Levesque Builders, Inc. v. Hoerle

717 A.2d 252, 49 Conn. App. 751, 1998 Conn. App. LEXIS 338
CourtConnecticut Appellate Court
DecidedAugust 11, 1998
DocketAC 16530
StatusPublished
Cited by14 cases

This text of 717 A.2d 252 (Levesque Builders, Inc. v. Hoerle) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Levesque Builders, Inc. v. Hoerle, 717 A.2d 252, 49 Conn. App. 751, 1998 Conn. App. LEXIS 338 (Colo. Ct. App. 1998).

Opinion

Opinion

SCHALLER, J.

The defendant appeals from the judgment of the trial court awarding damages to the plaintiff for the defendant’s breach of contract between the parties for the sale of real property. The defendant claims that the trial court improperly (1) determined that the contract was enforceable, (2) determined that the contract language satisfied the statute of frauds, (3) awarded attorney’s fees to the plaintiff under the Connecticut Unfair Trade Practices Act (CUTPA), General Statutes § 42-110a et seq.,1 (4) denied the defendant’s motion in limine and (5) denied the defendant’s motion for a mistrial. We affirm the judgment of the trial court in part, and set aside the judgment with respect to the award of attorney’s fees.

The following facts are relevant to the resolution of this dispute. In May, 1991, the parties signed a contract that provided that the defendant would sell a thirty-six acre parcel and two building lots in New Hartford to the plaintiff for $110,000. The plaintiff paid a deposit [753]*753of $1000 and received a copy of the September, 1990 map referenced in the contract. The plaintiff was told that the thirty-six acre parcel included all of the property located to the right of a red line drawn on the map.

In January, 1993, the plaintiff, with permission from the defendant, arranged for the sale of one of the building lots to a third party. The defendant was paid $45,000, thus reducing the amount owed by the plaintiff to $64,000 for the remaining lot and the thirty-six acre parcel. In February, 1993, the defendant asked the plaintiff to sign a second contract, which allegedly contained only minor changes from the original contract, and which acknowledged the sale of the lot. The map referenced in this second contract, however, was different from that referenced in the original contract. The plaintiff never received a copy of the new map, and the trial court determined that the map did not exist. The plaintiff signed this second contract, assuming that it would be purchasing the same thirty-six acres referred to in the September, 1990 map.

In the spring of 1993, the plaintiff purchased the remaining lot from the defendant for $35,000, leaving a balance of $29,000 owing on the thirty-six acre parcel. In September, 1993, the plaintiff purchased a third lot from the defendant under a separate contract. At that time, the defendant indicated that the plaintiff could close on the thirty-six acre parcel in December, 1993. In January, 1994, however, the plaintiff was informed that the defendant did not intend to convey the parcel, and that he was claiming that there was an ambiguity in the description of the property. The defendant, meanwhile, had begun developing the parcel in April, 1993, and had mortgaged the property to Shawmut Bank in April, 1994, which mortgage was being foreclosed at the time of trial.

On August 17, 1994, the plaintiff brought a complaint in four counts, seeking specific performance and money [754]*754damages for breach of contract, and alleging fraudulent or negligent representation and a violation of CUTPA. The defendant filed a special defense, claiming that the contract was unenforceable because it failed to comply with General Statutes § 52-550, the statute of frauds.2 He also filed a counterclaim, alleging that the plaintiff brought the action without probable cause and with malicious intent, and alleging a violation of CUTPA. A trial to the court was held on the matter for six days during the period of June 6 through July 6, 1996. On October 9,1996, the trial court released a thirteen page memorandum of decision and an order that judgment enter for the plaintiff in the amount of $151,000 for damages on the contract and $2500 in attorney’s fees, plus costs. This appeal by the defendant followed.

I

The defendant’s first claim is that the trial court improperly determined that an enforceable contract existed. We are not persuaded.

In its memorandum of decision, the trial court found that “[t]here is no question that the parties agreed that the plaintiff would purchase and the defendant would sell to [it] the two lots plus 36 [plus or minus] acres for the sum of $110,000 and that the plaintiff did in fact pay to the defendant a down payment of $1000, plus $80,000 for the two lots.” The defendant, however, claims that no contract existed because there was no meeting of the minds between the parties.

“Whether a contract exists is a question of fact for the court to determine. ” (Internal quotation marks omitted.) Harris Calorific Sales Co. v. Manifold Systems, [755]*755Inc., 18 Conn. App. 559, 563, 559 A.2d 241 (1989). “It is not within the power of this court to find facts or draw conclusions from primary facts found by the trial court. As an appellate court, we review the trial court’s factual findings to ensure that they could have been found legally, logically and reasonably.” (Internal quotation marks omitted.) Lembo v. Schlesinger, 15 Conn. App. 150, 154, 543 A.2d 780 (1988). Thus, the trial court’s factual determination that a contract existed must stand unless we conclude that it was clearly erroneous. See Buddenhagen v. Luque, 10 Conn. App. 41, 44, 521 A.2d 221 (1987).

“Appellate review under the clearly erroneous standard is a two-pronged inquiry: [W]e first determine whether there is evidence to support the finding. If not, the finding is clearly erroneous. Even if there is evidence to support it, however, a finding is clearly erroneous if in view of the evidence and pleadings in the whole record [this court] is left with the definite and firm conviction that a mistake has been committed.” (Internal quotation marks omitted.) Nelson v. Nelson, 13 Conn. App. 355, 359, 536 A.2d 985 (1988).

In the present case, the trial court found that an enforceable contract existed between the parties. The trial court based its holding on careful consideration of the written contracts, the maps referenced therein, surveys prepared by the parties, and the testimony of the parties and their expert witnesses. In light of the evidence and the pleadings in the record as a whole, we cannot say that the trial court’s finding that the parties intended that there be a sale of the thirty-six acre parcel and, therefore, that an enforceable contract existed, was clearly erroneous.

II

The defendant’s second claim is that the trial court improperly determined that the contract language satisfied the statute of frauds under § 52-550. Specifically, [756]*756the defendant asserts that the description of the disputed parcel in the contract is not sufficiently specific. We disagree.

We first consider whether the plaintiffs part performance of the contract removes the case from the purview of the statute of frauds. “The statute of frauds requires contracts for the conveyance of realty to be in writing. . . . We have repeatedly recognized that a contract is enforceable, despite the statute, when, subsequent to the making of the contract, there has been conduct that amounts to part performance. . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

T & M Building Co. v. Hastings
194 Conn. App. 532 (Connecticut Appellate Court, 2019)
Errichetti v. Botoff
196 A.3d 1199 (Connecticut Appellate Court, 2018)
Grovenburg v. Rustle Meadow Associates, LLC
165 A.3d 193 (Connecticut Appellate Court, 2017)
City of New Haven v. Tuchmann
890 A.2d 664 (Connecticut Appellate Court, 2006)
Resurreccion v. Normandy Heights, LLC
820 A.2d 1116 (Connecticut Appellate Court, 2003)
Guillette v. McAlpine, No. Cv 02 0068940 (Mar. 24, 2003)
2003 Conn. Super. Ct. 4140 (Connecticut Superior Court, 2003)
Santangelo v. Carini, No. Cv 00 74488 S (Oct. 8, 2002)
2002 Conn. Super. Ct. 12901 (Connecticut Superior Court, 2002)
Tulip Construction, Inc. v. Dilorenzo, No. Cv00-0083389 (Aug. 14, 2002)
2002 Conn. Super. Ct. 10204 (Connecticut Superior Court, 2002)
State v. Lambert
799 A.2d 335 (Connecticut Appellate Court, 2002)
Gurski v. Town of Brookfield, No. Cv99-033 76 10 S (Nov. 23, 2001)
2001 Conn. Super. Ct. 15941-kd (Connecticut Superior Court, 2001)
Margulis v. Lenhart, No. Cv00 0178130 S (Nov. 14, 2000)
2000 Conn. Super. Ct. 13866 (Connecticut Superior Court, 2000)
Pheasant Chase Associates v. Pestretto, No. Cv00-0595819s (Aug. 9, 2000)
2000 Conn. Super. Ct. 10773-g (Connecticut Superior Court, 2000)
Pheasant Chase Associates v. Pestretto, No. Cv-00-0595819-S (Jul. 31, 2000)
2000 Conn. Super. Ct. 9374-k (Connecticut Superior Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
717 A.2d 252, 49 Conn. App. 751, 1998 Conn. App. LEXIS 338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/levesque-builders-inc-v-hoerle-connappct-1998.