LDI Design, LLC v. Glenn G. Dukes

CourtCourt of Appeals of Tennessee
DecidedDecember 28, 2005
DocketM2003-02905-COA-R3-CV
StatusPublished

This text of LDI Design, LLC v. Glenn G. Dukes (LDI Design, LLC v. Glenn G. Dukes) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LDI Design, LLC v. Glenn G. Dukes, (Tenn. Ct. App. 2005).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE February 10, 2005 Session

LDI DESIGN, LLC, v. GLENN G. DUKES, ET AL.

Appeal from the Chancery Court for Williamson County No. 27028 Donald P. Harris, Judge

No. M2003-02905-COA-R3-CV - Filed December 28, 2005

This appeal arises from a multi-faceted business dispute. LDI Design, LLC, an engineering firm, was engaged by Dukes & Co., a real estate developer, to design plans for Spencer Hall, a planned subdivision in Franklin, Tennessee. LDI provided its engineering services, however, Dukes failed to fulfill its financial obligation to LDI. The parties negotiated a new agreement in April 1999 compromising a claim for damages by Dukes in consideration of a reduced fee for LDI’s services. After Dukes failed to honor the new agreement, LDI filed this action. Dukes filed an answer denying liability and filed a counter complaint for damages due to deficiencies in the plans prepared by LDI. Spencer Hall, LLC, owner of the Spencer Hall subdivision, while not a party to the contract, joined in the counter complaint claiming to be a co-developer of the project and the third-party beneficiary of the contract between LDI and Dukes. The trial court dismissed the counterclaim finding the renegotiated agreement between LDI and Dukes constituted an accord and satisfaction that barred Duke’s claims, and the evidence insufficient to prove any claim for damages against LDI. Although we find the new agreement did not bar Dukes’ claim, we affirm the trial court’s finding that the evidence failed to prove any claim for damages against LDI. We, therefore, affirm the dismissal of all claims against LDI.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Reversed in Part and Affirmed in Part

FRANK G. CLEMENT , JR., J., delivered the opinion of the court, in which WILLIAM C. KOCH , JR., P.J., M.S., and WILLIAM B. CAIN , J., joined.

K. Harlan Dodson, III and Michael B. Bressman, Nashville, Tennessee, for the appellants, Glenn G. Dukes, Dukes & Co., and Spencer Hall, LLC.

Helen F. Bean and Mark A. Baugh, Nashville, Tennessee, for the appellee, LDI Design, LLC.

OPINION

Dukes & Co. entered into a contract with LDI Design, LLC, in July of 1997, whereby LDI, an engineering firm, agreed to perform land planning services, landscape architecture, and civil engineering for six of twelve sections of a thirty-two acre, seventy-five lot residential development known as Spencer Hall. Dukes was identified in the contract as the “Client.” Spencer Hall, LLC, owner of the property known as Spencer Hall that is the subject of this litigation, was not a party to the contract. Nevertheless, Spencer Hall, LLC, claims it was a co-developer of the project and a third-party beneficiary of the contract between LDI and Dukes.

The project was divided into twelve sections. LDI was engaged to work on Sections Seven through Twelve. During the construction of Section Nine, Dukes complained that it had encountered problems due to LDI’s design. Following a series of discussions, the problems were rectified and, in April of 1999 Dukes and LDI entered into an agreement whereby Dukes settled its claims against LDI in consideration for which LDI agreed to accept a reduced fee for its services on the project. Dukes was to pay the balance owing on the reduced fee in installments, however, it failed to honor the agreement. As a consequence, on October 22, 1999, LDI submitted a letter demanding payment, to which Dukes responded with one payment of $1,000.

Following the October correspondence and the $1,000 payment by Dukes, the contractor engaged by Dukes, MRM construction company, commenced construction on Sections Eleven and Twelve of Spencer Hall. Following the commencement of construction, Dukes contended it encountered two major flaws in LDI’s engineering plans for Section Twelve. These alleged flaws included sewer pipes that Dukes alleged improperly intersected with a storm drainage pipe, and problems with a drainage ditch that contributed to flooding of the neighboring Clairmont subdivision.1 Having severed ties with LDI, Dukes hired another engineer, DBS and Associates (hereinafter DBS), to prepare revised plans for Section Twelve. Following a series of delays and cessation of construction, the reasons for which are hotly disputed, the City of Franklin approved the plans prepared by DBS, and construction of the Spencer Hall project was completed.

In the interim, LDI filed this action to recover the outstanding balance owed for its services. Dukes answered the complaint, denying liability, and filed a counterclaim, along with Spencer Hall, LLC, contending LDI was responsible for damages resulting from a faulty design.2 LDI answered the counterclaim denying liability generally and asserting the affirmative defense of accord and satisfaction based on the April 1999 agreement.

The trial court found an accord and satisfaction between LDI and Dukes barred Dukes’ claims. The trial court further found Spencer Hall, LLC, failed to prove any claim for damages. Dukes and Spencer Hall, LLC, appeal contending the April 1999 accord was limited to Section Nine and did not constitute a bar to claims attributable to Section Twelve, thus they are entitled to recover damages resulting from LDI’s errors and omissions.

1 W e stress that attribution of the defects to LDI is simply Dukes & Co.’s allegation. Both parties seem to agree that these problems were present, but the parties dispute who is responsible for the problems.

2 The Answer and Counterclaim were filed by Dukes & Co. and Spencer Hall, LLC., but the contract in question was only between Dukes & Co. and LDI.

-2- STANDARD OF REVIEW

The standard of review of a trial court’s findings of fact is de novo and we presume that the findings of fact are correct unless the preponderance of the evidence is otherwise. Tenn. R. App. P. 13(d); Rawlings v. John Hancock Mut. Life Ins. Co., 78 S.W.3d 291, 296 (Tenn. Ct. App. 2001). For the evidence to preponderate against a trial court’s finding of fact, it must support another finding of fact with greater convincing effect. Walker v. Sidney Gilreath & Assocs., 40 S.W.3d 66, 71 (Tenn. Ct. App. 2000); The Realty Shop, Inc. v. R.R. Westminster Holding, Inc., 7 S.W.3d 581, 596 (Tenn. Ct. App. 1999). Where the trial court does not make findings of fact, there is no presumption of correctness and we “must conduct our own independent review of the record to determine where the preponderance of the evidence lies.” Brooks v. Brooks, 992 S.W.2d 403, 405 (Tenn. 1999). We also give great weight to a trial court’s determinations of credibility of witnesses. Estate of Walton v. Young, 950 S.W.2d 956, 959 (Tenn. 1997); B & G Constr., Inc. v. Polk, 37 S.W.3d 462, 465 (Tenn. Ct. App. 2000). Issues of law are reviewed de novo with no presumption of correctness. Nelson v. Wal-Mart Stores, Inc., 8 S.W.3d 625, 628 (Tenn. 1999).

ACCORD AND SATISFACTION

The trial court dismissed Dukes’ claim finding an accord and satisfaction was reached when the parties settled a previous claim by Dukes that it had incurred damages due to design errors by LDI.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brooks v. Brooks
992 S.W.2d 403 (Tennessee Supreme Court, 1999)
Estate of Walton v. Young
950 S.W.2d 956 (Tennessee Supreme Court, 1997)
Walker v. Sidney Gilreath & Associates
40 S.W.3d 66 (Court of Appeals of Tennessee, 2000)
B & G Construction, Inc. v. Polk
37 S.W.3d 462 (Court of Appeals of Tennessee, 2000)
Realty Shop, Inc. v. RR Westminster Holding, Inc.
7 S.W.3d 581 (Court of Appeals of Tennessee, 1999)
McClenahan v. Cooley
806 S.W.2d 767 (Tennessee Supreme Court, 1991)
Inland Equipment Co. v. Tennessee Foundry & MacHine Co.
241 S.W.2d 564 (Tennessee Supreme Court, 1951)
Helms v. Weaver
770 S.W.2d 552 (Court of Appeals of Tennessee, 1989)
Cole v. Henderson
454 S.W.2d 374 (Court of Appeals of Tennessee, 1969)
Rawlings v. John Hancock Mutual Life Ins. Co.
78 S.W.3d 291 (Court of Appeals of Tennessee, 2001)
Nelson v. Wal-Mart Stores, Inc.
8 S.W.3d 625 (Tennessee Supreme Court, 1999)
Pinney v. Tarpley
686 S.W.2d 574 (Court of Appeals of Tennessee, 1984)
R.J. Betterton Management Services, Inc. v. Whittemore
733 S.W.2d 880 (Court of Appeals of Tennessee, 1987)
United American Bank of Memphis v. Gardner
706 S.W.2d 639 (Court of Appeals of Tennessee, 1985)
Quality Care Nursing Services, Inc. v. Coleman
728 S.W.2d 1 (Tennessee Supreme Court, 1987)
Lindsey v. Lindsey
930 S.W.2d 553 (Court of Appeals of Tennessee, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
LDI Design, LLC v. Glenn G. Dukes, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ldi-design-llc-v-glenn-g-dukes-tennctapp-2005.