LeChase Construction Services, LLC. v. Escobar Construction, Inc.

CourtDistrict Court, N.D. New York
DecidedDecember 16, 2019
Docket3:18-cv-01021
StatusUnknown

This text of LeChase Construction Services, LLC. v. Escobar Construction, Inc. (LeChase Construction Services, LLC. v. Escobar Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LeChase Construction Services, LLC. v. Escobar Construction, Inc., (N.D.N.Y. 2019).

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF NEW YORK __________________________________________ LeCHASE CONSTR. SERVS., LLC, Plaintiff, v. ESCOBAR CONSTR., INC., Defendant, 3:18-CV-1021 ESCOBAR CONSTR., INC., (GTS/ML) Counter-Claimant, LeCHASE CONSTR. SERVS., LLC; and LIBERTY MUT. INS. CO., Counter-Defendants. __________________________________________ APPEARANCES: OF COUNSEL: ERNSTROM & DRESTE, LLP JOHN W. DRESTE, ESQ. Counsel for Plaintiff/Counter-Defendants MATTHEW D. HOLMES, ESQ. 925 Clinton Square Rochester, New York 14604 REEVE BROWN PLLC CHARLES A. REEVE, ESQ. Co-Counsel for Defendant/Counter-Claimant 3380 Monroe Avenue, Suite 200 Rochester, New York 14618 ALARIO & FISCHER, P.C. DONALD C. FISCHER, ESQ. Co-Counsel for Defendant/Counter-Claimant 5 Adler Drive, Suite 4 East Syracuse, New York 13507 GLENN T. SUDDABY, Chief United States District Judge DECISION and ORDER Currently before the Court, in this breach-of-contract action filed by LeChase Construction Services, LLC (“Plaintiff”) against Escobar Construction, Inc. (“Counter- Claimant”), are (1) Counter-Claimant’s motion for reconsideration of the Court’s Decision and

Order of July 1, 2019, and for leave to amend its Answer with Counterclaims, and (2) Counter- Claimant’s counsels’ motions to withdraw as counsel. (Dkt. Nos. 27, 41, 42.) For the reasons set forth below, Counter-Claimant’s motion for reconsideration and for leave to amend is denied, and Counter-Claimant’s counsels’ motions to withdraw are granted. I. RELEVANT BACKGROUND A. Procedural History Because this Decision and Order is intended primarily for the review of the parties, the

Court will not recite in detail this action’s procedural history, except to note the following events: (1) on August 24, 2018, Plaintiff filed the original Complaint in this action (Dkt. No. 1); (2) on October 29, 2018, Counter-Claimant filed an Answer to the Complaint and Counter-Claim against Plaintiff and Liberty Mutual Insurance Company (collectively “Counter-Defendants”) (Dkt. No. 5); (3) on November 19, 2018, Counter-Defendants filed an Answer to the Counter- Claim (Dkt. No. 10); (4) on December 10, 2018, Counter-Defendants filed a motion for judgment on the pleadings pursuant to Fed. R. Civ. P. 12(c) or, in the alternative, a motion to dismiss Counter-Claimant’s counterclaims for failure to state a claim pursuant to Fed. R. Civ. P. 12(b)(6)

(Dkt. No. 13, Attach. 5); (5) on July 1, 2019, the Court granted Counter-Defendants’ motion for judgment on the pleadings (Dkt. No. 25 [Decision and Order filed July 1, 2019]); (6) on July 15, 2019, Counter-Claimant filed motion for leave to amend and for reconsideration (Dkt. No. 27); -2- (7) on November 8, 2019, Counter-Claimant’s counsel Donald Fischer filed a motion to withdraw as counsel (Dkt. No. 41); and (8) on November 12, 2019, Counter-Claimant’s counsel Charles Reeve filed a motion to withdraw as counsel (Dkt. No. 42). B. Parties’ Briefing on Counter-Claimant’s Motion for Leave to Amend and for Reconsideration 1. Counter-Claimant’s Memorandum of Law-in-Chief Generally, in its motion for leave to amend and for reconsideration, Counter-Claimant asserts four arguments. First, Counter-Claimant argues that the Court should excuse Counter-

Claimant’s suspensions of work because Plaintiff allegedly breached the Subcontract before Counter-Claimant suspended its work. (Dkt. No. 27, at 9 [Counter-Claimant’s Mem. of Law].) Counter-Claimant argues that Plaintiff breached the Subcontract by (1) hindering or delaying Counter-Claimant’s performance of the Subcontract in that it failed to provide the worksite in suitable condition, thus requiring Counter-Claimant to complete additional work, which significantly increased the total cost of the project, and (2) breaching the covenant of good faith and fair dealing in that it (a) failed to provide the worksite in suitable condition, (b) scheduled the

on-site work in an unreasonable sequence, and (c) arbitrarily responded to Counter-Claimant’s change order submissions. (Id. at 10.) Second, Counter-Claimant argues that Section 33 of the Subcontract does not prohibit Counter-Claimant from suspending its work when (1) Plaintiff did not request the additional work in writing, and (2) Plaintiff did not perform its obligations in good faith and fair dealing. (Id.) Counter-Claimant alleges that Plaintiff requested “[m]uch of [the] additional work” through

-3- “verbal directives,” and that Plaintiff did not perform its obligations in good faith and fair dealing for the aforementioned reasons. (Id.) Third, Counter-Claimant argues that its first suspension of work did not qualify as a default because, under Section 31(A) of the Subcontract, Plaintiff must notify Counter-Claimant

of Counter-Claimant’s deficiency under the Subcontract and provide Counter-Claimant with an opportunity to cure the deficiency, but Plaintiff did not provide Counter-Claimant with notice to cure, and Counter-Claimant cured any deficiency by resuming work within two days. (Id. at 12.) Fourth, Counter-Claimant argues that Plaintiff breached the Subcontract by failing to pay Counter-Claimant the money Plaintiff owed it based on the original Subcontract. (Id.) Counter- Claimant argues that it primarily suspended its work due to that breach, not Plaintiff’s failure to pay for additional work, and that this Court made an error by finding that Counter-Claimant

suspended its work for the second time “solely” based on Plaintiff’s refusal to pay for additional work. (Id. at 12-13.) 2. Counter-Defendants’ Opposition Memorandum of Law Generally, in Counter-Defendants’ memorandum of law, Counter-Defendants assert three arguments. (Dkt. No. 32, at 2 [Counter-Defendants’ Mem. of Law].) First, Counter-Defendants allege that Counter-Claimant has not satisfied the standard for reconsideration. (Id. at 3.) More specifically, Counter-Defendants argue that Counter-Claimant’s motion for reconsideration does not indicate an intervening change in controlling law, any new evidence that was not previously

available, or any reason to believe this Court must reconsider this case to remedy a clear error of law or to prevent manifest injustice. (Id. at 3, 7-9.)

-4- Second, Counter-Defendants argue that Counter-Claimant’s failure to meet the standard for reconsideration bars its ability to amend its claims. (Id. at 10.) More specifically, Counter- Defendants argue that, although a court may consider a motions for leave to amend in conjunction with a motion for reconsideration, the movant must still meet the standard for

reconsideration under Fed. R. Civ. P. 59(e) or 60(b), and the court may not grant relief solely on the basis of a motion to amend. (Id. at 5.) Third, Counter-Defendants argue that Counter-Claimant’s proposed amendments are futile. (Id. at 10.) More specifically, Counter-Defendants argue that, pursuant to Section 33 of the Subcontract, Counter-Claimant had an obligation to continue to perform work under the Subcontract, even if Counter-Claimant had a valid complaint regarding Counter-Defendants’ lack of payment, as well as an obligation to provide Counter-Defendants with seven-to-ten days’

written notice before suspending work due to lack of payment. (Id. at 10-12.) Counter- Defendants also argue that Counter-Claimant’s proposed amendments related to a mechanic-lien are not valid. (Id. at 13-14.) II. LEGAL STANDARDS GOVERNING THE MOTIONS A court may “take into account the nature of the proposed amendment in deciding whether to vacate the previously entered judgment.” Williams v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams v. Citigroup Inc.
659 F.3d 208 (Second Circuit, 2011)
United States v. Carluin Sanchez
35 F.3d 673 (Second Circuit, 1994)
Bruce C. Shrader v. Csx Transportation, Inc.
70 F.3d 255 (Second Circuit, 1995)
Delaney v. Selsky
899 F. Supp. 923 (N.D. New York, 1995)
Continental Ins. Co. v. Coyne Int'l Enter. Corp.
700 F. Supp. 2d 207 (N.D. New York, 2010)
Sequa Corp. v. GBJ Corp.
156 F.3d 136 (Second Circuit, 1998)
Farmer v. Hyde Your Eyes Optical, Inc.
60 F. Supp. 3d 441 (S.D. New York, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
LeChase Construction Services, LLC. v. Escobar Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/lechase-construction-services-llc-v-escobar-construction-inc-nynd-2019.