Lazovitz, Inc. v. Saxon Construction, Inc., Defendant-Third Party v. The Klett Organization, Architects, P.A., Third Party

911 F.2d 588, 1990 U.S. App. LEXIS 15738, 1990 WL 120737
CourtCourt of Appeals for the Third Circuit
DecidedSeptember 10, 1990
Docket89-5403
StatusPublished
Cited by6 cases

This text of 911 F.2d 588 (Lazovitz, Inc. v. Saxon Construction, Inc., Defendant-Third Party v. The Klett Organization, Architects, P.A., Third Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lazovitz, Inc. v. Saxon Construction, Inc., Defendant-Third Party v. The Klett Organization, Architects, P.A., Third Party, 911 F.2d 588, 1990 U.S. App. LEXIS 15738, 1990 WL 120737 (3d Cir. 1990).

Opinion

CLARK, Circuit Judge:

FACTS

Lazovitz, Inc. (Lazovitz) as general contractor entered into three cost-plus construction contracts covering three different projects: Florida Club Care Center, Florida Club Apartments, and Grammercy Park Nursing Care Center. On paper, each project is owned by a limited partnership registered in Florida that carries the name of the project; however, the people behind all three projects are the same. In this opinion, the term “owner” refers to the common interest behind the three projects. To accomplish certain plastering and drywall work, Lazovitz entered into three subcontracts with Saxon Construction, Inc. (Saxon) for work on each of the three projects. Each subcontract was project specific. Insofar as they are at issue in this appeal, the terms of the three general contracts are the same and the terms of the three subcontracts are the same. On each of the three projects, Saxon allegedly breached its respective subcontract by failing to complete work as prescribed in the architect’s plans. Lazovitz discharged Saxon and hired a replacement subcontractor to complete the work. To ensure that the substitute work was accomplished in a timely fashion, the owner “advanced” La-zovitz the money needed to pay the substi *590 tute subcontractor for the repairs. Lazo-vitz and the owner executed separate supplemental letter agreements for each of the three projects to govern their respective obligations regarding the advance. The three agreements substantively are the same.

Pursuant to its understanding of its obligation under the supplemental agreements, Lazovitz filed a nine count complaint against Saxon for breach of contract and trespass on each of the three construction projects; Lazovitz alleged that Saxon breached the contract by failing to complete performance. Saxon counterclaimed on each of the subcontracts with Lazovitz for the amount due alleging substantial performance of the subcontract. Lazovitz answered that Saxon had breached the contract and claimed a set-off as an affirmative defense to Saxon’s counterclaim asserting the same damages alleged in its complaint. During discovery, Saxon obtained a copy of the supplemental agreement governing the Florida Club Care project; however, it did not obtain the supplemental agreements covering the other two projects. Saxon moved for summary judgment with respect to the counts concerning the Florida Club Care project, claiming that the supplemental agreement showed that Lazovitz had suffered no damages. On June 10, 1987, the district court granted Saxon’s motion. The case went to trial on November 2, 1987; in the interim, however, Saxon obtained copies of the remaining two supplemental agreements. At the start of the trial, Saxon made an ore terms motion for summary judgment on the counts concerning the remaining two projects. 1 The district court granted the motion and the trial proceeded on Saxon’s counterclaim for the balance due under the contract with Lazovitz claiming breach of contract and set-off.

In deciding the motions for summary judgment, the district court considered the underlying cost-plus contract and the supplemental agreement and concluded that Lazovitz had a conditional obligation to repay the owner. Since the owner had paid all the costs, including the additional amount necessary to effect the repairs, and had paid the agreed upon “plus,” the district court reasoned that Lazovitz had suffered no damage. The court also reasoned that since Lazovitz’s repayment obligation was conditional and since the owner had made no demand for repayment, the possibility that Lazovitz might at sometime in the future be held liable for the advanced funds was too speculative to give rise to any compensable damage. The court concluded that without any damages, Lazovitz did not have a cause of action.

At the trial on Saxon’s counterclaim, the court awarded Saxon the contract price minus certain set-offs. 2 The district court disallowed Lazovitz’s claims for breach of contract and setoff to obtain substitute performance on the same theory upon which it had relied to grant summary judgment. After trial, Saxon moved to tax costs against Lazovitz; the district court granted the motion concluding that Saxon was the prevailing party.

The gravamen of appellant’s claim is that the district court erred by interpreting the written supplemental agreement as a conditional obligation. Lazovitz maintains that the agreement is clear on its face that it is obligated to return the money advanced. In support of its contention, Lazovitz submitted the affidavit of the owner’s general partner who asserted that the money advanced to Lazovitz was to be returned. Saxon offered nothing to rebut the affidavit. Appellant also claims that even if the document is not clear on its face, the affidavit creates a genuine issue of material fact which precludes summary judgment. *591 Appellee asserts that since the district court heard appellant’s breach of contract and set-off claim at trial, the issue of whether the court properly granted summary judgment is moot.

DISCUSSION

A. Summary Judgment Was Not Appropriate.

The district court concluded that La-zovitz could not sue Saxon because Lazo-vitz had suffered no damages. In granting summary judgment, the district court relied on a line of Florida construction cases which hold that the non-breaching party “must show actual expenditures occasioned by the breach.” Tuttle/White Constructors, Inc. v. Montgomery Elevator Co., 385 So.2d 98, 100 (Fla.App. 5 Dist.1980); Young v. Johnston, 475 So.2d 1309, 1313 (Fla.App. 1 Dist.1985); R.K. Cooper Builders, Inc. v. Free-Lock Ceilings, Inc., 219 So.2d 87, 88-89 (Fla.App. 3 Dist.1969). This notion coupled with the general theory that damages are to place the injured party in as advantageous a position as he would have been had his contract not been broken, Popwell v. Abel, 226 So.2d 418, 422 (Fla.App. 4 Dist.1969); Fla.Jur.2d § 10 (1982), apparently led the district court to conclude that Lazovitz had suffered no injury. Thus, the district court would require a plaintiff to show current net out-of-pocket loss, concluding that any other losses would be too speculative to support their recovery as damages. These cases do not support that conclusion. They simply stand for the proposition that to recover damages, the amount of loss occasioned by the breach must be proved with reasonable certainty. Florida courts allow contractors to recover when necessary repairs, occasioned by a breach, have not been started; the contractor must be able to show the anticipated cost with reasonable certainty. Lynch v. Florida Min. & Materials Corp., 384 So.2d 325, 327-28 (Fla.App. 2 Dist.1980); B & J Holding Corp. v. Weiss, 353 So.2d 141, 143 (Fla.App. 3 Dist.1978). These “losses” are no less speculative than the ones at issue in the instant case and are recoverable under Florida law.

Additionally, the district court misapprehended the function of a cost-plus contract. Cost-plus contracts are often not competitively bid and are frequently used when the owner lacks the special expertise needed to select competent subcontractors and to coordinate the project. Jones v. J.H. Hiser Constr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cafaro v. Zois
693 F. App'x 810 (Eleventh Circuit, 2017)
Waters v. International Precious Metals Corp.
237 F.3d 1273 (Eleventh Circuit, 2001)
Waters v. Intl. Precious Metals
237 F.3d 1273 (Eleventh Circuit, 2001)
National Constructors, Inc. v. Ellenberg
681 So. 2d 791 (District Court of Appeal of Florida, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
911 F.2d 588, 1990 U.S. App. LEXIS 15738, 1990 WL 120737, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lazovitz-inc-v-saxon-construction-inc-defendant-third-party-v-the-ca3-1990.