Legum v. Harris

135 S.E.2d 125, 205 Va. 99, 1964 Va. LEXIS 150
CourtSupreme Court of Virginia
DecidedMarch 9, 1964
DocketRecord 5697
StatusPublished
Cited by2 cases

This text of 135 S.E.2d 125 (Legum v. Harris) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Legum v. Harris, 135 S.E.2d 125, 205 Va. 99, 1964 Va. LEXIS 150 (Va. 1964).

Opinion

Buchanan, J.,

delivered the opinion of the court.

Edward Legum, appellant, filed in the court below his petition for a writ of mandamus to compel the State Highway Commissioner, appellee, to institute and conduct condemnation proceedings to ascertain the damages to his building, alleged to have been caused by the con *100 struction of an underpass at the intersection of Tidewater Drive and Little Creek Road, in the city of Norfolk.

The petition alleged that in constructing the underpass the appellee’s contractor excavated deep holes close to appellant’s property and as a result the walls and other parts of his building cracked and were otherwise damaged. It also alleged that appellant had demanded of the appellee that he institute condemnation proceedings but appellee had failed to do so.

Appellee’s demurrer to the petition was overruled and he filed an answer in which he denied that he or his agents excavated deep holes close to the appellee’s property, or did anything by which appellant’s property, which he alleged was more than 250 feet from any right of way of the Highway Department, could have been damaged.

The court below heard the appellant’s evidence ore tenus and at its conclusion struck it out and dismissed appellant’s petition for mandamus on the ground that his evidence was too indefinite to prove the cause of any damage that appellant’s building may have suffered.

The first story of appellant’s building, approximately 90 x 165 feet, was erected in 1953, and a second story was added in 1955 or 1956. The evidence indicates that it was built of cinder blocks and stuccoed, and the architect testified that it was erected under his supervision in accordance with the plans and specifications in a substantial, workmanlike manner. However, in reply to questions by the court, he testified that with those plans in front of him an ordinarily prudent man would put down borings to determine what was beneath the surface and that was not done in this case.

This architect testified that there were no cracks in the building at the time it was completed but since then he had observed some cracks on the southwest corner, the east side and at the northwest of the building. He was asked his opinion as to whether there was connection between the cracks and the underpass work and replied, “There is a possibility they could be caused by pumping operations which, in turn, cause settlement.” The court asked him what caused the cracks and he replied that he did not think he could answer the question; that he just had an opinion. He then continued:

“Now, what caused the settlement, that I cannot prove. If the pumping operations have caused the settlement under the buildings and so on, it is possible they caused that. I do not think it is the pile driving because it is too far away, in my opinion, but I think that pumping operation could have something to do with that.”

A structural engineer testified that he examined the building in *101 1958 and found numerous cracks which varied from minor cracks, to be expected from temperature changes or shrinkage of the material, to others more serious, “and definitely caused by a settlement.” He said that his opinion at the time was that “were there any settlement,” it was due to the excavation for the underpass, that any deep excavation in this area required pumping out of the ground water, and “It is probable in my opinion, that some fine materials were carried out of the area by this well pointing and caused a general settlement of the entire area there.” He was asked to explain how the moving of water from underground some 240 feet away would cause erratic settling of the building as he had described, and he replied that he did not know, “It could be that the ground is not uniform. It has varying characteristics.”

He stated: “In my opinion, a strong probability exists that the work for the underpass could well result in this damage that I saw to the Legum building.” However, he said that he had no knowledge “one way or the other of the underpass,” and saw the construction of it only to the extent of driving by. He said that the cracks in the Legum building were “a little bit abnormal for uniform settlement,” and the only way he could explain it was to point to the work at the underpass “as a probability.” He could not say how much water would have to be removed to cause the condition in the Legum building, but he said it would be possible to construct the underpass without the damage to the building which he had described, “There are several probabilities which could occur, one of which you would have no damage, of course.”

A witness, formerly employed as a salesman by appellant, testified that the building cracked from the pile driving at the underpass. He first observed cracks in a couple of places, he said, and it gradually got worse, but he did not know how long it was before he saw any more. He said also that there was a continuous pumping operation going on.

Another witness testified that there were two or three pumping operations going on continuously, the exact location of which he did not recall. The pump station was perhaps 200 feet or less from Legum’s building. It required the digging of a hole the depth of which he thought was between 28 and 34 feet, he did not recall exactly. He said that during the excavation one of the water mains burst and dumped something like 1.5 million gallons of water in the underpass, which had to be pumped out eventually.

*102 The appellant testified that the cracks in his building became noticeable after the contractor started his work, and he made a claim to the Highway Commissioner about it; that the contractor had two or three deep well pumps which were operated continuously through the whole job. He was asked on cross-examination whether he rememberd a Mr. Armistead coming to his building in October 1957 and asking him when he first observed the cracks and whether he stated on that occasion that he was unable to state when the cracks first appeared, but that he noticed them before the construction of the underpass started. His reply was, “I don’t remember this moment making that statement. I can’t tell you I did or did not.”

The general contractor who built the original building in 1953 described the location of the cracks in the building and was asked his opinion as to what caused them. He replied that he assumed they were not there before the underpass was started, that in other cases he had known about where there was considerable pumping “the water carries a little silt with it and lets the ground down,” and he did not know what else could have caused the cracks in the Legum building. He stated, however, that he did not know the pattern that water would take when it was moved, and he would have to assume that it would be taken from under this building before it would cause a settling and “If no water was taken out from underneath it, I don’t think you would have any settlement.” He did not know, he said, that the damage to the building was caused by lowering the water table, and that it was purely an assumption that such was the cause of the damage.

On an ore terms

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Leasing Corp. v. MDA Lending Solutions, Inc.
82 Va. Cir. 230 (Hanover County Circuit Court, 2011)
Cartwright v. Commonwealth Transportation Comm'r
613 S.E.2d 449 (Supreme Court of Virginia, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
135 S.E.2d 125, 205 Va. 99, 1964 Va. LEXIS 150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/legum-v-harris-va-1964.