Leslie v. Glass

15 F. Cas. 389
CourtU.S. Circuit Court for the District of Maryland
DecidedApril 15, 1840
StatusPublished

This text of 15 F. Cas. 389 (Leslie v. Glass) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Leslie v. Glass, 15 F. Cas. 389 (circtdmd 1840).

Opinion

TANEY, Circuit Justice.

These two cases have come before the circuit court upon appeals from the district court.' They arose upon libels filed to recover money, which the respective libellants alleged to be due to them for work and labor done upon the ship Scotia, or for materials found for her construction. at the request of Leslie. The district court, in each of the cases, decreed in favor of the libellants, and from these decrees, Leslie has appealed to this court. The causes depend upon the same principles, and the decision of one must determine the other.

The case first in order is that of Leslie v. Glass, in which the appellee obtained a decree in the district court for the sum of $757 12, with interest thereon from the 25th day of February, 1839, together with the costs of suit.

It appeared from the testimony, that on the 23d of May, 1838, at the city of Baltimore, a contract in writing was made between the said Leslie and a certain W. F. Smith, master shipwright of the said city, whereby Smith, for the consideration therein mentioned, engaged to build for Leslie, a ship of the dimensions and kind particularly described in the said agreement. In consideration whereof, Leslie agreed to pay Smith $38 per ton, carpenters’ measure: $1,000 on the day of the date of the contract; $1,500 on the first of June following, and $2,000 on the first of each succeeding month, till the 1st of November; and the balance in two notes at four and six months from the delivery of the certificate by Smith and Leslie; the ship to be finished on or before the 1st of December, 1838.

The evidence shows, that although Smith had built smaller vessels, yet he had never built a ship, when he undertook the Scotia; and Leslie was aware of that fact. The usual price for a vessel of the description of the Scotia, at the time of the contract was about - dollars per ton, and the sum agreed on by Smith of $38 per ton, was below the usual price. He did not, it seems, engage in the work with an expectation of making money by it, but he hoped to be able to save himself, and his main object was, to obtain for himself the character of a first-rate ship builder, by constructing this ship of the best materials and in a superior manner. Leslie appears to have been sensible of Smith’s object, and that the price mentioned in the agreement was a low one, and at the time the written contract was signed, he promised Smith, verbally, to pay him a half a dollar per ton more than the writing called for. The ship was built under the inspection of Leslie, and the work done in the best manner and of the best materials.

The libellant, Glass, was one of Smith’s sureties to Leslie for the fulfilment of his contract. Upon the face of the paper, it would seem, that he signed it after Spreekel-sen, the other surety; and Spreckelsen, as has been proved and admitted, signed as surety at the request of Leslie, in order that he might exercise an influence over Smith in [391]*391urging on the work, but under an express agreement on the part of Leslie, that he would in no event hold him liable as surety.

It appears also, that after the contract was signed, an alteration was made in the plan of the ship by Leslie, and assented to by Smith. She was made longer and deeper than the written contract called for, and her breadth of beam was not increased. This alteration was in some degree disadvantageous to Smith, and made the construction of the vessel somewhat more expensive in proportion to her tonnage, than the plan set forth in the written contract. The sureties do not appear to have been consulted in relation to this change of plan, nor to have assented to it.

The keel was laid soon after the contract was made; hut as early as July the 3d, the confidence of Leslie in the ability of Smith to fulfil his agreement appears to nave been shaken, and being, on that day, called on by Smith for an advance of money, beyond the amount he was entitled to under the contract, he took from him the following assignment: “Received, Baltimore, July 3d, 1838, from Robert Leslie, the sum of one thousand dollars, on account of new snip building by me, as per contract; and I hereby assign over to Robert Leslie, all right and title to said ship, as she advances in construction, together with all materials collected and to be collected for the same. William F. Smith.”

This assignment was kept secret, and was not known to the sureties of Smith, or any one employed in working upon the ship, or in furnishing materials for her, until Smith stopped payment, as hereinafter mentioned. The work went on, after this assignment, as it did before, and Leslie continued to advance money, from time to time, in order to enable Smith to carry it on. The ship was launched about the 1st of January, which was one month later than the time stipulated in the contract; she was finished four or five weeks after the launch, and measured about five hundred and forty tons.

The difficulties of Smith continued to increase from the time of the assignment above-mentioned; but he entertained hopes of being able to complete the ship, and to pay those who had credited him, until about the time of the launch, relying, as he states, upon the verbal promise of Leslie, that he should not lose by this contract. But about the time last, mentioned, a note, which he had given for materials furnished for the vessel, fell due, which he was unable to take up, and applied to Leslie for assistance; Leslie, however, refused to advance any further, and Smith thereupon was obliged to stop payment, because insolvent, and was unable to go on with the work; and much more money was, at that time, due to the mechanics and material men, than was due from Leslie under his written contract

The ship was launched about the 1st of January, and the situation of Smith having then become public, those who had worked upon the ship, or furnished materials for her, and whose bills were yet unpaid, became uneasy and applied to Leslie upon the subject. He assured those who called on him that he would pay all just bills against the ship;' and in various conversations with other persons who were not interested in their claims, he repeatedly declared that all just bills against the ship should be paid, and requested one of those persons to make the statement known, and to defend him, if he heard any report, imputing to him a contrary intention. In a conversation with a clerk of Smith, the day before the ship was launched, he said, that he had agreed to pay all the bills against the ship, but he would pay nothing more until the ship was launcheu. It appeared from the evidence, that Smith had applied all the money he had received from Leslie toward the construction of the ship and the purchase of materials for her.

The libellant Glass was employed by Smith to do the outside joiners’ work. It was all done after the assignment hereinbefore mentioned, according to the testimony, and a small portion of it, after the ship was launched, and after the assurances above-mentioned had been given by Leslie, and had become publicly known among the persons engaged upon the ship About the month of January, after the ship had been launched, certain bills receivable were transferred to Glass by Smith; but they do not appear to have been on account of the present claim, although there is some controversy on that point; the bills could not De collected, and were returned by Glass to Smith.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
15 F. Cas. 389, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leslie-v-glass-circtdmd-1840.