Le-Nature's, Inc. v. Latrobe Municipal Authority

913 A.2d 988, 2006 Pa. Commw. LEXIS 688
CourtCommonwealth Court of Pennsylvania
DecidedDecember 28, 2006
StatusPublished
Cited by9 cases

This text of 913 A.2d 988 (Le-Nature's, Inc. v. Latrobe Municipal Authority) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Le-Nature's, Inc. v. Latrobe Municipal Authority, 913 A.2d 988, 2006 Pa. Commw. LEXIS 688 (Pa. Ct. App. 2006).

Opinion

OPINION BY

Senior Judge FLAHERTY.

Le-Nature’s, Inc. (Le-Nature) appeals from the decision of the Court of Common Pleas of Westmoreland County (trial court) which sustained the preliminary objections filed by Latrobe Municipal Authority (Authority) and the City of Latrobe (City)(collectively, Latrobe) and dismissed Le-Nature’s complaint. We affirm.

Le-Nature is a Delaware corporation with its principal place of business at 11 Lloyd Avenue, Latrobe, Westmoreland County. In 2003, Le-Nature was planning *990 a construction project at its principal place of business. In July of 2003, Le-Nature hired TEDCO Construction (TEDCO) to be the general contractor for the project. TEDCO subsequently contracted with Shelly Drilling Company (Shelly) to drill and place caissons for the project. On July 16, 2003, TEDCO called Pennsylvania One Call (One Call) to determine whether there were any utility lines located where Shelly was scheduled to drill. 1 Latrobe did not respond to the One Call request. Shelly proceeded with the drilling on October 3, 2003 and struck and damaged a sewer line owned and/or operated by Latrobe.

On January 26, 2004, Le-Nature filed a writ of summons. On December 20, 2004, Le-Nature filed a complaint against Latrobe. Le-Nature contends in its complaint that TEDCO and Shelly were required under the One Call statute to determine whether any utility or other lines or facilities were located in the area of the project prior to any excavation and that Latrobe was required under the One Call statute to provide One Call with the location of all of their utility lines and other facilities and to respond in a timely manner to a request made pursuant to the One Call statute.

Authority thereafter filed preliminary objections to the complaint. Le-Nature amended the complaint on January 27, 2005. In its amended complaint, Le-Nature seeks damages in the amount of $1,030,255.35 against Latrobe due to its failure to respond to TEDCO’s One Call request resulting in damage to the sewer line owned and operated by Latrobe and causing significant delays in Le-Nature’s construction project. Le-Nature alleges that Latrobe was negligent and that Latrobe breached an implied contract in failing to perform the duties imposed on it by the One Call statute and such was the direct and proximate cause of the damages.

On February 1, 2005, Latrobe filed preliminary objections to the amended complaint. Latrobe contends that Le-Nature failed to set forth a breach of duty that Latrobe owed to Le-Nature and also raised governmental immunity.

On March 23, 2005, the trial court sustained Latrobe’s preliminary objections and dismissed Le-Nature’s amended complaint. The trial court determined that the One Call statute only establishes a duty between a contractor and the facility owners who own or operate the underground lines and that no duty is owed to an owner. The One Call statute defines a “contractor” as “any person who or which performs excavation or demolition work for himself or for another person.” 73 P.S. § 176. The term “facility owner” is defined under the Act as “the public utility or agency, political subdivision, municipality, authority, rural electric cooperative or other person or entity who or which owns or operates a line....” 73 P.S. § 176. “Owner” is defined under the Act as “any person who or which engages a contractor for construction or any other project which requires excavation or demolition work as herein defined.” 73 P.S. § 176. Therefore, the trial court determined that Latrobe did not owe a duty to Le-Nature because Le-Nature was not a contractor but an owner under the One Call statute. *991 Le-Nature timely appealed to the Superi- or Court, which subsequently transferred the matter to our Court. 2

Before our Court, Le-Nature contends that the trial court erred in sustaining Latrobe’s preliminary objections and dismissing its amended complaint. Le-Nature contends that Latrobe owes it a duty of care and that the duty arose when it created a foreseeable risk of harm by failing to respond to all notices and mark its underground lines. 3

In proving negligence, LeNature must show that there was a duty that was breached, that there was a causal connection between the breach of duty and the harm suffered, and that Le-Nature suffered actual harm. R.W. v. Manzek, 838 A.2d 801 (Pa.Super.2003). The first two prongs, i.e. duty and causal connection, are the only negligence issue before us.

The One Call statute created a duty which is owed by facility owners. Section 2 of the One Call statute states in pertinent part as follows:

It shall be the duty of each facility owner:
(5) Not more than two working days after receipt of a timely request therefore from a contractor or operator who identifies the site of excavation or demolition work he intends to perform:
(i) To mark, stake, locate or otherwise provide the position of the facility owner’s underground lines at the site within eighteen inches horizontally from the outside wall of such line in a manner so as to enable the contractor, where appropriate, to employ prudent techniques, which may include hand-dug test holes, to determine the precise position of the underground facility owner’s lines. This shall be done to the extent such information is available in the facility owner’s records or by use of standard locating techniques other than excavation.
(v) To respond to all notices through a One Call System, provided the request is made in the time frame set forth under this act. (Emphasis added).

73 P.S. § 177(5)(i), (5)(v). In accordance with the above statute, the facility owner has a duty to respond to “all notices” received through the One Call system and to mark its lines within two working days after receiving the call. However, Latrobe contends and the trial court found that Latrobe did not owe a duty to Le-Nature, as facility owners do not owe owners a duty under the One Call statute. We disagree.

Under Section 1 of the One Call statute, the purpose of the “One Call System” is defined to provide a telephone number for contractors or designers “or any other person covered by this act.” 73 *992 P.S. § 176. By expressly providing for “any other person” covered by the Act besides a contractor, the Act obviously was not intended to be limited to protecting only contractors and designers but also was intended to cover the other party necessarily involved in the excavation or demolition work associated with the project, the owner. Further, an owner could also have the same intent to do such work in the area of underground utilities without even using a contractor. Following the logic of Latrobe’s argument, an owner doing such work without a contractor who had one of its employees make the “One Call,” would not be covered by the statute unless it hired a contractor, architect, engineer or other designer to make the call for it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

T.B. Fry v. City of Philadelphia
Commonwealth Court of Pennsylvania, 2022
Grey Fox Plaza v. Herbert, Rowland and Grubic, Inc.
Commonwealth Court of Pennsylvania, 2017
D. Sobat and E. Sobat v. The Borough of Midland ~ Appeal of: E. Sobat
141 A.3d 618 (Commonwealth Court of Pennsylvania, 2016)
Falor v. Southwestern Pennsylvania Water Authority
102 A.3d 584 (Commonwealth Court of Pennsylvania, 2014)
McCarthy v. City of Bethlehem
962 A.2d 1276 (Commonwealth Court of Pennsylvania, 2008)
Metropolitan Edison Co. v. Reading Area Water Authority
937 A.2d 1173 (Commonwealth Court of Pennsylvania, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
913 A.2d 988, 2006 Pa. Commw. LEXIS 688, Counsel Stack Legal Research, https://law.counselstack.com/opinion/le-natures-inc-v-latrobe-municipal-authority-pacommwct-2006.