Lesher v. United States Fidelity & Guaranty Co.

144 Ill. App. 632, 1908 Ill. App. LEXIS 515
CourtAppellate Court of Illinois
DecidedNovember 12, 1908
DocketGen. No. 14,011
StatusPublished
Cited by3 cases

This text of 144 Ill. App. 632 (Lesher v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lesher v. United States Fidelity & Guaranty Co., 144 Ill. App. 632, 1908 Ill. App. LEXIS 515 (Ill. Ct. App. 1908).

Opinion

Mr. Presiding Justice Adams

delivered the opinion of the court.

November 25, 1903, the appellant, Jacob H. Lesher, brought suit against the appellee, the United States Fidelity & Guaranty Co. and Henry W. Schlueter. May 6, 1906, the suit, on appellant’s motion, was dismissed as to Schlueter. The suit is on a bond of date August 25, 1902, in the penalty of $50,000, executed by appellee and Schlueter to appellant. One of the conditions of the bond is as follows:

“Third. That in no event shall the surety be liable for a greater sum than the penalty of this bond, or subject to any suit, action or other proceeding thereon that is instituted later than the 15th day of March, A. D. 1903”.

In an amended declaration, filed May 6, 1905, there is set out, in words and figures, next after the formal commencement, a contract, dated August 22, 1905, between Henry W. Schlueter and J. H. Lesher, by which Schlueter agrees to construct a building and provide all material and work for the same, according to certain specifications and plans shown on drawings prepared by certain named architects. Article 6 of the agreement provides: “The contractor shall complete the several portions and the whole of the work comprehended in this agreement by and at the time hereinafter stated, the entire work of this contract to be completed on or before December fifteenth, 1902 ’ ’. The bond, a condition, of which is above quoted, is then set out, followed by assignments of breaches of the conditions of the bond, one of which is as follows:

“And for assigning a further breach of the condition of said writing obligatory, plaintiff says that by the contract with the plaintiff above herein described the said Schlueter covenanted and agreed that the entire work described in the said contract should be completed on or before December 15th, 1902; but the plaintiff avers that the said Schlueter did not complete the said building within the said time, nor for a long time thereafter, to-wit, six months, and that due notice of such default was given to the defendant at the time and in the manner required by said writing obligatory; that said building was an office and store building, for office and mercantile purposes, as shown in the plans and specifications described in said contract, and this was well known to the said Schlueter and to the defendant herein; and it was well known to the said Schlueter and to this defendant that in case the said building should not be completed by the time aforesaid plaintiff would be deprived of a large amount of gains and profits which he would otherwise make as and for the rentals and rental value thereof during the time that would.be lost by such default; nevertheless, the said Schlueter did not nor would, although often requested, complete the said building at the time required by said contract, nor within the period last above mentioned, and that the rentals and rental value of the said property during the said period, which the plaintiff lost thereby, was very great, to-wit, the sum of ten thousand dollars ’ ’, etc.

The declaration, in the concluding part thereof, contains the following averments:

“And plaintiff further shows that the plaintiff on his part complied with all and singular the provisions and requirements of the said writing obligatory on his part to be kept and performed, excepting only that this present action by the plaintiff against the said defendant was not brought on or prior to March 15,1903; and in respect to said provision or requirement of the said writing obligatory the plaintiff avers that the said building which should by the terms of said contract have been completed by December 15th, 1902, was not in fact completed for a long time, to-wit, for the period of eleven months thereafter, and that on March 15th, 1903, the said building was in an uncompleted state and the said Schlueter was still engaged in the construction thereof and in laboring in and about the same with numerous employes and sub-contractors; and that it was not known to the plaintiff at the said date, and could not have been known at the said time nor until long afterwards, to-wit, eleven months, what injury, loss or damage, if any, would be sustained by the plaintiff by reason of said breach of contract, nor whether the said Schlueter would himself indemnify and save harmless the said plaintiff from any pecuniary loss resulting from such breach of the terms, covenants and conditions of said contract; and that the said loss or- damage could not have been known to the plaintiff until shortly before the time when he brought this present action; nor could the plaintiff, until the last work done or caused to be done by the said Sehlueter upon the said building had been completed, have known or in any way ascertained the amount which the defendant herein ought to pay the plaintiff by virtue of the covenants and provisions of the said instrument; nor could plaintiff by any means know or ascertain that the defendant herein would decline or refuse to make good, without suit, the amount of such loss or damage when ascertained; by reason whereof the plaintiff avers that the said provisions of said writing obligatory that action thereon should be brought by March 15th, 1903, was unreasonable and void; and that plaintiff was not in any way bound thereby.”

Appellee demurred to the declaration generally and specially, and the court, July 8, 1905, overruled the demurrer and ruled appellee to plead to the declaration within thirty days, which time was subsequently extended till September 30, 1905. September 25, 1905, appellee filed thirteen pleas. Appellant demurred generally and specially to the 1st, 3rd, 5th, 6th, 7th, 8th, 9th, 11th and 13th pleas. The 13th plea is as follows :

“And for a further plea in this behalf, the defendant says the plaintiff ought not to have his aforesaid action against it, the defendant, because it says that the plaintiff did not commence his said action on or before the 15th day of March, A. D. 1903, but, on the contrary thereof, commenced his said action on or about the 27th day of November, 1903, contrary to the terms and conditions of the said writing obligatory; and this the defendant is ready to verify; wherefore it prays judgment if the plaintiff ought to have his'aforesaid action, etc”.

The following causes of demurrer are assigned:

“The said thirteenth plea is not a sufficient plea to the said declaration, since it sets up and relies upon matters which are defenses of law alone”. The said thirteenth plea is not sufficient as a plea to the said declaration, since it sets up matters and things already adjudged and determined against the defendant by its demurrer to the plaintiff’s declaration”.

June 15, 1907, the court overruled appellant’s demurrer to appellee’s thirteenth plea; appellant elected to stand by its demurrer, and the court rendered judgment in favor of appellee for its costs, and appellant prayed and was allowed an appeal.

Appellant has assigned as error the overruling his demurrer to appellee’s thirteenth plea. Appellant’s counsel rely on the following proposition: •

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bowers v. Claxton
212 Ill. App. 609 (Appellate Court of Illinois, 1918)
Whelan v. Massachusetts Bonding & Insurance
205 Ill. App. 122 (Appellate Court of Illinois, 1917)
Brown v. Massachusetts Bonding & Insurance
176 Ill. App. 502 (Appellate Court of Illinois, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
144 Ill. App. 632, 1908 Ill. App. LEXIS 515, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lesher-v-united-states-fidelity-guaranty-co-illappct-1908.