Layne-Atlantic Co. v. Koppers Co.

201 S.E.2d 609, 214 Va. 467, 14 U.C.C. Rep. Serv. (West) 70, 1974 Va. LEXIS 162
CourtSupreme Court of Virginia
DecidedJanuary 14, 1974
DocketRecord 8240
StatusPublished
Cited by11 cases

This text of 201 S.E.2d 609 (Layne-Atlantic Co. v. Koppers Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Layne-Atlantic Co. v. Koppers Co., 201 S.E.2d 609, 214 Va. 467, 14 U.C.C. Rep. Serv. (West) 70, 1974 Va. LEXIS 162 (Va. 1974).

Opinion

Harrison, J.,

delivered the opinion of the court.

Koppers Company, Inc. sought to recover a judgment against Layne-Atlantic Company in the amount of $14,580.95 for certain fiber glass well casing sold to Layne. The defendant denied liability, alleging failure of consideration and breach of warranty as to the fitness of the casing. Layne also counter-claimed against Koppers for damages alleged to have been suffered because of such breach. At the conclusion of all the evidence the trial court struck the evidence of Layne with reference to its counterclaim, and entered summary judgment for Koppers.

*468 Involved here is an injection well which the United States Geological Survey desired to build in Norfolk. Its purpose was to test the feasibility of storing fresh water underground. The plans and specifications for sinking and piping the well were prepared by U. S. G. S. The contract was a fixed price one providing that if the well failed to produce water of a particular quality it would have to be abandoned and a new one drilled at the contractor’s expense.

The specifications as originally drafted by Donald Brown, a geologist employed by U. S. G. S., provided that the topmost 230 feet of the well casing (hereinafter called pipe) be 18" in diameter and the remaining pipe be 8" in diameter. Brown consulted with Stuart Adler, a Koppers’ representative, who recommended that the 18" pipe be .5" thick. All bids received on the original solicitations were rejected as too high.

U. S. G. S. then decided, after further consultation between Brown and Adler, to reduce the footage of 18" pipe from 230 feet to about 125 feet and to reduce the wall thickness to .3", thus effecting a savings in cost. The specifications were changed accordingly, and a new solicitation was issued. Layne’s bid was accepted, and the contract was executed. Layne then purchased the pipe from Koppers.

There are numerous exhibits and voluminous testimony concerning the manner in which the well was to be constructed and the pipes installed. It suffices for our purposes to say that the well was 1010 feet deep. From the ground level down to a depth of about 85 feet, a 34" diameter steel pit casing was cemented into place. Within the steel pit casing (as far as it extended) and from the ground level down to a depth of about 125 feet there was 18" fiber glass pipe. From the level of 125 feet down to a depth of about 900 feet below the ground surface there was 8" fiber glass pipe. From the 900-foot level to the level of about 1000 feet there was a stainless steel screen welded to the end of the 8" pipe, and the last 10-foot section was a blank stainless steel pipe. A transition pipe was installed to effect the connection of the 8" and 18" pipes. The hole in which the pipe is installed is of necessity drilled larger than the pipe to be installed therein (36" in diameter where the steel casing was to be installed, 32" in diameter from the bottom of the casing to a depth of about 125 feet below land surface and 18" in diameter from a depth of approximately 125 feet to the total depth). The space between the pipe and the side or wall of the hole is known as the annular space. Within the annular space, as well as within the installed pipe itself, drilling mud is used and *469 kept circulating by a pump during drilling operations. This mud must be of sufficient density to prevent a caving in of the walls of the hole.

The specifications provided that upon reaching the required depth of 1010 feet a filter pack (gravel) be placed extending from 5 feet below the bottom of the lowest stainless steel screen to 10 feet above the top of the uppermost screen; that on top of the filter pack there be placed a 10-foot layer of fine sand and silt to insure that the cement grout (to be thereafter emplaced on the layer of sand) did not infiltrate downward into the filter pack materials; and that after the filter pack, and the overlying 10-foot layer of fine sand were em-placed, the remainder of the annular space to the ground surface be filled with cement grout. The purpose of this grout is to support the pipe which it surrounds and eliminate external pressures upon the pipe.

The specifications further provided that the filter pack be installed as soon as possible after the casings and screens were installed, and that the contractor secure from the government representative approval of the method used to emplace the filter pack and of the manner in which the cement grout was to be injected into the annular space. It directed that upon completion of the screening, gravel packing and cementing, no work be done on the well for 24 hours after cementing is completed; and thereafter that the well be pumped and surged by air to clear it of mud and develop it.

The construction of the well, including the installation of all pipe, proceeded uneventfully through the emplacement of the required thickness of fine sand above the filter pack. It was at this point that employees of Layne “pumped the line”. This is accomplished by pumping air into a 2" fine that was run into a 4" fiber glass pipe injection fine which paralleled the 18" pipe for approximately 105 feet and was connected thereto by an L joint. The pumping lowered the water inside the 18" pipe to a point 51 feet below the surface. At that time the water in the annular space outside the 18" pipe stood at ground level.

The pumping continued for several minutes after the 51-foot measurement, and at this point a section of the 18" pipe collapsed. The section that collapsed was about 39 feet long, the third section of the pipe from the top. As a result of the collapse the well had to be abandoned, cemented up and a new well constructed by Layne.

This controversy revolves around the amount of pressure exerted on the pipe and the fact that Layne “pumped the well” before filling *470 with cement grout the annular space between the pipe and the wall of the drill hole. Koppers contends that Layne’s pumping the well prematurely was in violation of the contract and that such action produced excessive external pressures upon the pipe in that the water level on the inside of the 18" pipe was lowered while the water and drilling mud in the 36" annular space around the outside of the pipe remained at ground level. It says that the purpose of filling the annular space from the bottom of the well to ground surface with cement is to efiminate such pressure, for once the cement hardens it supports the pipe and reduces the pressure thereon to zero. This, it says, is the reason for the specification that the cement must set for 24 hours before the well is to be pumped.

Koppers further claims that Layne took a calculated risk and was in effect testing the well to see if it was producing and that it did this prior to the cement grouting to be in a position to salvage the pipe if the well had to be abandoned. After pipe is cemented it cannot be pulled out or reclaimed. Ralph Simmons, field supervisor of Layne and in charge of the construction, admitted that it would be “taking a gamble” to cement before pumping as called for in the contract. His explanation was: “Well, not trying to go against the contract, but that’s a standard procedure with all well drilling. That is one of the main things that you do in any well regardless of what the contract calls for____”

Robert R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cooper Industries, Inc. v. Melendez
537 S.E.2d 580 (Supreme Court of Virginia, 2000)
Bayliner Marine Corp. v. Crow
509 S.E.2d 499 (Supreme Court of Virginia, 1999)
Rule v. Best Industries Inc
Fourth Circuit, 1997
Stratford v. Jefferson Jones, Inc.
37 Va. Cir. 277 (Richmond County Circuit Court, 1995)
White Consolidated Industry, Inc. v. Swiney
376 S.E.2d 283 (Supreme Court of Virginia, 1989)
Featherall v. Firestone Tire and Rubber Co.
252 S.E.2d 358 (Supreme Court of Virginia, 1979)
Turner v. Manning, Maxwell & Moore, Inc.
217 S.E.2d 863 (Supreme Court of Virginia, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
201 S.E.2d 609, 214 Va. 467, 14 U.C.C. Rep. Serv. (West) 70, 1974 Va. LEXIS 162, Counsel Stack Legal Research, https://law.counselstack.com/opinion/layne-atlantic-co-v-koppers-co-va-1974.