Lewis v. Haskell Co., Inc.

304 F. Supp. 2d 1347, 2004 U.S. Dist. LEXIS 2369, 2004 WL 314460
CourtDistrict Court, M.D. Alabama
DecidedFebruary 17, 2004
DocketCivil Action 98-T-816-N
StatusPublished
Cited by1 cases

This text of 304 F. Supp. 2d 1347 (Lewis v. Haskell Co., Inc.) is published on Counsel Stack Legal Research, covering District Court, M.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lewis v. Haskell Co., Inc., 304 F. Supp. 2d 1347, 2004 U.S. Dist. LEXIS 2369, 2004 WL 314460 (M.D. Ala. 2004).

Opinion

OPINION

MYRON H. THOMPSON, District Judge.

This lawsuit is before the court again, this time on the issue of whether a party which has received an arbitration award in its favor is also entitled to a court order giving it “post-award, pre-judgment interest,” that is, interest that has accrued between the date of the arbitration award and the date of the court judgment confirming the award.

I.

The plaintiffs, Gilmore & Sons, Inc. (G & S) and three of its employees (Eddie Lewis, Larry Lewis, and Maurice Mims, who are African-Americans), charged the defendants, Haskell Company, Inc. (HCo.) and one of its supervisors (Louis Gouy-gou), with various federal and state-law violations arising out of work done at a construction project pursuant to a subcontract between G & S and HCo. The plaintiffs charged that the defendants discriminated against the Lewises and Mims because of their race in violation of 42 U.S.C.A. § 1981. They also asserted various state-law claims, including breach of contract, tortuous interference with business contract, general negligence and wantonness, negligent training and supervision, and outrage. The jurisdiction of the court was invoked pursuant to 42 U.S.C.A. §§ 1331 (federal question), and 1343 (civil rights), and 28 U.S.C.A. § 1367 (supplemental).

By order entered on August 4, 2000, this court required the plaintiffs to arbitrate their claims. Lewis v. Haskell Co., 108 F.Supp.2d 1288 (M.D.Ala.2002). In January 2002, this matter was heard by an arbitration panel, and, on September 13, 2002, the panel rejected all of the plaintiffs’ claims except one: 1 the panel found that G *1349 & S was entitled to be paid for satisfactory work it had completed but for which it had not been paid. 2 The panel calculated that the amount due for this work was $ 19,-848.00. 3 In the section of its decision and award entitled “conclusion,” the panel wrote “[G & S] is entitled to $ 19,848.00 from Haskell plus.prejudgment interest on said amount from September 1, 1998.” 4 Immediately below the conclusion, the panel stated that the amount owed for “Prejudgment interest' per Florida Statutes § 55.03 for the period 9/1/98 through 3/31/02 (% 10)” is $ 7,107.21 for a total award of $ 26,995.21. 5

On July 11, 2003, G & S returned to this court and filed an . application for judgment confirming the arbitration award, in which it requested this court “to enter a judgment upon the arbitration award in favor of Gilmore & Sons, Inc. and against [HCo.] in the amount of $ 26,995.21.” 6 On July 31, G & S amended its application to claim that it is also entitled to “post-award, prejudgment interest” from September 1, 1998, until the entry of a judgment by this court, and not just until March 31, 2002, as calculated in the arbitration award. 7 Accordingly, G & S seeks an additional $ 2,646.40 in post-award, pre-judgment interest, representing interest accumulated between March 31, 2002, and July 31, 2003. 8

After HCo. confirmed that it had paid G & S the $ 26,995.21 specified as the total amount due in the arbitration panel’s award, 9 this court issued an order denying G & S’s July 11 application for judgment confirming the arbitration award as moot and directing that its July 31 application be treated as an application for post-award, pre-judgment interest. 10

It is this application for post-award, prejudgment interest that is now before the court.

II.

G & S claims to be entitled to prejudgment interest for the period between March 31, 2002, and July 31, 2003; HCo. disagrees. Both parties rely on the terms of the arbitration award to support their arguments. Relying on the sentence *1350 in the conclusion of the arbitration panel’s decision that reads that G & S “is entitled to $ 19,848.00 plus prejudgment interest on said amount from September 1, 1998,” 11 G & S argues that the panel intended the payment of post-award, pre-judgment interest from September 1, 1998, until the confirmation of the underlying award, and it asks this court to order HCo. to pay interest from March 31, 2002, to July 31, 2003. HCo., on the other hand, relying on the panel’s calculation of pre-judgment interest from “9/1/98 through 3/31/02,” argues that the panel intended that no interest be paid for any period past March 31, 2002; HCo. further argues that G & S’s claim is foreclosed by the Federal Arbitration Act (FAA), 9 U.S.C.A. §§ 1-16, and Florida law.

This focus on the terms of the arbitration award is misguided, however. The issue of interest for the period of time between the arbitrator’s award and a final-court judgment confirming the award, that is, post-award, pre-judgment interest, is not one for the arbitrator to decide at all. As the Third Circuit Court of Appeals wrote in a case brought under the FAA to confirm an arbitration award, “the arbitrators were concerned with interest to the date of their award. They lacked authority to decide the entirely separate question of prejudgment interest on the amount confirmed by the district court judgment.” Sun Ship, Inc. v. Matson Navigation Co., 785 F.2d 59, 62-63 (3d Cir.1986). Rather, as the Tenth Circuit Court of Appeals has observed, “the granting of prejudgment interest from the date of the arbitrator’s award in an action seeking to confirm that award is a question of federal law entrusted to the sound discretion of the district court.” United Food and Commercial Workers, Local Union No. 7R v. Safeway Stores, Inc., 889 F.2d 940, 949 (10th Cir.1989); see also Val-U Constr. Co. of South Dakota v. Rosebud Sioux Tribe, 146 F.3d 573, 581 (8th Cir.1998); accord 1 Gabriel M. Wilner Domke on Commercial Arbitration § 30:05 (Rev. ed.2002). Thus, the obligation of the court responsible for determining whether the award should be confirmed is also to determine whether post-award, pre-judgment interest should be allowed. In this case, that means this court.

Under federal law, the prevailing party in FAA arbitration-confirmation proceedings is presumptively entitled to post-award, pre-judgment interest.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harris v. NCR Corporation
N.D. Georgia, 2024

Cite This Page — Counsel Stack

Bluebook (online)
304 F. Supp. 2d 1347, 2004 U.S. Dist. LEXIS 2369, 2004 WL 314460, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lewis-v-haskell-co-inc-almd-2004.