Le Sage v. Pitts

223 S.W.2d 347, 311 Ky. 155, 1949 Ky. LEXIS 1047
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedJune 7, 1949
StatusPublished
Cited by9 cases

This text of 223 S.W.2d 347 (Le Sage v. Pitts) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Le Sage v. Pitts, 223 S.W.2d 347, 311 Ky. 155, 1949 Ky. LEXIS 1047 (Ky. 1949).

Opinion

Van Sant, Commissioner

Affirming.

The action was instituted by appellant, Larry Le-Sage against appellee, H. V. Pitts, to recover damages sustained in falling twenty-five feet to the ground while engaged in work on the top of a wall of a warehouse being constructed for Southern States Co-Operative in Shelbyville. It was stipulated that at the time appellant was injured H. J. Steilberg and Son were general contractors for the erection of the warehouse; appellee had *157 a sub-contract, under the general contractor, to erect the walls; E. D. Cross and Sons had a sub-contract, under the general contractor, to erect the steel structure; and appellant was the Superintendent of E. D. Cross & Sons in charge of erecting the steel in the building.

The walls were constructed of concrete blocks 16" long, 8" wide, and 8" high. The plans or directions of the general contractor required appellee to leave openings in the walls in which to place structural steel trusses. The walls were constructed first and work thereon was suspended on the 13th day of June, 1946. At that time all of the Avail structure had been erected except the closing of gaps which invariably appear between the wall and the steel structure after the steel has been bolted into position. On July 2nd, the steel workers entered on the premises and on the following day had completed their work Avith the exception of erecting one truss, which was being placed into position for permanent anchoring, when appellant, in charge of the work, having climbed a ladder to the top of the wall, was standing on one of the blocks immediately adjoining the opening left for the truss. The block slipped from its position and “rolled” with him, throwing him off balance, and causing him to fall to the ground on the outside of the building. Mortar adhered to the block in question, indicating that it had been laid firmly in position when the wall first was erected.

The action was based on the allegation that prior to the date of the accident the defendant (appellee) negligently left a concrete block in the wall of the building in a dangerous and unsafe condition and the block was situated in a place and in a position where the defendant knew, or by the exercise of ordinary care could have known, that plaintiff would be working while installing a steel unit in the building, and that the plaintiff, while engaged in installing the steel unit, stepped on the concrete block in its unsafe and dangerous condition, and, because of such dangerous and unsafe condition, was caused to fall from the top of the wall to the ground beneath, resulting in the injuries complained of, all of which injuries and damages in the alleged amount of $40,000 were the direct and proximate result of the negligence of the defendant as related above.

*158 At the completion of the evidence introduced on behalf of appellant the Trial Judge sustained appellee’s motion for a peremptory instruction and directed the jury to find a verdict for appellee. Judgment was entered in accordance with the verdict. The Trial Judge wrote a short opinion setting forth his reasons for directing a verdict in favor of defendant, the gist of which is that the plaintiff failed to prove that any overt act or omission on the part of defendant caused the accident or caused the block which “rolled” with plaintiff to be loosened; that to conclude otherwise would require an inference to be drawn upon an inference, and would permit the jury to speculate in respect to the responsible cause of the accident. In support of this conclusion he cited Cross v. Clark, 304 Ky. 676, 201 S. W. 2d 884. Thus the sole question for our determination is whether the evidence introduced by appellant was sufficient to submit the case to the jury and to sustain its verdict if favorable to appellant.

In appellant’s brief, counsel has analyzed in concise and succinct language the evidence he relies on to support his theory of the case and has pointed out the inference he has drawn from such evidence. We will copy this analysis in its entirety and of our own accord will italicize the inferences that we may point out what we conceive to be fallacies contained in appellant’s argument and the soundness of the conclusion of the Trial Judge. Where we do not agree with counsel for appellant that the evidence supports the facts set forth in his analysis, we will make our own comments and enclose them in parentheses.

“(1) When appellant fell, the wall in question was in process of construction by appellee.” (We think this statement is not completely accurate, although we realize that it is made in good faith. Appellee had not fulfilled all of the duties required of him under his contract with the general contractor, but actually had completed the erection of the walls of the building. He was still under contract to return after the steel work was completed, in order to fill any gaps between the wall structure and the steel. Therefore, in so far as the placing of the concrete blocks was concerned, appellee’s obligation under his contract had been completed and his men had not *159 been on the premises for a period of approximately three weeks.)

“(2) Appellee knew that steel trusses were to be erected on the walls to support the roof.

“ (3) It was appellee’s duty to prepare for the erection of the trusses by leaving suitable openings in the walls where the trusses were to be placed.

“(4) If appellee’s employees, in constructing the walls, forgot to leave the openings for the trusses it would have been their duty to knock out the openings in the walls. (This statement is true but there was no evidence to support the theory that appellee’s employees forgot to leave the openings and there was no evidence to support the consequent theory that, after erecting the walls in solid formation, appellee’s servants knocked out openings which they should have left in the original erection of the walls.)

“ (5) It was the duty of appellee to fill in the openings after the trusses were set up. The openings were actually filled in by appellee about July 13, 1946. (The filling in referred to in the above statement was merely the spotting up of gaps left by failure of the steel structure to fit the exact form of the openings. This filling in was done on July 13, 1946.)

“(6) In setting steel trusses as was done in this ease it was customary and necessary for the steel men to stand on top of the walls.

“(7) In doing his job it was necessary for the appellant to stand on the concrete block which rolled and fell with him.

“(8) Appellee knew, or should have known, that a steel man would stand on that particular block in placing the truss in the opening adjacent to that block.

“(9) The block which caused appellant to fall appeared to him to be in a permanent position.

“ (10) When appellant stepped on the block in question it ‘rolled out from under’ him, which proves it was a loose block.”

Appellant summarizes the evidence he relies on as inferential proof that appellee caused the block to be *160 loosened and negligently permitted it to remain loose and dangerous in the following language:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

K.H. v. Cabinet for Health & Family Services
358 S.W.3d 29 (Court of Appeals of Kentucky, 2011)
Smith v. General Motors Corp.
979 S.W.2d 127 (Court of Appeals of Kentucky, 1998)
Kiser v. Bryant Electric
695 F.2d 207 (Sixth Circuit, 1982)
In Re Beverly Hills Fire Litigation
695 F.2d 207 (Sixth Circuit, 1982)
King v. South Kentucky Rural Electric Co-Operative Corp.
500 S.W.2d 793 (Court of Appeals of Kentucky, 1973)
Briner v. General Motors Corporation
461 S.W.2d 99 (Court of Appeals of Kentucky (pre-1976), 1970)
Klingenfus v. Dunaway
402 S.W.2d 844 (Court of Appeals of Kentucky (pre-1976), 1966)
Rollins v. Avey
296 S.W.2d 214 (Court of Appeals of Kentucky (pre-1976), 1956)
Central Lumber Co. v. Spark's Adm'r
296 S.W.2d 453 (Court of Appeals of Kentucky, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
223 S.W.2d 347, 311 Ky. 155, 1949 Ky. LEXIS 1047, Counsel Stack Legal Research, https://law.counselstack.com/opinion/le-sage-v-pitts-kyctapphigh-1949.