Lefevre v. L. K. Construction, No. Cv 97 0056889 S (Mar. 1, 1999)

1999 Conn. Super. Ct. 2890
CourtConnecticut Superior Court
DecidedMarch 1, 1999
DocketNo. CV 97 0056889 S
StatusUnpublished

This text of 1999 Conn. Super. Ct. 2890 (Lefevre v. L. K. Construction, No. Cv 97 0056889 S (Mar. 1, 1999)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lefevre v. L. K. Construction, No. Cv 97 0056889 S (Mar. 1, 1999), 1999 Conn. Super. Ct. 2890 (Colo. Ct. App. 1999).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
On February 23, 1999, the court heard evidence at a trial regarding the complaint of the plaintiffs, Robert Lefevre and Steve Gelinas, against the defendant, L.K. Construction Services, Inc., for breach of contract, unjust enrichment, quantum meruit, and a violation of the Connecticut Unfair Trade Practices Act (CUTPA). The defendant counterclaims for breach of contract.

The court finds the following facts. The plaintiffs are self-employed duct craftsmen. The defendant was, in December 1995, a new corporation whose first project was to provide labor for the installation of new ductwork at Backus Hospital in Norwich. The defendant's general manager, David Kennedy, had worked with and supervised the plaintiffs during the past ten years, and the three were friends. Kennedy contacted the plaintiffs in December 1995 to find out if the were interested in working on this project. The job required the removal of old ductwork and the installation of new ductwork in a section of the hospital known as the E-wing. Kennedy estimated the E-wing phase would entail 1,360 hours of labor.

The plaintiffs were interested and submitted a proposal to CT Page 2891 the defendant. The defendant rejected the proposal as too costly. Kennedy prepared a counteroffer whereby some of the work at E-wing would be performed by a third workman, at a cheaper cost, and by Kennedy himself, The plaintiffs and the third worker would each perform 420 hours and Kennedy would work the remaining 100 hours. The E-wing installation was to be completed by June 1, 1996. The counteroffer dated January 19, 1996, proposed compensation for the plaintiffs of $22 per hour for 420 hours each for a total of $9,240 each rounded up to $10,000 per man.

The counteroffer was handwritten on a blank sheet by Kennedy. This document was, unsigned and makes no reference to any parties. (Exhibit B.)

No formal or explicit acceptance of this offer occurred. The plaintiffs, however, worked on the project regularly from January 3, 1996, before the counteroffer, to June 1, 1996. On January 29, 1996, the defendant issued purchase orders to the plaintiffs for the E-wing work These orders indicated that the plaintiffs were responsible for installing ductwork in accordance with certain plans at a payment rate of $22 per hour up to 420 hours. (Exhibits C and G.) The orders also note that additional labor might be necessary, not to exceed 260 hours, that the plaintiffs were to submit weekly time slips to the defendant, and that the plaintiffs were to secure insurance coverage certification. These orders were signed by Kennedy. The orders lack any mention of the $10,000 per person compensation which was contained in the counteroffer made ten days earlier.

Neither plaintiff submitted time slips, and none was requested by the defendant's agents. Instead, each plaintiff submitted progress invoices on various dates indicating that a certain percentage of the project had been completed and requesting payments commensurate with that percentage of the $10,000 figure. The defendant honored these invoices up to the point where 80% of the work for E-wing was finished, that is, each plaintiff received a total of $8,000 plus $800 for demolition work previously accomplished.

The third installer was frequently utilized by the defendant on phases of the project besides the E-wing. His contribution to the E-wing portion never approached the 420 hours allocated to him. As a result, the plaintiffs labored more than 420 hours a piece to make up for this deficit. Concerned about compensation for these excess hours, the plaintiffs inquired of Kennedy. CT Page 2892 Kennedy assured the plaintiff that everything would work out fairly in the end Kennedy knew that the plaintiffs continued to work on the E-wing phase, although no express approval or authorization was sought by the plaintiffs nor given by the defendant for labor provided beyond 420 hours.

On June 1, 1996, the E-wing installation was complete except for one to two weeks work. Kennedy informed the plaintiffs that, due to a materials error and engineering changes, work or the E-wing area would be suspended until these difficulties were cleared up, which, in his estimation, would take about two weeks. The plaintiffs informed Kennedy that they had taken on other work but could complete the job at the hospital if they worked nights and weekends Kennedy told them he would contact them when work in the E-wing area might resume.

Instead, Kennedy offered the remaining ductwork installation to another installer at $22 per hour. That arrangement fell through, and the defendant paid Kennedy and two other employees $5,600 to finish the installation. The project was completed around June 10, 1996.

The plaintiffs contend that they each had a contract with the defendant which provided that each plaintiff would receive $10,000 for 420 hours of labor and $22 per hour for every hour beyond 420 up to 680 hours total. The defendant, on the other hand, contends that the contract was that the entire job would be completed for $10,000 each, notwithstanding the actual hours worked.

I
The first count of the complaint alleges breach of an express contract. The party asserting a breach of an agreement bears the burden of proving the agreement existed and its terms. Ferrie v.Sperry, 85 Conn. 337, 342 (1912). For a contract to exist, there must be a meeting of the minds as to the terms of the agreement.Hirschfeld v. Hirschfeld,, 50 Conn. App. 280, 287 (1998). A "meeting of the minds" is defined as a mutual agreement and assent of the parties to the substance and terms of the contract.Sicaras v. Hartford, 44 Conn. App. 771, 784 (1997).

The court finds no meeting of the minds occurred between these parties as to the method of and amount of compensation for the labor needed to install ductwork for the E-wing area. The CT Page 2893 documents proffered by the parties fail to evince a mutual understanding of the terms of any purported agreement. The plaintiffs began work on January 3, 1996. The counteroffer was made January 19, 1996, and is unsigned and fails to identify any participants. If conflicts with the defendant's purchase orders of January 29, 1996, as to whether the compensation for the plaintiff was based on hours worked or a set price.

The plaintiffs began working and continued to work in the hope that an agreement would evolve. This hope was based on the good previous work relationship with Kennedy and their friendship. Unfortunately, that friendship and hope caused each side of this litigation to believe, erroneously, that its view of the method of calculating compensation was understood and acceptable to the other.

At times the plaintiffs acted as if a set price of $10,000 applied, such as when they submitted invoices requesting progress payments based on percentage of work completed. At other times, they acted consistently with an hourly basis for compensation, such as when they voiced concern to Kennedy over the mounting hours.

The defendant behaved equally equivocally. The defendant submitted purchase order clearly based on hourly rate compensation, yet it paid the plaintiffs on a basis of percentage of job completion for a $10,000 set price. The defendant never demanded weekly time slips despite that provision in the purchase orders.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ferrie v. Sperry
82 A. 577 (Supreme Court of Connecticut, 1912)
Burns v. Koellmer
527 A.2d 1210 (Connecticut Appellate Court, 1987)
Sicaras v. City of Hartford
692 A.2d 1290 (Connecticut Appellate Court, 1997)
Hirschfeld v. Hirschfeld
719 A.2d 41 (Connecticut Appellate Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
1999 Conn. Super. Ct. 2890, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lefevre-v-l-k-construction-no-cv-97-0056889-s-mar-1-1999-connsuperct-1999.