LeChase Construction Services, LLC. v. Escobar Construction, Inc.

CourtDistrict Court, N.D. New York
DecidedSeptember 28, 2020
Docket3:18-cv-01021
StatusUnknown

This text of LeChase Construction Services, LLC. v. Escobar Construction, Inc. (LeChase Construction Services, LLC. v. Escobar Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LeChase Construction Services, LLC. v. Escobar Construction, Inc., (N.D.N.Y. 2020).

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF NEW YORK ___________________________________________ LeCHASE CONSTRUCTION SERVICES, LLC, Plaintiff, v. 3:18-CV-1021 (GTS/ML) ESCOBAR CONSTRUCTION, INC., Defendant. ___________________________________________ APPEARANCES: OF COUNSEL: ERNSTROM & DRESTE, LLP JOHN W. DRESTE, ESQ. Counsel for Plaintiff MATTHEW D. HOLMES, ESQ. 925 Clinton Square Rochester, NY 14604 WASSERMAN GRUBIN & ROGERS LLP ANDREW K. LIPETZ, ESQ. Counsel for Defendant 1700 Broadway, 16th Floor New York, NY 10019 GLENN T. SUDDABY, Chief United States District Judge DECISION and ORDER Currently before the Court, in this breach-of-contract action filed by LeChase Construction Services, LLC (“Plaintiff”) against Escobar Construction, Inc. (“Defendant”), is Plaintiff’s motion to strike Defendant’s Answer, enter default, and schedule a hearing related to damages, or, in the alternative, for partial summary judgment and to schedule a hearing related to damages. (Dkt. No. 55.) For the reasons set forth below, Plaintiff’s motion is granted. I. RELEVANT BACKGROUND A. Plaintiff's Complaint Generally, in its Complaint, Plaintiff asserts a claim for breach of contract against Defendant related to a subcontract that Plaintiff entered into with Defendant, in which Defendant agreed to perform certain subcontract work for Plaintiff related to Plaintiff’s building project. (Dkt. No. 1 [Pl.’s Compl.].) Plaintiff alleges that Defendant materially breached its obligations

under that subcontract by failing to complete various aspects of the contracted-for work, causing Plaintiff to incur “millions of dollars of costs and associated damages.” (Id.) B. Undisputed Material Facts on Plaintiff’s Motion for Summary Judgment Defendant did not provide a response to Plaintiff’s Statement of Material Facts as required by the Local Rules of this Court. See N.D.N.Y. L.R. 7.1(a)(3) (“The opposing party shall file a response to the Statement of Material Facts. The non-movant’s response shall mirror the movant’s Statement of Material Facts by admitting and/or denying each of the movant’s

assertions in a short and concise statement, in matching numbered paragraphs. Each denial shall set forth a specific citation to the record where the factual issue arises.”). Defendant’s failure to respond according to the Local Rules entitles the Court to deem the factually supported assertions in Plaintiff’s Statement of Material Facts to be admitted. See N.D.N.Y. L.R. 7.1(a)(3) (“The Court shall deem admitted any properly supported facts set forth in the Statement of Material Facts that the opposing party does not specifically controvert.”). Defendant’s current counsel made a notice of appearance in this matter shortly before Plaintiff filed its current motion. (Dkt. No. 53.) The Court granted two extensions of time (on

February 26, 2020, and March 25, 2020) to allow Defendant to respond to Plaintiff’s motion. (Dkt. Nos. 59, 61.) As of the date of this Decision and Order, Defendant has not made any response to Plaintiff’s motion. As a result, the Court has deemed as admitted the following 2 asserted facts, which are each supported by the admissible evidence and not controverted by any admissible record evidence.1 (Dkt. No. 55, Attach. 17 [Pl.’s Rule 7.1 Statement].) 1. Plaintiff is a construction contractor and was retained by EdR Maplewood LLC to construct approximately 500,000 square feet of apartments and townhouses for incoming

graduate and professional students at Cornell University in Ithaca, New York (“the Project”). 2. Plaintiff and Defendant entered into a subcontract dated May 26, 2017, pursuant to which Defendant would complete, among other things, drywall and associated work for the Project. 3. The subcontract specified that time was of the essence related to Defendant’s completion of its work under the subcontract. 4. Article 33 of the subcontract required Defendant to “diligently proceed

with all Subcontract Work, including any changed or disputed work directed in writing, notwithstanding that an outstanding change order request claim, or protest with respect to such Work is pending or unresolved or Contractor has withheld payment in good faith.” 5. The designated completion date for the Project was August 20, 2018. 6. Defendant abandoned the Project worksite on August 14, 2018. 7. Defendant returned to the Project worksite on or about August 15, 2018. 8. Defendant abandoned the Project worksite again on August 19, 2018. C. Parties’ Briefing on Plaintiff’s Motion

1 For the purposes of this Statement of Undisputed Material Facts, the Court has omitted Plaintiff’s asserted facts that involve previous decisions by this Court, because such facts are merely procedural. To the extent that Plaintiff intended to establish the Court’s findings as undisputed, the Court will discuss those findings as appropriate in its analysis in Part III of this Decision and Order. 3 1. Plaintiff’s Memorandum of Law Generally, in its motion, Plaintiff makes three arguments. (Dkt. No. 55 [Pl.’s Mem. of Law].) First, Plaintiff argues that the Court should strike Defendant’s Answer and enter a default judgment in favor of Plaintiff because Defendant willfully and in bad faith failed to comply with

the Court’s scheduling and discovery orders. (Id. at 8.) More specifically, Plaintiff argues that (a) the Court has already found that Defendant’s conduct was intentional, in bad faith, and in violation of the Court’s orders, (b) Defendant’s actions are well-documented in the record, (c) Defendant was aware of his obligations to the Court and Plaintiff, and has not offered any credible good faith explanation for failing to comply, and (d) any lesser sanction than dismissal would simply continue to delay the resolution of Plaintiff’s claim. (Id. at 10.) Plaintiff further argues that, because the Court has already found that Defendant materially breached the

subcontract related to the underlying claim in Plaintiff’s Complaint, the Court should find that liability has been established for the purposes of default judgment. (Id. at 10-11.) Second, Plaintiff argues that the Court should schedule an inquest to determine the amount of damages caused to Plaintiff as a result of Defendant’s material breaches of the subcontract because those damages are not a sum certain and an inquest will provide Defendant with an opportunity to defend itself against Plaintiff’s proof of damages. (Id. at 11.) Third, Plaintiff argues that, in the alternative to default judgment, the Court should grant partial summary judgment as to liability to Plaintiff on the breach-of-contract claim based on the

fact the Court already found in its prior Decision and Order that Defendant breached the subcontract. (Id. at 12-13.) 2. Plaintiff’s Failure to Respond 4 Defendant failed to file a response to Plaintiff’s motion by the deadline of May 26, 2020, and has not filed any response or a request to file a response out-of-time as of the date of this Decision and Order. (See generally Docket Sheet.) II. GOVERNING LEGAL STANDARDS

A. Standards Governing Sanctions Pursuant to Fed. R. Civ. P. 37(b)(2)(A) Federal Rule of Civil Procedure

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Guggenheim Capital, LLC v. Birnbaum
722 F.3d 444 (Second Circuit, 2013)
Agiwal v. Mid Island Mortgage Corp.
555 F.3d 298 (Second Circuit, 2009)
Cusamano v. Sobek
604 F. Supp. 2d 416 (N.D. New York, 2009)
Allen v. Comprehensive Analytical Group, Inc.
140 F. Supp. 2d 229 (N.D. New York, 2001)
Funk v. Belneftekhim
861 F.3d 354 (Second Circuit, 2017)
M.B. v. CSX Transportation, Inc.
299 F.R.D. 341 (N.D. New York, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
LeChase Construction Services, LLC. v. Escobar Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/lechase-construction-services-llc-v-escobar-construction-inc-nynd-2020.