Laws v. Parker Petroleum Co.

237 S.W.2d 398, 1951 Tex. App. LEXIS 1530
CourtCourt of Appeals of Texas
DecidedFebruary 21, 1951
Docket9946
StatusPublished
Cited by3 cases

This text of 237 S.W.2d 398 (Laws v. Parker Petroleum Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Laws v. Parker Petroleum Co., 237 S.W.2d 398, 1951 Tex. App. LEXIS 1530 (Tex. Ct. App. 1951).

Opinion

HUGHES, Justice.

Preston Laws, appellant, and Parker Petroleum Company, appellee, entered into a written contract by the terms of which appellant agreed to drill a well for oil and gas in Caldwell County to a depth of 2200-feet, unless appellee directed that drilling cease at a lesser depth. After drilling to 2104 feet a cavity of some sort was encountered, difficulties arose, arguments ensued, and the well was never completed.

. Appellant sued to recover the contract price of $2.25 per foot for the number of feet actually drilled, alleging that his failure to complete the well to the contract depth was because of appellee’s breach of the provision in the contract requiring it to “furnish the mud weighting material at company’s expense if and when same is found necessary.”

Reasonable attorney’s fees under Art. 2226, Vernon’s Ann.Civ.St., were also' sought.

Appellee answered this suit by admitting the execution of the drilling contract and *399 the drilling of the well to 2107 feet, and alleging that appellant abandoned the well at that depth and moved his equipment from the lease. It was further alleged that as a consequence of appellant’s refusal to complete the well as agreed that “a dispute arose between plaintiff (appellant) and defendant (appellee) as to the liability, if any, ■of defendant for the partially completed work performed by plaintiff prior to his abandonment of said well and the liability, if any, of plaintiff for his failure to drill and complete said well as required by the terms of said contract * ⅝ and that as a result of this dispute an accord and satisfaction was effected by the payment of $913.50-to appellant and his execution of the following release:

“Lading, Texas,
“August 31, 1949.
■“Received of Parker Petroleum Company Nine Hundred & Thirteen And 50/100 Dollars (913.50) in cash, being payment in full and final settlement of any and all claims and demands account of that certain drilling contract entered into between Preston Laws and Parker Petroleum Company, dated August 15th, 1949; which said Drilling Contract provided for drilling the #3 well ■on the Robert Malone et al lease in Caldwell County, Texas.
“/S/ Preston Laws
Preston' Laws.”

The answer also contained’ a general denial.

Trial by the court resulted in a judgment for appellee. It is worthy of note that'this judgment did not contain the usual recitation that “the law and the facts are with defendant” but only recited that “the law of this case is with the defendant.”

Findings of fact and conclusions of law were not requested and were not filed.

Appellant’s three points question the efficacy of the release executed by him to discharge appellee’s obligations under the contract. -

■ Appellee has two counter points, the second of which asserts that since there was a bona fide dispute concerning a breach, vel non, of the contract and the respective liabilities, if any, of the parties thereunder, the release executed by appellant constituted a valid accord and satisfaction.

Appellee’s first counter point is that in support of the judgment it must be presumed that the coiirt found adversely to appellant on all issues relating to his action for breach of .contract.

The argument under this point is unattended by any facts and in order to pass upon this question we have had to read the 242-page statement of facts. 1 We will state the material facts and evidence.

Saturday, Sunday, Monday, Tuesday and Wednesday hereafter mentioned are August 27, 28, 29, 30 and 31, 1949.

The contract contained these material provisions:

“Contractor 2 agrees that operations for the drilling of said well shall be commenced on or before August 20, 1949; and that the drilling operation shall be continued with thé due diligence to completion as hereinafter provided, that said well shall be drilled in a thorough and work-man like manner, with a 'hole for surface casing 15 inches in diameter and the balance of the hole a minimum of 8-¾" in diameter; to a depth of 2200 feet, or to such lesser depth at which Company shall select to abandon the well or to set an oil string and complete the well as a producing well. ⅜ ⅜ % ' ■ ‘
“Contractor shall' take cores, drill reduced hole,' make drill stem tests and electrical log or other surveys at such points and time .as Company may designate; shall set liner and/or- test at any depth, when requested by and in a' manner acceptable to Company. • Coring and testing, shall be paid for by Company at the hourly rate hereinafter -specified, except that no extra charge or .rig time shall -be made by Contractor. while electrical ■ or •gamma ray log is being -run, while surface cement is setting, or while any casing ce-ment, is setting. Service charges made by *400 Service Companies for electrical logs, drill stem testing and cementing will be paid by Company.
⅜ ‡ ⅜ ⅝ ⅝ ♦ .
“Contractor shall maintain the kind, nature, wfeight, viscosity, water loss, and other awasteristics and properties of the mud in the condition required by Company or its representatives at any and all times, it being understood,, however, that Company shall furnish the mud weighting material at Company’s expense, if and when same is found necessary;
* * * * * *
“(b) For the drilling, completion or abandonment of said well, and the performance of all acts, duties and operations herein specified to be done, made and performed by Contractor, other than work herein expressly stipulated to be hourly work, Contractor , shall receive $2.25 per foot. Any hole made by the Contractor, at Company’s request, below 2200 feet de&th, will be on the basis of $15.00 per hour. It is understood and agreed that any hourly work done at the request of Company will be on the basis of $15.00 per hour.
“(c) It is understood and agreed that no rig time costs will accumulate while either the surface casing cement is setting or while any other casing cement is setting.
“Any circulating for samples, at Company’s request, will 'be paid for by Company on the hourly basis set out herein, -but it is expressly understood and agreed that any other circulating, including that done to condition the hole, will be at the Contractor’s sole cost and expense.
“(d) $500.00 shall be paid by Company to Contractor when the surface casing is set; said $500.00 to be deducted from the total consideration when Contractor is finally paid for completed well.
“The balance of the contract price to be paid by Company to Contractor when the well is completed; it being understood and agreed that the final consideration will be computed on the basis set out above for the actual footage drilled up to the completion or abandonment of the well.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Friedsam v. Ulbricht
315 S.W.2d 442 (Court of Appeals of Texas, 1958)
Parker Petroleum Co. v. Laws
242 S.W.2d 164 (Texas Supreme Court, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
237 S.W.2d 398, 1951 Tex. App. LEXIS 1530, Counsel Stack Legal Research, https://law.counselstack.com/opinion/laws-v-parker-petroleum-co-texapp-1951.