Lehigh Gas & Oil Co. v. Pennsylvania Department of Environmental Resources

671 A.2d 241, 1995 Pa. Commw. LEXIS 611
CourtCommonwealth Court of Pennsylvania
DecidedDecember 4, 1995
StatusPublished
Cited by4 cases

This text of 671 A.2d 241 (Lehigh Gas & Oil Co. v. Pennsylvania Department of Environmental Resources) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lehigh Gas & Oil Co. v. Pennsylvania Department of Environmental Resources, 671 A.2d 241, 1995 Pa. Commw. LEXIS 611 (Pa. Ct. App. 1995).

Opinion

SILVESTRI, Senior Judge.

Lehigh Gas & Oil Company (Lehigh) petitions for review of an order and adjudication from the Environmental Hearing Board (Board) which dismissed Lehigh’s appeal from the Department of Environmental Resources’ (DER) December 10, 1991 order directing Lehigh to take certain measures to remedy the contamination resulting from the discharge of petroleum products1 at the Har-tranft Service Station (Station).

[243]*243The Station is located in the southeastern quadrant of the intersections of Route 64 and Clearmont Avenue in the village of Hometown (Hometown).2 Located underground of the Station were six storage tanks3 which were owned by Lehigh. On January 7,1991, the Department received a complaint from the Rush Township Sewer Authority concerning petroleum odors in the homes and sewer lines in Hometown. In response thereto, DER conducted a preliminary investigation which identified two potential sources of the contamination: 1) the Station; and 2) a pipeline owned and operated by Sun Pipe Line Company (Sun).4 The contamination pervaded the air, water, and soil primarily within in the southeastern quadrant of Hometown from the Station to McMullen’s Pond (Pond).5

On January 8, 1991, DER determined through its investigation that a 6,000-10,000 gallon release had occurred at the Station over the past two years.6 On January 15, 1991, Lehigh confirmed a recent release at the Station. On January 28, 1991, DER issued a notice of violation to Lehigh setting forth Lehigh’s responsibilities to do a site assessment and integrity testing of lines and systems in order to define the vertical and horizontal extent of the contamination as verified by specific field investigations.7 In response thereto, Lehigh submitted a proposed site characterization plan8 on February 8, 1991; said plan was tentatively approved by DER in March of 1991 subject to additional amendments. During the implementation of the plan, certain remedial actions were undertaken by both Lehigh and DER; in addition thereto, testing continued by Lehigh, DER, and Sun.

On December 3, 1991, Lehigh submitted an amended site characterization and partial remediation plan which claimed that the contamination from the Station was limited to its immediate vicinity, i.e. the area south of Route 54 between Clearmont and Cumberland Avenues, and as a result thereof Lehigh would take no remedial action other than the removal of the tanks themselves. After reviewing the amended site characterization plan, DER concluded that it did not adequately define the vertical and horizontal extent of the contamination.

On December 10, 1991, DER issued an administrative order9 in which it made Find[244]*244ings (A-AA) and ordered, in pertinent part, as follows:

1. Lehigh Gas and Oil Company shall further define the vertical and horizontal extent of contamination, fully verified by site-specific field investigation, emanating from the Hartranft Service Station. Le-high Gas and Oil Company shall submit the findings of the field investigation and a full remediation plan (addressing air, water and soil contamination) within ninety (90) days of receipt of this Order.
2. Lehigh Gas and Oil Company shall plan, construct and maintain a vapor recovery system at the Ryan, Evans and Bowe residences. Lehigh Gas and Oil Company shall identify its contractor and define the scope of work, both of which must be submitted to the Department for receipt by December 13,1991.
3. Lehigh Gas and Oil Company shall design, construct and maintain an interceptor trench immediately upgradient of the pond on the McMullen property in order to alleviate petroleum odors emanating from the pond and reduce the amount of petroleum product flowing into the pond. Le-high Gas and Oil (sic) shall submit a work plan for Department approval, including but not limited to construction parameters for the interceptor trench within fourteen (14) days of receipt of this Order....

On December 17, 1991, Lehigh filed a notice of appeal seeking Board review of DER’s order. During the pendency of the appeal, however, both Lehigh and DER continued to take steps to determine the source and extent of the contamination11 as well as implementing measures to remedy the contamination as it currently existed.

On January 10, 1992, Lehigh submitted to DER a proposed phase II site characterization plan along with a proposed tank removal and site remediation plan pertaining to the underground tanks and systems at the Station. Pursuant thereto, the storage tanks and 1,533 tons of contaminated soil were removed from the immediate vicinity of the Station between January 22-31, 1992. Tests on the soil samples taken from the Station were conducted by Lehigh and DER both of whom continued to conduct additional tests of the soil, air, and water in the contaminated area; DER also continued to perform additional remedial measures.

During May of 1992, DER decided to have R.E. Wright Associates, Inc. (REW), a general environmental technical assistance contractor, do a hydrogeologic site characterization in the affected area of Hometown to determine the source and extent of hydrocarbon impact to the Pond and residences south of Route 54 and east of Clearmont Avenue. After learning that DER had contracted with REW to do a site characterization, Lehigh all but ceased further investigations of its own.12 In its August 1992 report to DER, REW concluded that, based upon the documented release of gasoline at the Station, the direction of the groundwater flow from that site, the existence of a plume of contamination following the groundwater flow direction, and the surfacing of that contamination at the Pond, the Station was the source of the contamination. Based on the investigations of Lehigh and REW, as well as its own investigation, DER concluded that the Station was in fact the source of the eontamina[245]*245tion which existed south of Route 54 and extended east of both Clearmont and Cumberland Avenues from the Station to the Pond.

Without admitting responsibility for the contamination, Lehigh submitted to DER, in October of 1992, a proposed Remedial Action Plan which proposed, inter alia, to 1) continue the recovery of free product from the Pond and trench sump, 2) continue operation of the vapor extraction systems in the residences, and 3) continue venting the sewer system, as needed.13 On November 3, 1992, DER met with Lehigh to discuss its disagreements with the proposed remedial action plan. By letter of November 5, 1992, DER set forth a list of ten matters requiring further clarification and/or additional data prior to implementation of the proposed remedial activities. (Exhibit S-10, R.R. 938a-940a).

No further action in this matter was taken until the Board conducted hearings, beginning on June 7 and continuing through July 6, 1993, during which Lehigh contested its liability for the contamination beyond the immediate vicinity of the Station and the reasonableness of the remediation required by DER. The Board predicated its decision upon Section 1311(a) of the Storage Tank and Spill Prevention Act (Storage Tank Act) which provides as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
671 A.2d 241, 1995 Pa. Commw. LEXIS 611, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lehigh-gas-oil-co-v-pennsylvania-department-of-environmental-resources-pacommwct-1995.