Les Grumdahl Window & Siding LLC, A Minnesota Limited Liability Company v. Holly Brown, ...

Court of Appeals of Minnesota·Decided May 6, 2024·No. a231069·Published

Opinion

This opinion is nonprecedential except as provided by Minn. R. Civ. App. P. 136.01, subd. 1(c).

STATE OF MINNESOTA

IN COURT OF APPEALS

A23-1069

Les Grumdahl Window & Siding LLC, A Minnesota Limited Liability Company, Respondent,

vs.

Holly Brown,

Appellant,

Mortgage Electronic Registration Systems, Inc., Defendant.

Filed May 6, 2024

Affirmed

Slieter, Judge

St. Louis County District Court File No. 69DU-CV-22-211

Matthew H. Hanka, Thomas R. Witt, Fryberger Law Firm, Duluth, Minnesota (for respondent)

William D. Paul, William D. Paul Law Office, Duluth, Minnesota (for appellant)

Considered and decided by Schmidt, Presiding Judge; Slieter, Judge; and Klaphake, Judge. ∗

Retired judge of the Minnesota Court of Appeals, serving by appointment pursuant to Minn. Const. art. VI, § 10.

NONPRECEDENTIAL OPINION

SLIETER, Judge Following a court trial in this breach-of-contract and mechanic’s-lien-foreclosure action, appellant argues that the district court (1) erred in concluding that respondent-contractor complied with statutory prelien-notice requirements and (2) abused its discretion in denying appellant’s posttrial motions. Because the prelien notice was part of the parties’ written contract, and because the district court acted within its discretion in denying Brown’s posttrial motions, we affirm.

FACTS

Appellant Holly Brown retained respondent Les Grumdahl Window & Siding LLC, to remodel the exterior of her Duluth home. Disputes arose during performance of the work. Grumdahl ultimately filed a mechanic’s lien against the property and commenced this action for breach of contract and to enforce the mechanic’s lien. The following facts derive from the February 2023 court trial.

The parties’ written contract consists of several documents. The first document is a proposal which provided that Grumdahl would install siding and 13 windows. The second document is a prelien notice. The third, fourth, and fifth documents include agreements for additional work and a notice regarding paint and stain. According to the parties’ agreement, Brown was to provide one-third of the total project cost as a down payment, another third was due when work started, and the balance was due upon completion.

Brown made the down payment when accepting the proposal in June 2020. The parties agreed that Grumdahl would begin work the following year. In July 2021, Grumdahl sought the second payment, having begun work in June 2021. Brown gave Grumdahl a check but later canceled payment on the check. As a result, Grumdahl stopped work on the project.

In August 2021, the lien statement was publicly recorded against Brown’s property.

In January 2022, Grumdahl served Brown with a summons and complaint, which was filed in district court the following month. In April 2022, the district court issued a scheduling order directing discovery to be completed by November 1, 2022. Brown retained counsel in mid-November 2022, after discovery had closed. On February 6, 2023—the day before trial—Brown filed an answer and counterclaim. The district court stated that the “filing was far too late” and rejected it. The district court also rejected “about 400 pages of documents” provided by Brown on the same day, noting discovery was due about three months prior. However, the district court allowed Brown’s attorney to cross-examine Grumdahl’s witnesses and allowed Brown to testify.

After the court trial on February 7, 2023, and following posttrial briefing, the district court issued an order granting judgment in Grumdahl’s favor for breach-of-contract damages and mechanic’s-lien foreclosure. After the decision, Brown retained new counsel and filed two motions relevant to this appeal. In her posttrial motions, Brown sought to vacate judgment pursuant to Minn. R. Civ. P. 60.02 and, in the alternative, she sought a new trial pursuant to Minn. R. Civ. P. 59.01. The district court denied each.

Brown appeals.

DECISION

I. Because the district court’s finding that the prelien notice was included in the parties’ written contract is not clearly erroneous, it appropriately determined that Grumdahl complied with the statutory prelien-notice requirements.

Every person who contracts with an owner for the improvement of real property may have a mechanic’s lien upon the property they have been contracted to improve. Minn. Stat. § 514.01 (2022). However, “any written contract with the owner” must include prelien notice, and the contractor must “provide the owner with a copy of the written contract” containing the notice. Minn. Stat. § 514.011, subd. 1 (2022). If there is no written contract, prelien notice “must be prepared separately and delivered personally or by certified mail to the owner or the owner’s authorized agent within ten days after the work of improvement is agreed upon.” Id.

Brown states that, because it was provided in a separate document from the proposal, Grumdahl’s prelien notice was not included in the parties’ written contract. She argues that Grumdahl was, therefore, required to provide prelien notice by personal service or certified mail, which it failed to do.

The existence and terms of a contract are questions of fact reviewed for clear error.

Morrisette v. Harrison Int’l Corp., 486 N.W.2d 424, 427 (Minn. 1992) (stating that “the existence and terms of a contract are questions for the fact finder”). A district court’s factual findings will be reversed only if we are left with the definite and firm conviction that a mistake has been made. Gjovik v. Strope, 401 N.W.2d 664, 667 (Minn. 1987).

The district court found that the parties’ contract was comprised of a series of documents “entered into during the months of June to November 2020,” and it observed

that the prelien notice “is dated June 26, 2020, clearly within the time of contract formation.” The district court concluded that the prelien notice was part of the written contract, which was provided to Brown, and that Grumdahl satisfied the statutory requirements to proceed with foreclosure of the mechanic’s lien.

As an initial matter, Brown summarily states that the district court erred in determining that Grumdahl satisfied the statutory requirements to pursue a mechanic’s-lien claim. Brown does not, however, identify clear error in the district court’s finding that the parties’ contract was comprised of a series of documents, including the prelien notice. Waters v. Fiebelkorn, 13 N.W.2d 461, 464-65 (Minn. 1944) (“[O]n appeal error is never presumed. It must be made to appear affirmatively before there can be reversal . . . [and] the burden of showing error rests upon the one who relies upon it.”); see also Midway Ctr. Assocs. v. Midway Ctr., Inc., 237 N.W.2d 76, 78 (Minn. 1975) (quoting Waters). We nevertheless consider whether the district court’s finding was clearly erroneous.

Free access — add to your briefcase to read the full text and ask questions with AI

Les Grumdahl Window & Siding LLC, A Minnesota Limited Liability Company v. Holly Brown, ..., (Mich. Ct. App. 2024).

Les Grumdahl Window & Siding LLC, A Minnesota Limited Liability Company v. Holly Brown, ... (Les Grumdahl Window & Siding LLC, A Minnesota Limited Liability Company v. Holly Brown, ...) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Marso v. Mankato Clinic, Ltd.
153 N.W.2d 281 (Supreme Court of Minnesota, 1967)
Midway Center Associates v. Midway Center, Inc.
237 N.W.2d 76 (Supreme Court of Minnesota, 1975)
Marriage of Sefkow v. Sefkow
427 N.W.2d 203 (Supreme Court of Minnesota, 1988)
Gjovik v. Strope
401 N.W.2d 664 (Supreme Court of Minnesota, 1987)
Howard v. Frondell
387 N.W.2d 205 (Court of Appeals of Minnesota, 1986)
Morrisette v. Harrison International Corp.
486 N.W.2d 424 (Supreme Court of Minnesota, 1992)
Thayer v. American Financial Advisers, Inc.
322 N.W.2d 599 (Supreme Court of Minnesota, 1982)
Imperial Premium Finance, Inc. v. GK Cab Co.
603 N.W.2d 853 (Court of Appeals of Minnesota, 2000)
Hinz v. Northland Milk & Ice Cream Co.
53 N.W.2d 454 (Supreme Court of Minnesota, 1952)
Waters v. Fiebelkorn
13 N.W.2d 461 (Supreme Court of Minnesota, 1944)
Moorhead Economic Development Authority v. Anda
789 N.W.2d 860 (Supreme Court of Minnesota, 2010)
Christie v. Estate
911 N.W.2d 833 (Supreme Court of Minnesota, 2018)