failure to keep his temper under control. On June 8, 1993, the court entered its judgment awarding respondent $42 in damages, $251 in costs and disbursements, and $3931.50 in attorney fees, pursuant to § 71-3-124, MCA.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conner v. City of Dillon
2012 MT 21 (Montana Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
870 P.2d 95, 264 Mont. 141, 51 State Rptr. 192, 1994 Mont. LEXIS 53, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lewis-v-huyser-mont-1994.