Levingston Shipbuilding Co. v. Ailes

239 F. Supp. 775, 1965 U.S. Dist. LEXIS 7102
CourtDistrict Court, E.D. Texas
DecidedMarch 30, 1965
DocketCiv. A. No. 4915
StatusPublished
Cited by1 cases

This text of 239 F. Supp. 775 (Levingston Shipbuilding Co. v. Ailes) is published on Counsel Stack Legal Research, covering District Court, E.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Levingston Shipbuilding Co. v. Ailes, 239 F. Supp. 775, 1965 U.S. Dist. LEXIS 7102 (E.D. Tex. 1965).

Opinion

FISHER, District Judge.

This case involves the much publicized, proposed fixed span bridge which is to be constructed across the Sabine-Neches Waterway unless enjoined by court action.

The present bascule type bridge, in use for some 35 years, is considered to be inadequate for modern day use, and is extremely hazardous to navigation. Numerous vessels have collided with the present bridge and such accidents have become more frequent with the increase of waterway traffic in recent years. As the result of collisions, the present bridge has been rendered inoperative for extended periods of time, causing inconvenience, not only to navigation, but also to the vehicular traffic en route from the City of Port Arthur to a tract of land commonly called “Pleasure Island”, and a highway connecting with Cameron Parish, Louisiana. The Sabine-Neches Canal is too shallow and too narrow to adequately accommodate the heavy water traffic at the present time, and unless remedied, the situation will become a greater problem in the future. The Sabine-Neches Waterway project is intended to improve the navigability of the waterway while simultaneously providing a more convenient passageway for persons and vehicles to and from the City of Port Arthur and the Island as well as Cameron Parish, Louisiana.

There is no disagreement with the ultimate goal, that is, the “deepening” and “widening” of the canal, the argument is solely about the vertical clearance of the bridge to be constructed. The type of bridge which the Federal Government seeks to build in this case, is a fixed, non-suspension bridge of reinforced concrete to have a vertical clearance of 138 feet above mean low tide.

The Plaintiff, Levingston Shipbuilding Company, seeks to have the proposed fixed span bridge declared an unlawful obstruction of the Sabine-Neches Waterway to free navigation, and thus constituting a public nuisance; alternatively, Plaintiff seeks a writ of mandamus directing the Defendants to provide adequate clearance for the navigation of said waterway and to preserve and to protect Plaintiff’s established and potential use of said waterway for all purposes.

The Defendants filed a Motion to Dismiss, contending that the question of obstructing a waterway by building a bridge, is solely and exclusively within the power of Congress, and is not a subject matter over which this Court has jurisdiction; further, that Plaintiff has [777]*777no cause of action or standing in Court, and that Defendants are acting within the scope of their authority and are agents of the United States Government and that this cause of action is against the Government without its consent.

The Motion to Dismiss was carried along with the trial on the merits and the attorneys for the respective parties were given until February 12, 1965, to file briefs in support of their respective positions.

Under the Commerce Clause of the Constitution, Article I, section 8, clause 3, Congress is given plenary power over the navigable waters of the United States and by virtue of this authority, the courts have held that Congress also has the power to authorize the construction of bridges across navigable waters. Newport and Cincinnati Bridge Co. v. United States, 105 U.S. 470, 26 L.Ed. 1143 (1881), Stockton v. Baltimore & N. Y. R. Co., C.C., 32 F. 9 (App.Dism., 140 U.S. 699, 11 S.Ct. 1028, 35 L.Ed. 603) (1887), United States v. Ingram, 203 F.2d 91 (8th Cir. 1953). Pursuant to this power, Congress enacted the River and Harbor Act of 1962 (87th Congress, 2nd Session (76 Stat. 1173), which provided in part as follows:

“TITLE I — RIVERS AND HARBORS
“Sec. 101. That the following works of improvement of rivers and harbors and other waterways for navigation, flood control, and other purposes are hereby adopted and authorized to be prosecuted under the direction of the Secretary of the Army and supervision of the Chief of Engineers, in accordance with the plans and subject to the conditions recommended by the Chief of Engineers in the respective reports hereinafter designated: Provided, That the provisions of Section 1 of the River and Harbor Act approved March 2,1945 (Public Law Numbered 14, Seventy-ninth Congress, first session), shall govern with respect to projects authorized in this title; and the procedures therein set forth with respect to plans, proposals, or reports for works of improvement for navigation or flood control and for irrigation and purposes incidental thereto, shall apply as if herein set forth in full:
“NAVIGATION
“Sabine-Neehes Waterway, Texas: House Document Numbered 553, Eighty-seventh Congress, at an estimated cost of $20,830,000.”

The specific Sabine-Neehes Waterway project referred to in the River and Harbor Act of 1962, is set forth in the House Document Number 553, (Pages 14 to 55) as the recommendations of the District Engineers, in part as follows:

“The channel from Port Arthur to Beaumont to have a depth of 40 feet and a width of 400 feet. The existing double-leaf bascule highway bridge crossing the Sabine-Neehes Canal at Port Arthur should be removed and replaced by one with horizontal clearance at least equal to the channel width and vertical clearance of at least 138 feet above mean low tide.” (Page 53.)

These recommendations were properly approved by the Board of Engineers and the Chief of Engineers and thus became a part of the Statute.1

The River and Harbor Act of 1962 specifies further that Section 1 of the River and Harbor Act of 1945, 59 Stat. 10, “ * * * shall govern with respect to projects authorized in this Title; and * * * shall apply as if herein set forth in full.” The incorporated provisions provide that:

“ * * * it is hereby declared to be the policy of the Congress * * * to preserve and protect to the fullest [778]*778possible extent established potential uses, for all purposes, of the waters of the Nation’s rivers * * * and to limit the authorization and construction of navigation works to those in which a substantial benefit to navigation will be realized therefrom and which can be operated consistently with appropriate and economic use for the waters of such rivers by other users.”

Plaintiff’s theory briefly is that the said proposed fixed span bridge is both unlawful and obstructive. It is unlawful because the River and Harbor Act of 1962, with the enabling House Document Number 553, does not authorize the type of bridge which Defendants are attempting to construct, therefore, the Defendants are exceeding and acting beyond the scope of their lawful authority, and that Plaintiff is entitled to judicial relief.2 *****8 Plaintiff argues that the Defendants are only authorized to build a bridge with adequate

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
239 F. Supp. 775, 1965 U.S. Dist. LEXIS 7102, Counsel Stack Legal Research, https://law.counselstack.com/opinion/levingston-shipbuilding-co-v-ailes-txed-1965.