Levco Construction Corp. v. State

43 A.D.2d 759, 350 N.Y.S.2d 219, 1973 N.Y. App. Div. LEXIS 2895
CourtAppellate Division of the Supreme Court of the State of New York
DecidedDecember 13, 1973
DocketClaim No. 49440
StatusPublished
Cited by3 cases

This text of 43 A.D.2d 759 (Levco Construction Corp. v. State) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Levco Construction Corp. v. State, 43 A.D.2d 759, 350 N.Y.S.2d 219, 1973 N.Y. App. Div. LEXIS 2895 (N.Y. Ct. App. 1973).

Opinion

Cross appeals from a judgment in favor of claimant, entered January 26, 1972, upon a decision of the Court of Claims. On November 10, 1964, the -State of New York issued an invitation for bids for the construction portion -of modernization work on the Alfred E. Smith Office Building in Albany, New York. The work encompassed by this invitation involved the replacement of a heating system and the installation of air conditioning in the building. The bidding for this work was submitted under two alternative proposals. Proposal No. 1 included all of the work contained in the specifications and/or on the drawings. Proposal No. 2 eliminated certain portions of the work contained in the specifications. Because some of the original language of Proposal No. 2 was thought to be unclear, Proposal No. 2 was amended by Addendum No. 5 issued December 14, 1964. On March 5, 1965, claimant and the State entered into a contract based on claimant’s bid under Proposal No. 2. Claimant commenced work on the project on April 1, 1965. The trial court awarded claimant damages in the sum of $24,155,91. The trial court sustained claimant’s causes of action numbers 5, 6, 8, 9, 13, 17 and 18, but dismissed causes of action numbers 2, 3, 7, 10, 11, 12, 14, 15, 16 and 19. Claimant appeals from this judgment of the trial court, contending that causes of action numbers 2, 3, 12, [760]*76014, 15 and 16 were erroneously dismissed. The State cross-appeals, contending that claimant’s recovery in action numbers 9 and 13 was improper. The present appeal raises five issues concerning the construction of the contract between the claimant and the State. We note at the outset that the court may not, under the guise of interpretation, make a new contract for the parties or change the words of a written contract so as to make it express the real intention of the parties if to do so would contradict the clearly expressed language of the contract (Bodolitz v. Neptune Paper Prods., 22 N Y 2d 383). Circumstances extrinsic to the agreement will not be considered when the intention of the parties can be gathered from the .instrument itself (West, Weir <& Bartel v. Garter Paint Go., 25 N Y 2d 535). The first issue raised on this appeal is whether the trial court erred in dismissing claimant’s “ Second ” and “ Third ” causes of action. In its second cause of action, claimant alleged that the State breached the contract by requiring claimant to install new ceilings in the center core of the office building. In its third cause of action, claimant alleged that the State breached the contract by requiring claimant to remove existing ceilings and ceiling materials from the center core and wings of the office building. Both of these two causes of action, which constituted the major part of the claim (seeking damages in the sum of $120,475), were based on the conflict between the claimant’s and the Stage’s understanding of the scope of work encompassed by alternate Proposal No. 2. As originally drafted, Proposal Nos. 1 and 2 read as follows: “Alternate Proposals Separate proposals will be required for work of this Contract as follows: Proposal No. 1 — If the Contract is awarded upon the basis of Proposal No. 1, it shall include all work specified and/or shown on the drawings. Proposal No. 2 — If the Contract is awarded upon the basis of Proposal No. 2, it shall include all work specified and/or shown on the drawings except toilet rooms, first floor, new ceilings and pipe and duet closures in the entire two wings indicated as Phase II, Stage I, and the entire Tower indicated as Phase II, Stage II on Drawing 64/254 shall be omitted.” Subsequently, pursuant to Addendum No. 5 dated December 14, 1964, the wording of Proposal No. 2 was changed to read as follows: “Alternate Proposals Change Proposal No. 2 to read as follows: Proposal No. 2 — If the contract is awarded upon the basis of Proposal No. 2, it shall include all work specified and/or shown on the drawings except toilet rooms on the first floor, new ceilings and pipe and duet closures in the entire two-wings indicated as Phase II, 'Stage I and the entire tower indicated as Phase II, Stage II on drawing 64/254 shall be omitted.” The singular purpose of this change in wording was to clarify any ambiguity which might exist as to the work excluded under Proposal No. 2, specifically the work involving the toilet rooms. Instead of a comma after “rooms”, the words “on the” were added between “ rooms ” and “ first ” to plainly indicate that the “ toilet rooms on the first floor ”, and not toilet rooms ” and the “ first floor ”, were not included under Proposal No. 2. No other change was made in Proposal.No. 2. Claimant contends that all the work on new ceilings throughout the entire building was excluded from the contract under Proposal No. 2. The trial court found that the only new ceilings eliminated under Proposal No. 2, by clear and unambiguous language, were the new ceilings in the wings. We agree. The work excepted by Proposal No. 2 is plainly comprised of three sections: the toilet rooms on the first floor, new ceilings and pipe and duct closures in the entire two wings, and the entire tower. Claimant contends that the word “ and ” between new ceilings ” and “ pipe ” in this clause was used by the draftsman of Proposal No. 2 in a connective as [761]*761well as in a separative sense, with the resulting ambiguity compounded by careless punctuation. In our view, however, the presence or absence of a comma after “new ceilings” is integral to a determination of whether or not “new ceilings” was modified by “in the entire two wings”, and we therefore feel that the trial court was correct in concluding that the absence of a comma was not unintentional so as to create an ambiguity. Since, therefore, the language of the contract could not be found to be ambiguous, the trial court was correct in not considering the extrinsic evidence offered by claimant with regard to the interpretation of Proposal No. 2. The trial court’s decision dismissing claimant’s second and third causes of action should therefore be affirmed. The second issue raised on this appeal is whether the trial court erred in dismissing claimant’s “Twelfth” cause of action. In this cause of action, claimant sought to recover damages in the amount of $1,981.93, resulting from the State’s allegedly unwarranted refusal to permit claimant to use gypsum blocks in lieu of hollow tile or concrete blocks in the mechanical equipment rooms. Claimant based this cause of action on paragraph 8 of section 10 of the State Architect's Standard Specifications, which provides as follows: “8. Gypsum Blocks, conforming to the requirements of A.S.T.M. Specification C-52-41, may be used in lieu of hollow tile or concrete blocks except in the following locations: (a) In basements, (b) In shower rooms, (e) Back of tile wainscots or tile base, (d) Back of cement plaster, lime plaster cement base or terrazzo base, (e) Where load bearing blocks are specified.” Since mechanical equipment rooms are not listed as an exception in the above paragraph, claimant argued that he should have been permitted to use gypsum blocks in lieu of hollow concrete blocks in those rooms. The trial court rejected this argument on the basis of another paragraph in the same section of the standard specifications. Paragraph 1 of section 10 of the State Architect's Standard ’Specifications provides: “1. Option.— Hollow Blocks may be hollow tile or hollow concrete except only concrete blocks shall be used where blocks are exposed (not furred or plastered).” The trial court held that gypsum blocks could not be used here because they would be exposed. In our view, the trial court’s interpretation fails to harmonize these provisions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Topps Chewing Gum, Inc. v. Imperial Toy Corp.
686 F. Supp. 402 (E.D. New York, 1988)
Dobbins v. Dobbins
59 A.D.2d 548 (Appellate Division of the Supreme Court of New York, 1977)
Cities Service Company v. Gardinier, Inc.
344 A.2d 254 (Superior Court of Delaware, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
43 A.D.2d 759, 350 N.Y.S.2d 219, 1973 N.Y. App. Div. LEXIS 2895, Counsel Stack Legal Research, https://law.counselstack.com/opinion/levco-construction-corp-v-state-nyappdiv-1973.