Levi v. M. Schwartz & Bro.

34 La. 209
CourtSupreme Court of Louisiana
DecidedMarch 15, 1882
DocketNo. 7417
StatusPublished

This text of 34 La. 209 (Levi v. M. Schwartz & Bro.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Levi v. M. Schwartz & Bro., 34 La. 209 (La. 1882).

Opinion

The opinion of the Conrt was delivered by

Fenner, J.

This action is based upon a contract entered into between plaintiff and defendants, on August 26th, 1876, the essential terms and conditions of which are the following:

The defendants bound and obligated themselves to build and erect, on brick foundations, for plaintiff, in the main yard of the Natchez Cotton Press, in this city, a 73 inch cylinder Tyler Press,” according to certain specifications, and of certain quality of materials and workmanship, named in the contract, the same to be constructed to the entire satisfaction of said Levi A. Levy, Jr.;” and to be so completed and finished, and in good running- order and ready to be delivered to said Levy, on or before the 11th of October, 1876; in default whereof, it was stipulated, that the defendants should forfeit and pay to Levy, fifty dollars per day for each and every day that the said press and appurtenances shall remain unfinished and undelivered, which sum he shall be allowed to retain as liquidated damages out of any moneys that may be due ox owing-by him, for or on account of this contract.”

It cannot, as we conceive, admit of dispute, that under a proper construction of this contract, the obligation of defendants was to construct and have ready to be delivered at the date stipulated, not simply a [212]*212press, not any press, but a press constructed according to the terms of the contract, and to the satisfaction of plaintiff; and that the delay, for which damages were stipulated, might have resulted, not only from the total inexecution of the contract, by failure to construct or complete, within the term any press whatever, but equally from a partial inexecution, by constructing and delivering a press which did not comply with the contract.

The original petition of plaintiff set forth the provisions of the contract, and simply averred, “ that the defendants heroin failed to comply with the terms and conditions of their contract, in this: that they failed to deliver the press completed, on the date fixed by said contract; that he did not receive or accept said press on said day; that said press was delivered and accepted by him, as finished and completed, only on the 6th of July, 1877; and that the negligence and delay of defendants in complying with the terms and conditions of their contract, has caused petitioner damage to an amount equal to, if not exceeding, that fixed by the contract; ” and he claims the stipulated damages for the whole term, from October 11th, 1876, to July 6th, 1877. It is manifest that the terms of this petition are broad enough to cover delay caused either by non-execution, or by defective and imperfect execution of the work; and, while objectionably vague, it strongly suggests that the complaint is levelled at the delay from the latter cause.

We therefore think there was no inconsistency or change of cause of action in the supplemental petition, wherein plaintiff alleges, substantially, that defendants did construct and present for delivery, a press, claimed by defendants to be such as was required by tlie contract, which, under the exigencies of his business, he took charge of and attempted to operate, under the supervision and with the assistance of defendants, but which lie never accepted as satisfactory, or as in compliance with the contract, until July 6th, 1877. He avers sundry imperfections and defects of workmanship and material, in violation of the contract; that the press worked imperfectly and unsatisfactorily; that it frequently broke down and required repairs, during the iiorformanoe of which its operation was often entirely suspended for considerable periods.

This state of affairs continued until June, 1877, when, after numerous repairs had been made by defendants, the question as to whether the press was then in acceptable condition was, by agreement of parties, referred to Mr. Tilton, as expert and arbitrator, who reported, recommending certain alterations in, and additions to, the press, which when done, “would, in Ms opinion, put the press in acceptable condition.”

‘ Whereupon, defendants executed the required work, and on the 6th [213]*213«lay of July, 1877, tlie press was, for tlie first time, accepted by plaintiff as satisfactory, and in compliance with the contract.

The supplemental petition sets forth, with great particularity, the various defects in the construction of the press, and the various accidents, imperfections and. detentions resulting therefrom, and alleged numerous items of actual and special damages resulting to him, far ■exceeding in amount the stipulated damages for the entire term; but it renewed the prayer of the original petition, which was for the stipulated damages only. These allegations were entirely appropriate to the relief, as conducive to the allowance of tlie entire penalty, under the discretion vested in the Judge by Article 2127, C. C., which provides, that “ the penalty hiay be modified by the Judge, when the principal obligation has been pafthj executed.” The exception to the supplemental petition, on the ground of inconsistency and change of «original cause of action, was, therefore, properly overruled.

The defendants, however, object to the maintenance of the action, on the ground that there was neither allegation nor proof that defendants had been put in default, both of which, they contend, are essential in such a suit.

The contract sued on is an obligation with a penal clause, the latter being “ a secondary obligation entered into for the purpose of enforcing the performance of the primary obligation.” C. C. 2117.

The penal clause is the compensation for the damages which the creditor sustains by the non-execution of the principal obligation.” C. C. 2125.

“ Whether the principal obligation contain, or do not contain, a term in which it is to be fulfilled, the penalty is forfeited only when he who has obligated himself * * is in default.” '

Under these textual provisions, in actions to enforce penal clauses, two inquiries must be made, viz: 1. Has the obligor failed to perform tlie primary or principal obligation ? 2. Is he in default ?

As to the first question, if the evidence otherwise left it in doubt, which it does not, the agreement to arbitrate the report of the arbitrator selected jointly by plaintiff and defendants, and the action had on his report would conclusively settle it. ' They establish beyond question, that up to that time, the press had not been accepted by plaintiff, and was not “ in acceptable condition,” according to the requirements of the contract.

As to the second question, we consider that the construction upon plaintiff’s premises and delivery to him of a press constructed unskilfully and not in accordance with the contract, was an active violation of the contract, which ipso facto placed defendants in default, without the necessity of any formal putting in mora.

[214]*214Such has been the uniform jurisprudence of this Court, notwithstanding the broad terms of Art. 1931, C. C. Lobdell vs. Parker, 3 La. 331; Martin vs. Pollard, 9 La. 174; Cable vs. Leeds, 6 A. 293; Nicholson vs. Desobry, 14 A. 81; Hill vs. Penny, 15 A. 212.

It is a mere play upon words to say that in an action for- delay in delivery, plaintiff claims damages for delivery of imperfect and insufficient work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Benjamin v. Hillard
64 U.S. 149 (Supreme Court, 1860)
Smith v. . Brady
17 N.Y. 173 (New York Court of Appeals, 1858)
Lobdell v. Parker
3 La. 328 (Supreme Court of Louisiana, 1832)
Morton v. Pollard
9 La. 174 (Supreme Court of Louisiana, 1836)
Stewart v. Fulton
31 Mo. 59 (Supreme Court of Missouri, 1860)

Cite This Page — Counsel Stack

Bluebook (online)
34 La. 209, Counsel Stack Legal Research, https://law.counselstack.com/opinion/levi-v-m-schwartz-bro-la-1882.