Legislative Utility Consumers' Council v. Public Utilities Commission

383 A.2d 89, 118 N.H. 93, 1978 N.H. LEXIS 351
CourtSupreme Court of New Hampshire
DecidedFebruary 17, 1978
Docket7810
StatusPublished
Cited by8 cases

This text of 383 A.2d 89 (Legislative Utility Consumers' Council v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Legislative Utility Consumers' Council v. Public Utilities Commission, 383 A.2d 89, 118 N.H. 93, 1978 N.H. LEXIS 351 (N.H. 1978).

Opinion

Bois, J.

This is an appeal under RSA 541:6 from an order of the Public Utilities Commission [commission] denying certain refund claims made by the Legislative Utility Consumers’ Council [LUCC] and Volunteers Organized in Community Education [VOICE]. The refund claims were asserted by the plaintiffs, as intervenors, against the Public Service Company of New Hampshire [PSC] in the course of monthly fuel adjustment rate hearings authorized by RSA 378:3-a II (Supp. 1976). These claims and a motion for a rehearing, subsequently filed, were denied by the commission. For the reasons which follow herein, we uphold the decisions of the commission and dismiss the appeal.

PSC has a fuel adjustment clause as part of its tariff, which operates to recover fossil fuel costs which exceed fuel costs included in the basic rates. For PSC the fuel adjustment charge represents the increased cost of fossil fuel over what those costs were in mid-1971. Included within the calculation of the monthly fuel adjustment charge is the cost of coal which is eventually passed on to and paid for by consumers. Legislative Utility Consumers’ Council v. PUC, 117 N.H. 972, 380 A.2d 1083 (1977).

PSC has a coal contract with Consolidation Coal Company [CCC] which provides in part that CCC will maintain a storage pile and that the total monthly price will equal the appropriate unit contract price multiplied by the tons bunkered by PSC.

In 1971 the storage pile was reduced to zero. CCC then began rebuilding a coal reserve for PSC. In 1975 it was discovered that more than 100,000 tons of coal had been paid for but not bunkered. Thus PSC had recorded on its inventory and paid CCC for more coal than it actually burned. The cost of this coal had been included in the monthly fuel adjustment charges, passed on to and paid for by the consumers, so a refund was in order. Three independent surveys of the coal pile, ordered by PSC and CCC, differed by a small amount and a settlement figure of 127,209.60 tons was agreed to.

When the commission was informed of the discrepancy, a conference was held on August 30, 1976, to discuss the manner in which the overcharges would be returned to PSC’s customers. The *96 precise times when the discrepancy was built up could not be established. It was proposed that the buildup be assumed to have occurred from November 1971 to August 1976. If it were further assumed to have occurred equally in each of those months, then the built-up tons should be priced out at the cost of coal during those months. Being unable, however, to establish the buildup in each month, and because of the constantly escalating price, PSC decided to price out the refundable coal at the current, higher price of $34.03 per ton. It was computed that pricing the coal out at the actual increasing prices over the five-year period would yield a refund of about $2.5 million, as opposed to $4.5 million based on the current price. CCC agreed to make its refund on the current rather than the historical cost of the coal.

Matters concerning the coal pile inventory discrepancy were raised at monthly fuel adjustment charge hearings held from August 20, 1976, to January 18, 1977. These monthly hearings, open to the public, were held pursuant to RSA 378:3-A II (Supp. 1976), requiring commission approval before a utility levies a fuel adjustment charge. LUCC (joined by VOICE), intervened pursuant to RSA 363-C:8 III (Supp. 1976), empowering LUCC to “intervene in, any proceeding before any . . . regulatory body in which the interests of utility consumers are involved . . . .” In addition to inquiring about the coal buildup, the plaintiffs raised questions concerning the quality of contract coal and the reasonableness of PSC’s purchases of noncontract coal during the inventory buildup. They eventually sought the following refunds:

(a) a BTU deficiency adjustment;

(b) a refund for transportation costs associated with BTU deficient coal;

(c) a refund for purchases for noncontract coal above the contract price; and

(d) interest on refunds (a), (b), and (c) as well as on the coal inventory refund.

Additional claims were raised and denied but have not been appealed. PSC agreed to distribute a refund based on deficiency in BTU content of some of the coal it purchased as well as its transportation costs. It refused, however, to distribute interest on these two refunds and refused the other refunds requested by the intervenors.

*97 On April 7, 1977, the commission denied the remaining claims. Even though the contract with CCC was a requirements contract and further required CCC to maintain a 45-day stockpile of coal as a reserve, the commission sustained PSC’s purchase of noncontract coal. The ruling was based on the commission’s findings that (1) the Arab oil embargo of 1973 had a substantial effect upon PSC’s decisions to purchase noncontract coal; (2) the company properly wanted to test the coal market, from time to time, realizing that the contract with CCC would soon expire; and (3) PSC was not satisfied with its supplier’s ability to maintain a coal reserve sufficient to hedge against such anticipated interruptions as railroad delivery problems, coal miners’ strikes, and holidays. Interest was denied because “PSC did not obtain an interest element in its settlement with CCC and thus has no funds which belong to its customers.”

On April 26, 1977, the intervenors moved for a rehearing, alleging the denial of their claims was “clearly unlawful or unreasonable.” They also argued that the commission erred in denying refunds on the spot purchases of coal based on the consideration of the effect of the Arab oil embargo, “when there is no evidence in the record concerning the same.” The motion was denied. Intervenors thereupon filed an appeal to this court under ESA 541:6 contesting the denial of their claims as well as of their motion for a rehearing.

The first question is whether the commission had the statutory authority to pass on the claims raised by LUCC and VOICE. PSC argues that the refunds sought by the intervenors were “reparations” and recoverable only by a proceeding pursuant to ESA 365:29. That statute provides that:

Whenever complaint has been made to the commission covering any rate, fare, charge or price demanded and collected by any public utility, and the commission has found, after hearing and investigation, that an illegal or unjustly discriminatory rate, fare, charge or price has been collected for any service, the commission may order the public utility which has collected the same to make due reparation to the person who has paid the same, with interest from the date of the payment. Such order for reparation shall cover only payments made within two years before the date of filing the petition for reparation.

*98 The intervenors did not initiate a reparation claim proceeding, so the company asserts that their claims should never have been heard.

PSC had filed a motion with the commission at the hearing, seeking to limit the scope of inquiry to the question of how the coal adjustment refund was to be passed on to the consumers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Appeal of Town of Seabrook
44 A.3d 518 (Supreme Court of New Hampshire, 2012)
Appeal of Pennichuck Water Works, Inc.
992 A.2d 740 (Supreme Court of New Hampshire, 2010)
Appeal of Department of Safety
461 A.2d 98 (Supreme Court of New Hampshire, 1983)
Appeal of Nationwide Insurance
411 A.2d 1107 (Supreme Court of New Hampshire, 1980)
LEGISLATIVE UTIL. CONSUMERS'COUNCIL v. Granite State Elec. Co.
402 A.2d 644 (Supreme Court of New Hampshire, 1979)
Legislative Utility Consumers' Council v. Public Service Co.
402 A.2d 626 (Supreme Court of New Hampshire, 1979)
Application of Hawaii Elec. Light Co., Inc.
594 P.2d 612 (Hawaii Supreme Court, 1979)
Patenaude v. Town of Meredith
392 A.2d 582 (Supreme Court of New Hampshire, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
383 A.2d 89, 118 N.H. 93, 1978 N.H. LEXIS 351, Counsel Stack Legal Research, https://law.counselstack.com/opinion/legislative-utility-consumers-council-v-public-utilities-commission-nh-1978.