Lehigh Valley R. v. Kiszel

80 F. 470, 25 C.C.A. 566, 1897 U.S. App. LEXIS 1834
CourtCourt of Appeals for the Second Circuit
DecidedMay 3, 1897
StatusPublished

This text of 80 F. 470 (Lehigh Valley R. v. Kiszel) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lehigh Valley R. v. Kiszel, 80 F. 470, 25 C.C.A. 566, 1897 U.S. App. LEXIS 1834 (2d Cir. 1897).

Opinion

SHIPMAN, Circuit Judge.

The complaint alleged that the accident solely resulted from the defendant’s negligence in using a boiler that was, to its knowledge, defective and out of repair, and that the explosion occurred by reason of this defective condition. The answer, in addition to a general denial, alleged also, as defenses, that the accident was caused by the contributory negligence of the plaintiff, and by the negligence of one of his fellow servants.

[471]*471The facts, as narrated by the plaintiff on the trial, are, in outline, as follows:

“On the day of the accident, plaintiff, who had been in the company’s employ at Lost Creek for several years, working part of the time in the breaker, and part of the time in the boiler house, was assigned to work at the boiler house, to assist John Miller. Miller was fireman in charge, in the absence of James Egan, the head fireman, who was unwell that day. There were seven sets of boilers in this boiler house, three boilers to each set, making twenty-one boilers in all. The boilers rested at one end on a wall, and were hung at the other end on girders. When Kiszel began work, about 2 o’clock p. m. on the day of the accident, the fires were already lighted under eighteen boilers. The other three were cold, having been out of use for a week for repairs to the flues and surrounding masonry. A fire was put under these three boilers between 5 and 6 o’clock p. m., while he was at his supper.”

About 7 o’clock lie» was told by Miller to watch these three boilers, and found that the water in the first boiler just caught the middle. gauge, and was higher than that gauge in the second and third boilers. The first boiler was the one that exploded. At a quarter past 8, when he was looking under it, he saw that the water was “dropping down in the middle from the boiler.” Miller was there at the time, and also looked at the boiler, and said, “Most of those boilers leaked.” About five minutes before 9 o’clock, Miller, Shields, who was hoisting engineer, and Lanbach, who was the pump-man, came to look at the boiler. Kiszel also looked in, and saw that it was leaking badly. It exploded at 9 o’clock, and Miller, Shields, and Laubach were killed. Nothing had been done to extinguish the fire or blow off steam or disconnect this set of boilers from the rest. The boiler in question was a plain cylinder boiler, made at the Hazel-ton shops. The Hazelton boilers are considered about the best make of boilers used in that region. It was regularly inspected every six months. The last inspection had been made on March 2, 1894, between four and five months before the accident. At that time the inspector went into the boiler with a lamp and his tools, and examined the boiler and the rivets, and reported the boiler good. It had been in active use and working well up to the time the fires were drawn for repairs to the masonry, about a week before the accident.

The defendant moved, at the close of the testimony, for the direction of a verdict in its favor, because no negligence or want of care on its part had been established, whereas the plaintiff had been guilty of contributory negligence, and because the negligence, if any, was that of Miller, a co-employó with the plaintiff. The denial of this motion is the subject of one or more of the assignments of error. The adequate difficulty which prevented the direction of a verdict was the state of the evidence upon the questions of fact. Kiszel was the only survivor who knew anything of the occurrences during the afternoon and evening before the explosion, and the inferences which could fairly be drawn from his testimony on the trial were against the safety of the boiler, and were not in favor of the negligence of Miller, who was admitted by his employers to have been a competent fireman. Kiszel, shortly after his injury, when he was in the hospital, had given a history of the accident, and had also testified before the coroner, and his statements on both those occasions bore with severity [472]*472upon the carelessness of Miller, but upon the trial the drift of his testimony was quite different. The prominent fact which he then sought to have inferred was the defective character of the boiler. He said that it was originally half an inch thick, and that on the bottom, where the break occurred, it had worn down to an eighth of an inch, and that the bottom was worn out. The other testimony adverse to its safety, and which called upon the defendant for the exercise of care in its examination, and in the maintenance of its soundness, was in regard to the usual duration of the life of a boiler, and upon this point the defendant’s witnesses alone testified. One said, “I have known some of them [the Hazelton boilers] to last eighteen or twenty years.” Another said that they lasted from 20 to 22 years. Another said, “I have known them to last twenty years.” The exploded boiler was 18 years old. The opinion of the defendant’s experts who subsequently investigated the subject was that the crack and the resulting explosion were due to the unequal expansion of the bottom and the top of the boiler, caused by too sudden and hot a fire when the boiler was cold and the masonry was still damp, and there was not enough water in the boiler. Upon this state of the evidence, especially in regard to the time when a boiler must be expected to wear out, the question of an unsoundness which ought to have been ascertained by the defendant’s agents or representatives could not be taken from the jury. But it is said that the defendant had discharged its duty by the purchase of a boiler of the best material, from manufacturers of the best reputation, by semiannual careful inspection of it, and by -its previous freedom from indications of leaks, for the defendant is not a warrantor of the absolute safety of.its machinery, and is not liable for the consequences of unknown defects which reasonable and accurate investigation, made at the time when due care requires that such investigation should be made, failed to discover. That statement of the law is not objectionable, but the question of a defendant’s liability for the defects of old machinery turns upon the continued exercise of due care, for its duty to its employés is only discharged when “its agents whose business it is to supply such instrumentalities exercise due care, as well in their purchase originally as in keeping and maintaining them in such condition as to be reasonably and adequately safe for use by employés.” Hough v. Bailway Co., 100 U. S. 213. It was a question of moment in this case whether, if this boiler was defective, its condition, after 18 years of use, ought not to have been previously ascertained by the defendant. The difficulty which prevented the trial judge from taking the question of the defective condition of the boiler from the jury was also apparent in regard to the negligence of Miller. As the plaintiff presented Miller’s conduct to the jury, he was apparently thoughtful, and not inattentive, but his conduct was heedless and willful, if the declaration of Kiszel before the coroner and in the hospital, and the inferences directly deducible from his story, were true. The question was one of the credibility to be given to the plaintiff as he appeared upon the stand, and the jury decided in his favor.

The defendant made divers requests to charge in regard to the [473]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hough v. Railway Co.
100 U.S. 213 (Supreme Court, 1880)

Cite This Page — Counsel Stack

Bluebook (online)
80 F. 470, 25 C.C.A. 566, 1897 U.S. App. LEXIS 1834, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lehigh-valley-r-v-kiszel-ca2-1897.