Leonard's Estate

22 A.2d 676, 343 Pa. 198, 1941 Pa. LEXIS 595
Supreme Court of Pennsylvania·Decided September 30, 1941·No. Appeal, 133·Published·Cited by 4 cases

Opinion

Opinion by

Mr. Justice Stern,

The Mausoleum Building Corporation undertook the construction in Sylvan Heights Cemetery, located near Uniontown, of a mausoleum for the burial of the dead. Plans were prepared for a marble structure designed originally to accommodate five hundred, but later, by amendment, seven hundred bodies. Written contracts were entered into between the corporation and so-called “purchasers” who subscribed for rights of interment in designated crypts, the purchase price to be paid in instalments of 10% at the time of signing the contract, 10% when the foundation was started, 15% upon completion of the foundation, 25% upon installation of the crypts, 25% when the roof was constructed, and 15% when the mausoleum was completed. The corporation executed a bond to a trustee for the use and benefit of the purchasers in the sum of $200,000, with McClellan Leonard, who was an officer and stockholder of the corporation, as surety, Leonard receiving compensation from the corporation for assuming this obligation. The bond recited that the corporation had entered, and would thereafter enter, into written contracts with persons for the sale of crypts and burial spaces in the mausoleum, and the condition of the bond was that when and as the persons entering into the contracts “do, keep, comply and perform all things in accordance with the true intent and meaning of their contracts in writing, then the said bounded principal will build, construct *200 and erect the said proposed mausoleum building and make ready for the sepulture of bodies therein and will keep, comply, perform and do all things as provided by the terms and conditions of its contracts.”

The bond was executed in 1929 and was used as an inducement to persons to enter into contracts for the purchase of crypts. In 1940 the Mausoleum Building Corporation, being without funds, was thrown into receivership at the suit of a number of the purchasers, the money subscribed having been expended partly on the building and partly for salaries and administrative expenses of the corporation. The mausoleum was then only one-third or one-fourth completed as to bulk and one-sixth as to cost; there was no roof or external wall construction; the crypts had been installed in concrete but without the specified marble facing. According to the finding of the court below it will require more than the amount of the bond to finish the mausoleum in accordance with the original plans; there was testimony that the cost of such completion would be between $235,000 and $250,000. The total amount of the contracts entered into with purchasers is $158,550, of which $72,605.75 has been paid. The number of purchasers is 86, of whom 46 have paid 60% or more of an aggregate purchase price of $84,675, such payments amounting to $53,745. The building not having progressed beyond the stage of installation of the crypts, none of the purchasers owes at the present time in excess of 60% of the contract price. A large number of burials have been made in the crypts.

Leonard died in 1937, intestate. At the audit of the second and partial account of the administrator of his estate, the substituted trustee under the bond (the original trustee having died) presented a claim based upon Leonard’s liability as surety. The claim was allowed by the auditing judge in the sum of $200,000. The estate being, as a result, hopelessly insolvent, the court awarded a dividend - of 8% on the claims, amounting to $16,000 *201 on the award in favor of the trustee under the bond. The present appeal is by one of Leonard’s heirs at law.

The question raised under this peculiar, not to say unique, situation, is in regard to the proper measure of damages for breach of the condition of the bond. That instrument does not merely indemnify against loss, but contains an express affirmative covenant that the principal “will build, construct and erect the said proposed mausoleum building.” It therefore constitutes a guaranty or absolute undertaking to build the structure, and ordinarily, when the obligation of such a bond is breached, the measure of damages is the cost of completion, not exceeding, of course, the amount of the bond: Mechanics Trust Co. v. Fidelity & Casualty Co., 304 Pa. 526, 535, 156 A. 146, 149; Purdy v. Massey, 306 Pa. 288, 295, 159 A. 545, 547.

Free access — add to your briefcase to read the full text and ask questions with AI

Leonard's Estate, 22 A.2d 676, 343 Pa. 198, 1941 Pa. LEXIS 595 (Pa. 1941).

22 A.2d 676 (Leonard's Estate) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Restland Memorial Parks, Inc.
W.D. Pennsylvania, 2021
Zeitlin Estate
12 Pa. D. & C.3d 513 (Philadelphia County Court of Common Pleas, 1979)
Janka v. Oakland Cemetery Co.
89 Pa. D. & C. 431 (Philadelphia County Court of Common Pleas, 1954)
Slifer v. Greenmount Cemetery Co.
67 A.2d 584 (Superior Court of Pennsylvania, 1949)