Lent's, Inc. v. Santa Fe Engineers, Inc.

628 P.2d 488, 29 Wash. App. 257, 1981 Wash. App. LEXIS 2336
CourtCourt of Appeals of Washington
DecidedMay 11, 1981
Docket8086-5-I
StatusPublished
Cited by11 cases

This text of 628 P.2d 488 (Lent's, Inc. v. Santa Fe Engineers, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lent's, Inc. v. Santa Fe Engineers, Inc., 628 P.2d 488, 29 Wash. App. 257, 1981 Wash. App. LEXIS 2336 (Wash. Ct. App. 1981).

Opinion

Swanson, J.

This appeal involves the validity of an arbitration award vacated by the trial court on the ground that it was not rendered within 30 days of the close of the arbitration hearings as required by RCW 7.04.090. 1 Appellants, Santa Fe Engineers, Inc., and Howard Electric Co., contend that the award was rendered in a timely manner or, in the alternative, that respondent, Lent's, Inc., waived any objection it had to the timeliness of the award. In a cross appeal, Lent's contends that the trial court erred in *259 not holding that the arbitration award demonstrated on its face an error in the application of law.

The pertinent facts are these: Santa Fe Engineers, a California corporation, was prime contractor for construction of training facilities at the Naval Torpedo Station in Keyport, Washington. Howard Electric Co., a Colorado corporation, and Lent's, Inc., a Washington corporation located in Bremerton, were, respectively, the electrical and mechanical subcontractors for the project.

The subcontracts between Santa Fe and Howard and Santa Fe and Lent's contained a clause providing that either party could demand that a dispute be submitted to arbitration in accordance with the rules of the American Arbitration Association (AAA). During construction, a dispute arose concerning which one of the two subcontractors was responsible for furnishing and installing electric motor starters and disconnect switches for certain mechanical equipment. Santa Fe, as general contractor, directed Howard to do. the work, but it withheld $158,949 from Lent's pending resolution of the dispute. On March 20, 1977, Howard invoked the arbitration clause of the contract and demanded arbitration of the motor starter dispute. Santa Fe, in turn, made demand upon Lent's for arbitration of the same dispute. By agreement, the separate proceedings were consolidated, and a Seattle attorney was appointed arbitrator. The stipulation for consolidation of the hearings also specified that the arbitration was to be governed by the Construction Industry Arbitration (CIA) rules of the AAA.

Hearings were held on November 15 and 16,1978, during which testimony was taken and exhibits introduced. By letter dated November 30, 1978, the tribunal administrator for the AAA advised the parties that the hearing would be held open until December 5, 1978, to permit submission of posthearing summations. The letter further advised that the arbitrator's award would be transmitted within 30 days of the close of the hearing, or January 4, 1979. Despite that the deadline for the submission of briefs was December 5, *260 Lent's submitted a brief dated December 14, 1978. Over Howard's written objection, the arbitrator agreed to consider Lent's brief and briefs of the other parties if they desired to submit them. The arbitrator also stated that he nonetheless anticipated that the award would be rendered by January 4, 1979.

On January 4, 1979, the tribunal administrator sent another letter to the parties indicating that the arbitrator's decision was not ready and requesting that the parties extend the date for the award until January 15,1979. Santa Fe and Howard executed a written extension, but Lent's neither agreed nor objected to the extension. On January 12,1979, the arbitrator prepared his award and mailed it to the AAA. The award was received by the AAA on January 15, retyped on an AAA form, signed, and mailed to the parties on January 16, 1979.

The award was substantially in favor of Howard Electric, awarding it $158,948 as the cost of furnishing and installing the motor starters and switches. Lent's was awarded $15,000 which had been wrongfully withheld by Santa Fe. The arbitrator also indicated in his January 12 letter that he would explain the award if requested by the parties. In response to a request by Lent's, the arbitrator gave reasons for the award in a letter dated January 25, 1979.

On April 9, 1979, Lent's filed an action in superior court to vacate the award on two grounds: (1) that the award had not been rendered within 30 days of the close of the hearing as required by RCW 7.04.090, and (2) that the award was clearly erroneous as a matter of law. The trial court disagreed that the award was erroneous as a matter bf law, but it granted the motion to vacate because the award was not made within the time specified by the statute.

In this appeal, Santa Fe first argues that federal law, rather than state law, governs the enforceability of the award by virtue of either a choice of law provision in its subcontract with Lent's or the supremacy clause of the United States Constitution. We do not reach that issue, however, because the trial court erred in concluding that *261 the award was without legal effect under RCW 7.04.090.

The trial court held that the statute is mandatory and its provisions may not be waived. We agree that the statute's plain language provides that the 30-day time for award may be altered only be execution of a written extension or ratification signed by all the parties. However, the trial court's oral decision reveals that in reaching its conclusion it focused on only part of the statute. The court failed to give effect to the first clause of the statute which limits its application to those situations where "the time within which the award shall be made is not fixed in. the arbitration agreement,..."

Arbitration is consensual and contractual in nature. Balfour, Guthrie & Co. v. Commercial Metals Co., 93 Wn.2d 199, 607 P.2d 856 (1980). The statute. recognizes that the parties may, as they have here, establish a time for the award in the arbitration agreement. The disputes clause of the respective subcontracts did not set forth a time limit in terms of specific days or weeks. However, "The parties to an arbitration fix the time within which an award must be made, either by a specific agreement or by accepting the rules of an agency referred to in their arbitration clause. Parties enjoy considerable freedom in this regard." M. Domke, Commercial Arbitration § 29.01 (1968); accord, Fagnani v. Integrity Fin. Corp., 53 Del. 193, 167 A.2d 67 (1960).

The dispute clause of the subcontracts provide that "either party may demand that the dispute be submitted to arbitration in accordance with the rules of the American Arbitration Association." Further, the stipulation for consolidation of the hearings specified that the Construction Industry Arbitration rules of the AAA were to govern the arbitration, and no claim is now made that those rules are inapplicable.

We must give effect to the parties' clear manifestation of intent to conduct the arbitration in accordance with the CIA rules and to be bound by those rules.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mainline Rock & Ballast, Inc. v. Barnes, Inc.
439 P.3d 662 (Court of Appeals of Washington, 2019)
S & S Const., Inc. v. Adc Properties LLC
211 P.3d 415 (Court of Appeals of Washington, 2009)
S&S Construction, Inc. v. ADC Properties, LLC
151 Wash. App. 247 (Court of Appeals of Washington, 2009)
Hanson v. Shim
943 P.2d 322 (Court of Appeals of Washington, 1997)
Graceman v. Goldstein
613 A.2d 1049 (Court of Special Appeals of Maryland, 1992)
Lindon Commodities, Inc. v. Bambino Bean Co.
790 P.2d 228 (Court of Appeals of Washington, 1990)
Westmark Properties, Inc. v. McGuire
766 P.2d 1146 (Court of Appeals of Washington, 1989)
Marine Enterprises, Inc. v. Security Pacific Trading Corp.
750 P.2d 1290 (Court of Appeals of Washington, 1988)
Groves v. Progressive Casualty
747 P.2d 498 (Court of Appeals of Washington, 1987)
Ruff v. Metropolitan Property & Liability Insurance
508 A.2d 672 (Supreme Court of Rhode Island, 1986)
Monmouth School Committee v. Huston
437 A.2d 621 (Supreme Judicial Court of Maine, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
628 P.2d 488, 29 Wash. App. 257, 1981 Wash. App. LEXIS 2336, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lents-inc-v-santa-fe-engineers-inc-washctapp-1981.