Leeor Builders v. Forehand CA2/4

CourtCalifornia Court of Appeal
DecidedOctober 6, 2022
DocketB316785
StatusUnpublished

This text of Leeor Builders v. Forehand CA2/4 (Leeor Builders v. Forehand CA2/4) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Leeor Builders v. Forehand CA2/4, (Cal. Ct. App. 2022).

Opinion

Filed 10/6/22 Leeor Builders v. Forehand CA2/4 NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS

California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION FOUR

LEEOR BUILDERS, INC., B316785

Plaintiff and Appellant, (Los Angeles County Super. Ct. No. 21STCV15470) v.

LEROY FOREHAND,

Defendant and Respondent.

APPEAL from a judgment of the Superior Court of Los Angeles County, Theresa M. Traber, Judge. Affirmed. Law Office of Yossi Noudel and Yossi Noudel for Plaintiff and Appellant. Retz & Aldover and Kirk J. Retz for Defendant and Respondent. INTRODUCTION Respondent LeRoy Forehand and his wife Elizabeth entered into a contract with appellant Leeor Builders, Inc. for home improvements.1 The contract contained an arbitration provision and a box on the first page requiring the initials of the “Owner” in order for the arbitration provision to be effective. Elizabeth’s initials appear in the box, as well as on the page containing the language of the arbitration provision, where initials of “Direct Contractor” also appear. In July 2020, after Elizabeth had passed away, LeRoy brought a demand for arbitration, initially seeking $299,999. Over Leeor’s objections, both the trial court and the Arbitrator ruled the arbitration provision was enforceable. In a closing brief submitted in the arbitration, LeRoy sought additional damages. The Arbitrator ultimately awarded LeRoy $869,000 in damages, plus costs, for a total of $902,749.38. The Arbitrator expressly found that Leeor had been on notice of the claims and of the additional damages sought. The trial court confirmed the award, rejecting Leeor’s argument that in exceeding the original demand, the Arbitrator’s award was fundamentally unfair. On appeal, Leeor contends the court erred in finding the parties had agreed to arbitrate because “Owner” necessarily meant both Elizabeth and LeRoy, and thus

1 Because they share a surname, we refer to LeRoy and Elizabeth by their first names.

2 Elizabeth’s initials alone were insufficient to render the arbitration provision effective. Leeor further contends the court impermissibly deferred to the Arbitrator on the question whether there existed an agreement to arbitrate. Finally, Leeor contends the court erred in confirming an award that substantially exceeded the original demand. We reject Leeor’s construction of the contract (which it drafted) as requiring both LeRoy’s and Elizabeth’s initials to render the arbitration provision effective. Accordingly, we agree with both the trial court and the Arbitrator that Elizabeth’s initials were sufficient. Additionally, because both the trial court and the Arbitrator concluded the parties had agreed to arbitrate, we need not address whether the court erred to the extent it deferred the issue of the existence of an arbitration agreement to the Arbitrator.2 Finally, we conclude the court was required to accept the Arbitrator’s factual finding that Leeor was on notice of the damages sought and discern no fundamental unfairness in the award. We therefore affirm.

STATEMENT OF RELEVANT FACTS A. The Parties Enter into an Agreement In June 2018, LeRoy and Elizabeth Forehand entered into a “Home Improvement Contract” with Leeor. The top of the first page of the agreement stated it was an

2 Similarly, we need not address Leeor’s challenge to the court’s alternative holding that LeRoy could enforce any arbitration agreement between Leeor and Elizabeth.

3 “AGREEMENT BETWEEN DIRECT CONTRACTOR AND PROPERTY OWNER.” Beneath this statement on the left-hand side appeared a stylized logo with the words “Greener Solution Group.”3 To the right of this logo was the word “And” followed by six blank lines, underneath which were instructions about what information was to be filled in the blanks. The first blank line was for “Property Owner’s Name,” and “Leroy [sic] & Elizabeth Forehand” was handwritten in that blank. Near the bottom of the first page was a box containing the following text: “ARBITRATION [¶] OWNER: Initial this box if you agree to arbitration. Review the ‘Arbitration of Disputes’ section attached.” The box was large enough to fit only one set of initials, and contained the initials “EF.” Underneath the box was a blank line over text stating: “(Owner Sign Here – Read notice on Arbitration, Mechanics Lien Warning).” Elizabeth’s signature appeared in this blank. Below that was another blank line over text stating: “(If more than one Owner, please Sign Here).” LeRoy’s signature appeared here. The “Arbitration of Disputes” section provided, in relevant part, that all claims relating to the contract would “be settled by binding arbitration in accordance with the construction industry arbitration rules of the American

3 Greener Solution Group is Leeor’s DBA.

4 Arbitration Association [AAA].”4 Near the bottom of the provision was a line stating, “I agree to arbitration” followed by an “x,” followed by an underlined blank space, under which “(Direct Contractor’s Initials)” was written. The initials “OA” were written in that blank.5 On the same line was another statement of “I agree to arbitration” followed by an “x” and an underlined blank space, under which “(Owner’s Initials)” was written. The initials “EF” were written in that blank. Below the space for initials, the contract provided that “in the event that Contractor and Owner have not each initialed the arbitration provision above, then it shall be conclusively agreed without a subsequent written agreement by all parties, that neither party agrees to arbitrate and the arbitration of disputes provision shall not be deemed to be a part of this agreement.”

B. LeRoy’s Demand for Arbitration; Arbitration Proceedings6 In July 2020, LeRoy filed a demand for arbitration, alleging Leeor should be liable for construction deficiencies in the work it performed at his house, for failing to complete

4 The entirety of the “Arbitration of Disputes” section was printed in bold, capital letters, omitted here for readability. 5 OA may have stood for “Oshri Azoulay,” a salesperson working for Leeor. 6 Except where noted, the facts in this section are taken from a recitation in the Arbitrator’s July 2021 Final Award.

5 the work required in the contract, and for committing elder abuse. The demand sought $299,999 in damages. In September 2020, the Arbitrator held a preliminary hearing and issued a scheduling order. According to an e-mail from the Arbitrator, Leeor objected to AAA’s jurisdiction and the Arbitrator acknowledged Leeor’s participation in arbitration would not be deemed a waiver of its right to object to jurisdiction; the Arbitrator encouraged Leeor to bring a motion to dismiss as soon as possible, either before the superior court or the Arbitrator. LeRoy filed a Statement of Claims, detailing his claims and damages. In November 2020, Leeor filed a “Response to the Statement of Claims,” asserting numerous affirmative defenses. Leeor also attempted to file a counterclaim including several third parties, but it was rejected as untimely and noncompliant with AAA rules. The Arbitrator held another preliminary hearing, and issued a second scheduling order, extending deadlines to comply with the initial scheduling order. In April 2021, LeRoy filed a motion to bar Leeor from introducing evidence at the arbitration hearing because Leeor had failed to comply with the Arbitrator’s scheduling orders, including directives to produce documents and identify witnesses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moncharsh v. Heily & Blase
832 P.2d 899 (California Supreme Court, 1992)
Asbestos Claims Facility v. Berry & Berry
219 Cal. App. 3d 9 (California Court of Appeal, 1990)
People Ex Rel. Department of Public Works v. Ward
258 Cal. App. 2d 15 (California Court of Appeal, 1968)
Meat Cutters Local Number 439 v. Olson Bros.
186 Cal. App. 2d 200 (California Court of Appeal, 1960)
Rael v. Davis
166 Cal. App. 4th 1608 (California Court of Appeal, 2008)
Emerald Aero, LLC v. Kaplan
9 Cal. App. 5th 1125 (California Court of Appeal, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Leeor Builders v. Forehand CA2/4, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leeor-builders-v-forehand-ca24-calctapp-2022.