Lewis County v. Aetna Accident & Liability Co.

191 P. 146, 111 Wash. 333, 1920 Wash. LEXIS 636
CourtWashington Supreme Court
DecidedJune 23, 1920
DocketNo. 15686
StatusPublished
Cited by1 cases

This text of 191 P. 146 (Lewis County v. Aetna Accident & Liability Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lewis County v. Aetna Accident & Liability Co., 191 P. 146, 111 Wash. 333, 1920 Wash. LEXIS 636 (Wash. 1920).

Opinion

Bridges, J.

This is a suit on a road contractor’s bond to recover the value of certain cement furnished by Lewis county to the contractor.

In April, 1916, the respondent, Lewis county, entered into a contract with T. H. Cochran & Sons whereby the latter agreed to build a certain county road for $15,950. All cement to be used by the contractor was to be purchased from the county at $1.56 per barrel. With reference to payment therefor, the contract provided that, “payments for the cement to the county shall be made not later than the 10th day of the month following the month in which any cement was ordered. Payment for the cement may be made by check to Lewis county, or by the county withholding an amount equal to the price of the cement from the monthly esti[334]*334mates.” The contract further provided for monthly-payments not to exceed seventy-five per cent of the amount due the contractor for the previous month. It was further provided that,

“Final payment for said work shall be made within thirty (30) days after the entire work has been completed and accepted . . '. provided, that before the making of such final payment, the contractor shall show to the satisfaction of the board [of county commissioners] that all just dues, debts of laborers, mechanics, materialmen and persons who have supplied such contractor or subcontractor with material or goods of any kind for such work, have been paid.”

The contractor gave a bond for the faithful performance of the contract, with the appellant, Aetna Accident & Liability Company, as surety. This bond was conditioned upon the contractor complying with the contract in all of its terms and paying “all laborers, mechanics, subcontractors and material-men, and all persons who shall supply such person or persons or subcontractors with materials, supplies and provisions for carrying on such work, all just dues, debts and demands incurred in the performance of such work. ’ ’

In the performance of this contract, the county sold to the contractor $4,073.88 worth of cement. The road was completed and accepted and all the contract price paid to the contractor by the county, but the latter has not received payment for its cement. The county had a judgment in the lower court against the surety. All the other parties to the action were either not served with process or were, by the trial court, dismissed out of the suit.

From month to month, as the work progressed, the contractor was paid seventy-five per cent of the amount he had earned during the previous month. The road [335]*335was completed and duly accepted on November 9,1916, and at that time tbe balance found due to tbe contractor was $7,949.64. A warrant for tbis amount was drawn in favor of the contractor. Previously, be bad assigned tbis warrant to tbe defendant Peninsular National Bank, of St. Johns, Oregon, who subsequently received tbe same from tbe county auditor and cashed it with tbe county treasurer. At all times tbe county and its officers knew that it bad not received any pay for tbe cement it bad furnished. In fact, tbe testimony shows that tbe county commissioners and tbe county auditor intended to refuse to deliver1 tbe warrant until tbe county bad been paid, but through some apparent mistake tbe warrant was delivered without such payment being made, and without tbe amount owing for the cement being deducted from tbe warrant. Appellant did not know, before tbe bringing of tbis suit, that tbe bill bad not been paid.

Tbis suit was brought more than two years after tbe delivery and payment of tbis warrant. Tbe only question before us is whether, under these facts, tbe county is entitled to recover of the appellant. We are satisfied that tbe learned trial court erred in giving judgment against tbe appellant. It is fundamental that tbe county can have no right to recover on tbe bond if it has itself breached the contract in any material respect. Tbis we think it did. Tbe contractor was obliged to purchase bis cement from tbe county, and the contract required that,

“Payments for tbe cement to tbe county shall be made not later than the 10th day of tbe month following tbe month in which any cement was ordered. Payment for tbe cement may be made by check to Lewis county, or by tbe county withholding an amount equal to tbe price of cement from the monthly estimates of tbe engineer in charge. ”

[336]*336A fair construction of this provision of the contract required the county to get its pay monthly, either by receiving the cheek of the contractor or by deducting the amount from sums earned by the contractor. The county could not look to the contractor or to the surety at its option. The contract provided a way by which it could protect itself, and it was bound so to do. Indeed, the duty of the county was made the plainer by the actions of the parties themselves. After the work was completed, the county auditor wrote the contractor asking him to remit for the cement, and he answered, saying, “we wish you would retain from the amount due us for this improvement, the $4,073.88 for cement.”

The authorities are numerous in support of the proposition that, where the contract requires the county, or other builder, to apply money in its hands belonging to the contractor to the payment of claims or demands against the latter incurred in the performance of the work, it may not pay out to the contractor the balance earned by him and look to the surety for the payment of claims which at all times it knew existed.

In the case of Greenville v. Ormand, 51 S. C. 121, 28 S. E. 147, the court said:

“The payment by the city of Greenville to the contractor of the whole amount due under the engineer’s estimate, including the ten per cent reserve, without deducting- the amount due the city for tools and dynamite, which, under the contract the city had the right .to do, was the giving up of a security for the debt sued on upon which the surety had the right to rely.”

In Kiessig v. Allspaugh, 91 Cal. 231, 27 Pac. 662, 13 L. R. A. 418, the contract for the construction of a building provided that the owner should retain one-fourth of the contract price until final settlement. After the building was completed and accepted, and [337]*337after lie knew there were outstanding claims for labor, the owner paid the contractor the balance of the contract price. He then paid the laborers’ claims and sought to hold the surety company therefor; The court said:

“The appellant, Lundeen, was a surety, and as money sufficient to satisfy all of the liens mentioned in the complaint was, or ought to have been, in the hands of the plaintiff:' at the time of his settlement with the contractors, he should have so applied it, instead of paying it to the contractors. This balance was to be retained in his hands as an additional security against liens upon the building, and in equity, he held the same also for the benefit of the sureties.”

In the case of Taylor v. Jeter, 23 Mo. 244, the court said:

“The contract duty of this builder was to furnish the materials and do the labor, and he failed in both respects when he allowed the building to be encumbered with these liens.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Puget Sound Bridge & Dredging Co. v. Jahn & Bressi
268 P. 169 (Washington Supreme Court, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
191 P. 146, 111 Wash. 333, 1920 Wash. LEXIS 636, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lewis-county-v-aetna-accident-liability-co-wash-1920.