Lewis & Sims, Inc. v. Key Industries, Inc.

557 P.2d 1318, 16 Wash. App. 619, 20 U.C.C. Rep. Serv. (West) 1148, 1976 Wash. App. LEXIS 1756
CourtCourt of Appeals of Washington
DecidedDecember 29, 1976
Docket3245-1
StatusPublished
Cited by2 cases

This text of 557 P.2d 1318 (Lewis & Sims, Inc. v. Key Industries, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lewis & Sims, Inc. v. Key Industries, Inc., 557 P.2d 1318, 16 Wash. App. 619, 20 U.C.C. Rep. Serv. (West) 1148, 1976 Wash. App. LEXIS 1756 (Wash. Ct. App. 1976).

Opinion

Swanson, J.—Lewis

and Sims, Inc., an Alaska corporation, was awarded a subcontract to install a water and sewer system in the town of North Pole, Alaska. As part of the contract Lewis and Sims was required to furnish all the pipe necessary to complete the project. 1 Lewis and Sims *620 placed an order on January 27, 1972, with Liberty Equipment and Supply Co. (Liberty), a Washington corporation, for a quantity of pipe sufficient to complete the project. The purchase order signed by Harold Sims of Lewis and Sims and given to Liberty recited the size, quantity and the fact that the pipe was to be coal-tar enamel lined:

1,280' of 4" x 10" gage x 40' long pipe, coal tar enamel lined
11,560' of 6" x 10" gage x 40' long pipe, coal tar enamel lined
7,880' of 8" x 10" gage x 40' long pipe, coal tar enamel lined
1,640' of 10" x 10" gage x 40' long pipe, coal tar enamel lined
400' of 12" x 10" gage x 40' long pipe, coal tar enamel lined.

(Italics ours.) Finding of fact No. 3. (Note: The finding lists the total number of feet of pipe ordered in item two as 1,560' whereas the purchase order of Lewis and Sims lists the number of feet of pipe ordered as 11,560'.)

On February 2, 1972, Liberty which acted only as a middleman ordered the same pipe from Northwest. Pipe and Casing Co. (Northwest), an Oregon corporation engaged in the manufacture of steel pipe. Northwest in turn contracted with Hall Processing Co. (Hall), a Utah corporation with offices in Oregon, for the application of the coal-tar lining to the pipe. Thereafter, the pipe was shipped f.o.b. Clackamas, Oregon, to North Pole, Alaska, and was delivered at the jobsite on March 22 and 23, 1972. Once at the jobsite, the general contractor, Fairbanks-Lundgren, took charge of unloading the steel pipe. This unloading process with its inevitable rough handling of the pipe took place over a period during which the temperature at nearby Fairbanks, Alaska, ranged from a high on March 22, 1972, of +6° F to a low on March 24,1972, of -27° F.

*621 • During the middle of April 1972, Lewis and Sims began laying the pipe for the sewer outfall line. By early May of 1972, some 5,000 feet of pipe had been installed. It was also during the early part of May that Mr. Edwards Stitch commenced his duties as project inspector. His subsequent inspections of the steel pipe revealed that portions of the interior enamel lining had cracked away from the steel outer casing and were hanging down in large sheets. This condition existed throughout the remainder of the pipe except for the pipe already installed. As a consequence, the pipe not already in place was rejected. In order to complete the project, Lewis and Sims ordered replacement pipe from Beall Pipe & Tank Corp., paying $39,861.78 for the pipe and freight. 2

Suit was commenced by Lewis and Sims against Liberty, Northwest, and Hall to recover for damages it allegedly suffered due to the defective pipe. The trial court, sitting without a jury, after entering findings of fact and conclusions of law, awarded a $64,273.95 judgment to Lewis and Sims against Liberty and Northwest. In reaching its decision, the trial court found that the pipe was intended for a particular purpose—the installation of a sewer and water project at North Pole, Alaska, commencing in the early part of April 1972. Delivery, the trial court reasoned, necessarily required handling in the unloading process. Since the lining could not withstand even the most careful handling due to the unusually cold weather, the trial court found that the pipe was not fit for the particular purpose intended at the time of contracting, as impliedly warranted by RCW 62A.2-315:

Where the seller at the time of contracting has reason to know any particular purpose for which the goods are required and that the buyer is relying on the seller’s skill or judgment to select or furnish suitable goods, there is *622 unless excluded or modified under the next section an implied warranty that the goods shall be fit for such purpose.

Although the appellants present this court with 11 assignments of error, their primary challenge is to the trial court’s finding of fact No. 22:

Liberty and Northwest each breached their implied warranty of fitness to Lewis & Sims. Northwest breached its implied warranty of fitness to Liberty.

In order to invoke the provisions of the section 2-315 warranty, the evidence must be sufficient to show that (1) the seller at the time of contracting had reason to know the particular purpose for which the goods were required, and (2) that the buyer relied upon the seller’s skill or judgment in selecting or furnishing suitable goods. Ringstad v. I. Magnin & Co., 39 Wn.2d 923, 239 P.2d 848 (1952); Burnett v. Hunt, 5 Wn. App. 385, 486 P.2d 1129 (1971); Garner v. S & S Livestock Dealers, Inc., 248 So. 2d 783 (Miss. 1971); 1 R. Anderson, Anderson on the Uniform Commercial Code § 2-315:4 (2d ed. 1970). In marked contrast to other commercial code warranties, it is imperative to the existence of a warranty of fitness for a particular purpose that the buyer relied upon the seller’s skill or judgment in selecting the appropriate goods. In so relying, the buyer generally is ignorant of the fitness of the article offered by the seller and thus relies on the superior skill, information or judgment the seller possesses and not on his own judgment.

In Frisken v. Art Strand Floor Coverings, Inc., 47 Wn.2d 587, 288 P.2d 1087 (1955), 3 the owner of a commercial building entered into an agreement with a corporation engaged in the business of selling and laying floor coverings whereby the latter contracted to furnish and install asphalt tile on the floor of the premises. The building’s floor was concrete covered with magnesite. The corporation’s agent, after viewing the premises, recommended a certain tile suitable for the building owner’s needs. The tile, • as it *623 turned out, was incompatible with the magnesite under-flooring such that the tile floor became uneven and buckled. Our Supreme Court held that the seller impliedly warranted that the floor would be fit for the intended use regardless of the structure of the underflooring.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific American Leasing Corp. v. S.P.E. Building Systems, Inc.
730 P.2d 273 (Court of Appeals of Arizona, 1986)
Hiskey v. City of Seattle
720 P.2d 867 (Court of Appeals of Washington, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
557 P.2d 1318, 16 Wash. App. 619, 20 U.C.C. Rep. Serv. (West) 1148, 1976 Wash. App. LEXIS 1756, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lewis-sims-inc-v-key-industries-inc-washctapp-1976.