Lean Construction and Engineering Co.

CourtArmed Services Board of Contract Appeals
DecidedMay 18, 2016
DocketASBCA No. 59016
StatusPublished

This text of Lean Construction and Engineering Co. (Lean Construction and Engineering Co.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lean Construction and Engineering Co., (asbca 2016).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Lean Construction and Engineering Co. ) ASBCA No. 59016 ) Under Contract No. W56SGK-l 3-C-7073 )

APPEARANCE FOR THE APPELLANT: Mr. Abdul Ghafar Rassin Executive Director

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney L TC Brian J. Chapuran, JA MAJ Michael G. Pond, JA Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE PAUL

This is a timely appeal of a contracting officer's (CO's) decision partially terminating appellant, Lean Construction and Engineering Co.'s (Lean's) construction contract for default. The Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109, is applicable. A hearing was held at the Board's offices. Only entitlement is before us~ We deny the appeal.

FINDINGS OF FACT

1. On 15 April 2013, the Regional Contracting Center-Capital, Afghanistan, awarded Contract No. W56SGK-13-C-7073 to Lean for specified construction work to augment force protection measures at an Afghan National Army Logistics depot in the province of Kabul and to upgrade the base's western entry control point (ECP) to facilitate two-way traffic (R4, tab 1 at 1-2, tab 2 at 225).

2. Pursuant to CENTCOM Clause 952.232-0004, PAYMENT IN LOCAL CURRENCY (AFGHANISTAN) (AUG 2011), the contract was awarded on the basis of the local Afghan currency in a fixed-price amount of AFN 6,918,859.84. Based upon the exchange rate prevailing on the date the contract was awarded, this constituted approximately $142,297.20. (R4, tab 1 at 3-4, 7-8)

3. The contract incorporated by reference a host of Federal Acquisition Regulation (FAR) clauses. Those pertinent to this appeal include FAR 52.236-5(c), MATERIAL AND wORKMANSHIP (APR 1984 ), which provided, in pertinent part: "All work under this contract shall be performed in a skillful and workmanlike manner" (R4, tab 1 at 5). Also relevant is FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984 ), which stated:

(a) If the Contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified in this contract including any extensions, or fails to complete the work within this time, the Government may, by written notice to the Contractor, terminate the right to proceed with the work (or the separable part of the work) that has been delayed. In this event, the Government may take over the work and complete it by contract or otherwise, and may take possession of and use any materials, appliances, and plant on the work site necessary for completing the work. The Contractor and its sureties shall be liable for any damage to the Government resulting from the Contractor's refusal or failure to complete the work within the specified time, whether or not the Contractor's right to proceed with the work is terminated. This liability includes any increased costs incurred by the Government in completing the work.

(R4, tab 1at24) FAR 52.236-12, CLEANING UP (APR 1984), is also pertinent. It provided:

The Contractor shall at all times keep the work area, including storage areas, free from accumulations of waste materials. Before completing the work, the Contractor shall remove from the work and premises any rubbish, tools, scaffolding, equipment, and materials that are not the property of the Government. Upon completing the work, the Contractor shall leave the work area in a clean, neat, and orderly condition satisfactory to the Contracting Officer.

(Id.)

4. The contract also contained 13 attachments which described in minute detail the various technical requirements. They were listed as follows:

2 SOLICITATION ATTACHMENTS ATTACHMENT TABLE OF CONTENTS DOCUMENT TYPE DESCRIPTION PAGES DATE Attachment 1 TFP Standard Specifications 83 18 Jun 2009 Attachment 2 ANSF Construction Standards 10 5 Sep 2011 Attachment 3 Concrete Tower Design 22 NIA Attachment 4 Two Connex Guard Tower 15 NIA Attachment 5 Site Layout 1 NIA Attachment 6 Solar Panel Specs 10 NIA Attachment 7 Proposed ECP Drawing 1 NIA Attachment 8 Steel Panel Gates 10 NIA Attachment 9 Drop Gate Standard Design 6 NIA Attachment 10 Guard posts 1 NIA Attachment 11 Hesco Wall 7 NIA Attachment 12 Chain Link Fence Design 6 NIA Attachment 13 Statement of Work 7 NIA (R4, tab 1 at 32)

5. Attachment 1 contained the Coalition Joint Task Force Phoenix Engineers Standard Specifications (R4, tab 1 at 3 3-115). Part 1, "General Requirements," of the specification included the following, pertinent provisions:

4. Material: All materials shall be new and free of defects unless otherwise approved by the Contracting Officer Representative (COR). The Contractor shall remove defective materials from the site at no additional cost to the U.S. or Afghan Government.

6. Quality of Work: All work shall be conducted in a professional manner, in accordance with accepted methods of construction, as detailed in the attached specifications. U.S. and Afghan Government personnel on site shall make regular inspection of work as it progresses. When work is completed at each stage of the project, Contractor shall submit work for inspection and be signed off by U.S. or Afghan Government personnel on site.

3 9. Clean up: The Contractor shall clean up the work site at the end of every work day and upon project completion, including the removal of all debris and refuse from the site, to the satisfaction of the Contracting Officer Representative (COR).

(R4, tab l at 34-35)

6. Part 2 of the Standard Specifications was entitled "Site Construction." Subsection 2.1 of section 2.0, "GENERAL EXCAVATION," provided:

Contractor shall perform excavation of every type of material encountered within the limits of the project to the lines, grades, and elevations indicated and specified. Contractor shall transport satisfactory excavated materials and place in fill or embankment within the limits of the work. Contractor shall excavate unsatisfactory materials encountered within the limits of the work below grade and replace with satisfactory materials as directed. Contractor shall include such excavated material and the satisfactory material ordered as replacement in excavation. Contractor shall dispose surplus satisfactory excavated material not required for fill or embankment in areas approved for surplus material storage or designated waste areas. Contractor shall dispose unsatisfactory excavated material in designated waste or spoil areas. During construction, Contractor shall perform excavation and fill in a manner and sequence that will provide proper drainage at all times.

(R4, tab 1 at 42-43)

7. Part 3 of the Standard Specifications was entitled "Concrete." Section 1, also styled "Concrete," contained the following, relevant subsections:

1.1. Cement: 3000 PSI (20.0 MPa) Type I Portland Cement Concrete or equivalent will be utilized in the completion of this project. The Contractor will be required to prepare and place all concrete to include the specific requirements described below. The contractor shall submit the name and brand of concrete for the COR to approve.

4 1.2. Materials: Concrete will consist of the following ingredients only: 1.2.1. Portland Cement (Type 1) or equivalent 1.2.2. Clean Sand (O. l 5mm - 4.75mm) 1.2.3. Clean Course Aggregates (10mm-25mm crushed stone) 1.2.4. Clean Water 1.2.5. TF Phoenix Engineer Approved Chemical Admixtures

1.3. Concrete specifications: Basic Structural concrete shall at least meet these specifications: 1.3 .1. Designed strength = 21 MPa = 3000 psi 1.3.2. Minimum Cement content= 340kg/cubic meter 1.3.3. Maximum Water/Cement ratio= 0.68 by volume 1.3 .4. Maximum coarse aggregate size = 25mm 1.3.5.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
Lean Construction and Engineering Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/lean-construction-and-engineering-co-asbca-2016.