Layne v. City of Windsor

442 S.W.2d 497, 1969 Mo. LEXIS 827
CourtSupreme Court of Missouri
DecidedJune 9, 1969
DocketNo. 53763
StatusPublished
Cited by8 cases

This text of 442 S.W.2d 497 (Layne v. City of Windsor) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Layne v. City of Windsor, 442 S.W.2d 497, 1969 Mo. LEXIS 827 (Mo. 1969).

Opinion

WILLIAM E. BUDER, Special Judge.

Plaintiff appeals from a judgment for defendant where trial was to the Court without a jury. Plaintiff sought to recover damages for the amount of $20,000.00 on breach of contract from the City of Windsor, a city of the fourth class, located in Henry County, Missouri. Article V, Section 3, Constitution of Missouri, V.A.M. S., and the amount in dispute vest jurisdiction in this Court.

Plaintiff, a registered professional engineer, was employed by defendant under a contract, which was incorporated and set forth in a duly enacted ordinance, to prepare and submit plans and estimates for a sewer extension project to be constructed in the city and to direct and supervise the construction thereof under a master plan. Upon completion and submission of preliminary plans and estimates, construction on the sewer extension project was to proceed after a proposal for a bond issue therefor was adopted by the voters of the city. The ordinance was enacted on November 6, 1961, and the bond issue proposal was first submitted to the voters on May 18, 1964, but it was not adopted. Plaintiff then performed some adjustments and revisions to effect a reduction in cost of construction on the project and such proposal, which was submitted to the voters on October 20, 1964, also failed. Plaintiff had received $1,500.00 from defendant for his services. During the month of January, 1965, the board of aldermen adopted a resolution wherein plaintiff’s entire program was abandoned and notification thereof was had upon plaintiff. Sometime later another registered professional engineer was employed by defendant and a subsequent bond issue was approved by voters. The project then progressed under direction of the second engineer and under his plan and estimates.

The evidence shows that plaintiff and his staff prepared and completed plans, specifications and surveys for the preliminary report and secured estimates of cost thereon and the same all were embraced within the initial bond issue proposal. After the initial bond issue failed to pass, plaintiff met and conferred with members of the board of aldermen and some adjustments and revisions were achieved in plaintiff’s plan and estimates. Essentially these provided for an alternate alignment system to put a lagoon closer to the city and to put another lagoon in the northwest part of the city. City officials also requested plaintiff to attend a hearing before the Water Pollution Board at Columbia, Missouri, and this board found his preliminary plan and estimates to be economical and feasible. Plaintiff and his staff performed numerous and varied other services with respect to the project which extended over a three year period and he now contends he is entitled to payment under a schedule issued by the Society of Professional Engineers.

Pertinent portions of the ordinance relating to the contract of employment appear, in part, as follows:

“Section 1. * * * (D) After the presentation of the preliminary report the Consulting Engineer will attend a mass meeting to answer questions and present the Preliminary Master Plan estimate and report to the Citizens of the Community. The Board of Aldermen then shall submit bond issues for approval to the legal voters of Windsor, Missouri, for financing sewer system extension.”
[499]*499“Section 2. (A) That said Mark B Layne be also employed by the City of Windsor, Missouri, in the event such bond issues be approved by the legal voters of said City, to make and prepare complete plans, profiles and specifications and construction estimates for the construction of said sewer system extension and to do all other necessary engineering work in connection with the construction thereof, including the supervision of the construction of said improvements. This section to become effective only after the approval of the bonds by the voters.”
“(B) If after approval by the legal voters of Bond Issues for the financing of the project or parts thereof, sections of engineering services are delayed from causes beyond the control of the engineer such as Federal or State restrictions due to war or other causes, this agreement shall be a continuing contract, for engineering services on the project.”
“(C) The Engineer shall make revisions of the preliminary plans, report and estimate from time to time pending subsequent bond issues, or changes in Federal or State Regulations without additional expense to the City.” * * *

Plaintiff’s first assignment of error is directed to the holding by the trial court that the contract terminated by virtue of its own terms. Plaintiff takes the position that under the terms of the contract defendant was obligated to submit two additional bond issue proposals to voters after the first or initial submission had been rejected. This is based primarily upon the words “bond issues” appearing in Section 1 (D) and “subsequent bond issues” appearing on Section 2 (C) of the contract. The words “bond issues” mean, of course, more than one bond issue and actually more than one was submitted to voters. The words “subsequent bond issues,” being contained in Section 2, apply only in the event a bond issue was approved. The entire contract including these words must be construed, however, under controlling authorities relating to contracts of this character. The case of Kansas City v. City of Raytown, Mo., 421 S.W.2d 504, does concern a situation where a city of the fourth class sought cancellation of a contract for sewer construction after two unsuccessful bond elections were held. Although the said city did not prevail in that case, the terms of the cooperative agreement involved therein are entirely different than those presented in this case. The cases thus are clearly and readily distinguishable. Here the preliminary stages, as provided in Section 1, had progressed and were completed. The voters rejected bond issue proposals, which embraced plaintiff’s plans and estimates, on two separate occasions. No funds then became available for sewer construction and Section 2 of the contract did not become effective. The terms of the contract are very explicit in this respect. In Fulton v. City of Lockwood, Mo., 269 S.W.2d 1, 7, the following language appears and it is applicable in the present case.

“ * * * It is based upon the city incurring an indebtedness far in excess of any general obligation bonds the city could lawfully issue at that time under the applicable statutory and constitutional provisions so far as we have discovered. * * * Under said provisions municipalities may not spend or contract to spend, become indebted, in an amount exceeding the income and revenue provided for the calendar year involved, plus any unencumbered balances from previous years; are forbidden to anticipate the general revenues of subsequent years, and the permissible additional general obligation bonds must be authorized by the required two-thirds vote of the qualified electors.” It is apparent that the contract could not be carried out without approval by the voters. Upon defeat of two separate bond issue proposals, Section 2 did not become effective and was null and void. The con-tractural relationship then ceased to exist. Under these circumstances, no further obligation on the part of defendant remained in existence and defendant was wholly [500]*500without authority to proceed with the project. Needles v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Client Services, Inc. v. City of St. Charles
182 S.W.3d 718 (Missouri Court of Appeals, 2006)
Rice v. Huff
22 S.W.3d 774 (Missouri Court of Appeals, 2000)
Kennedy v. City of St. Louis
749 S.W.2d 427 (Missouri Court of Appeals, 1988)
McCarty v. City of Kansas City
671 S.W.2d 790 (Missouri Court of Appeals, 1984)
Smith v. City of De Soto
634 S.W.2d 204 (Missouri Court of Appeals, 1982)
Tuxedo Cheverly Volunteer Fire Co. v. Prince George's County
385 A.2d 819 (Court of Special Appeals of Maryland, 1978)
Missouri International Investigators, Inc. v. City of Pacific
545 S.W.2d 684 (Missouri Court of Appeals, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
442 S.W.2d 497, 1969 Mo. LEXIS 827, Counsel Stack Legal Research, https://law.counselstack.com/opinion/layne-v-city-of-windsor-mo-1969.