Lemartec Corporation v. East Coast Metal Structures Corp.

CourtDistrict Court of Appeal of Florida
DecidedMay 15, 2024
Docket2023-0601
StatusPublished

This text of Lemartec Corporation v. East Coast Metal Structures Corp. (Lemartec Corporation v. East Coast Metal Structures Corp.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lemartec Corporation v. East Coast Metal Structures Corp., (Fla. Ct. App. 2024).

Opinion

DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA FOURTH DISTRICT

LEMARTEC CORPORATION, et al., Appellants,

v.

EAST COAST METAL STRUCTURES CORP., Appellee.

No. 4D2023-0601

[May 15, 2024]

Appeal from the Circuit Court for the Fifteenth Judicial Circuit, Palm Beach County; Scott R. Kerner, Judge; L.T. Case No. 50-2017-CA-010645- XXXX-MB.

Joy Spillis Lundeen, Felix X. Rodriguez, and Kelly R. Melchiondo of Bilzin Sumberg Baena Price & Axelrod LLP, Miami, for appellants.

Thomasina F. Moore of GrayRobinson, P.A., Tallahassee, for appellee.

DAMOORGIAN, J.

Lemartec Corporation (“Contractor”), Tellus Products, LLC (“Project Owner”), Philadelphia Indemnity Insurance Company (“Philadelphia”), and Suretec Insurance Company (“Suretec”) (collectively “Defendants”) appeal the order denying their motion for attorney’s fees and the subsequent final judgment awarding prevailing party attorney’s fees to East Coast Metal Structures Corp. (“Subcontractor”). For the reasons discussed below, we reverse the award of attorney’s fees to Subcontractor in its entirety and remand for entry of an award of attorney’s fees to Defendants.

Background

The genesis of this appeal is a dispute arising out of the construction of a sugarcane bagasse processing facility located in Belle Glade, Florida (“the Project”). Our analysis of the issues related to the award of attorney’s fees in this appeal necessarily requires a brief discussion of the underlying facts which led to the dispute. Project Owner hired Contractor to design and construct the Project, which consisted of three separate buildings: an office building, a molding building, and a pulping building. Contractor thereafter issued bid drawings to prospective bidders for the steelwork to be completed on the three buildings. Contractor ultimately provided Subcontractor with Letters of Intent (“LOIs”). Each LOI identified the name of the building requiring work and a lump sum price to be paid for the work, and included express language that subcontracts were forthcoming. Shortly thereafter, Contractor sent Subcontractor three subcontracts, one for each building, providing for the fabrication, installation, and delivery of structural steel and miscellaneous metals. Unlike the LOIs, each of the subcontracts included a cross-default provision providing that if Subcontractor breached any of the subcontracts, Contractor could “offset all costs to complete the Work from this Subcontract Agreement and/or other contracts . . . to recompense the Contractor.”

It is undisputed that Subcontractor did not sign the subcontracts. Nonetheless, the parties proceeded as if the subcontracts had been executed, with Subcontractor completing all of the steelwork for the office and molding buildings, and part of the work for the pulping building, pursuant to the subcontracts. Subcontractor failed, however, to supply and install the stairs in the pulping building, as required under the pulping building subcontract.

Project Owner eventually took over the Project from Contractor and assumed the three subcontracts with Subcontractor. After several months of delay, Project Owner began searching for a replacement subcontractor to complete the stairs and requested a deductive change order from Subcontractor. In response, Subcontractor provided a deductive change order for $12,300, which was less than the original estimated value of the stairs at the time of Subcontractor’s bid. After Subcontractor refused to negotiate its proposed credit for the stairs, Project Owner sent Subcontractor a notice of default and eliminated the stairs from Subcontractor’s scope of work. Subcontractor did not respond to the notice of default or attempt to cure the default; instead, Subcontractor recorded a claim of lien.

Project Owner thereafter hired a new subcontractor to complete the stairs at a cost of nearly $127,000. In light thereof, Project Owner refused to pay Subcontractor the balance owed on the subcontracts, including the retainages on the molding and office building subcontracts, pursuant to the cross-default provisions.

2 The Lawsuit

Subcontractor then sued Defendants for the remainder of the balance. Subcontractor’s operative complaint also disputed the validity of the unexecuted subcontracts and argued the LOIs should govern instead.

Subcontractor’s complaint included five counts. Count I alleged claims against Contractor and its surety Philadelphia on the original payment bond pursuant to section 713.23, Florida Statutes. Count II alleged claims against Project Owner and its surety Suretec on the transfer payment bond pursuant to section 713.23, Florida Statutes. Count III alleged claims against Contractor and Project Owner for breach of contract on the pulping building, and sought $63,935.40. Count IV alleged claims against Contractor and Project Owner for breach of contract on the office and molding buildings, and sought $28,011.30 for the molding building and $10,065 for the office building. Finally, Count V alleged alternative quantum meruit claims against Contractor and Project Owner. In total, Subcontractor sought $102,011.70 in damages.

Defendants answered the complaint and raised several affirmative defenses seeking to avoid payment to Subcontractor for various reasons, including a claim for “set-off against any moneys owed to [Subcontractor]” for the cost of completing the stairs. Project Owner also filed a counterclaim against Subcontractor for breach of the pulping subcontract, and sought damages incurred as a result of Subcontractor’s failure to complete the stairs. Subcontractor answered the counterclaim and asserted several affirmative defenses, including that Project Owner “failed to satisfy all conditions precedent to bringing this action.”

The matter ultimately proceeded to a ten-day bench trial. Prior to trial, the parties filed a joint pretrial stipulation wherein they listed the following relevant disputed issues of fact for determination at trial:

1. Whether the parties ever entered into written subcontract agreements for the office building, molding building and pulping building . . . .

2. Whether the parties’ actions provided assent to the unsigned subcontracts for the office building, molding building, and pulping building.

3. Whether the Defendants breached the parties’ agreements related to the office building, molding building and pulping building . . . .

3 4. Whether [Subcontractor] breached the parties’ agreements by not supplying and installing the stairs at the pulping building in a timely fashion.

5. The amount of damages sustained on account of any breach of the contract by any party.

6. The reasonable value of the pulping stairs.

7. Whether [Subcontractor] has perfected and is entitled to foreclose its mechanic’s lien.

Final Merits Judgment

Following the bench trial, the trial judge—Judge Howard Coates— entered a detailed 35-page final judgment. The final judgment was divided into two parts: the first part addressed whether the LOIs or unexecuted subcontracts governed, and the second part addressed damages.

Regarding whether the LOIs or subcontracts governed, the trial judge began his analysis by noting that “the primary dispute is over which contract controls.” The trial judge ultimately concluded the LOIs were not enforceable, and that the subcontracts were enforceable and governed despite the lack of signatures.

Regarding the amounts owed between the parties, the trial judge found Subcontractor was entitled to $10,065 for the office building, $28,011.30 for the molding building, and $33,821.40 for the pulping building, for a total of $71,897.70. The trial judge also found Subcontractor failed to perfect its claims against the bonds, and therefore could not collect on the payment bonds.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M & P Concrete Products, Inc. v. Woods
590 So. 2d 429 (District Court of Appeal of Florida, 1991)
Strahan v. Gauldin
756 So. 2d 158 (District Court of Appeal of Florida, 2000)
Croker v. Reliance Nat. Indem. Co.
800 So. 2d 4 (Louisiana Court of Appeal, 2001)
Prosperi v. Code, Inc.
626 So. 2d 1360 (Supreme Court of Florida, 1993)
Moritz v. Hoyt Enterprises, Inc.
604 So. 2d 807 (Supreme Court of Florida, 1992)
AAA Sod, Inc. v. Weitzer Corporation
513 So. 2d 750 (District Court of Appeal of Florida, 1987)
Liggett Group, Inc. v. Davis
975 So. 2d 1281 (District Court of Appeal of Florida, 2008)
Ancel Pratt, Jr. v. Michael C. Weiss, D.O.
161 So. 3d 1268 (Supreme Court of Florida, 2015)
Susanne L. Kuhajda v. Borden Dairy Company of Alabama, LLC.
202 So. 3d 391 (Supreme Court of Florida, 2016)
Hoang Dinh Duong v. Ziadie
153 So. 3d 354 (District Court of Appeal of Florida, 2014)
Newman v. Guerra
208 So. 3d 314 (District Court of Appeal of Florida, 2017)
Arrowood Indemnity Co. v. Acosta, Inc.
58 So. 3d 286 (District Court of Appeal of Florida, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Lemartec Corporation v. East Coast Metal Structures Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/lemartec-corporation-v-east-coast-metal-structures-corp-fladistctapp-2024.