Nott, Ch. J.,

delivered the opinion of the court:

This case is identical with a number of cases which have been before the court — the cases of the Squando (27 C. Cls. R., 422), the Nauset (29 id., 567), the Umpqua (28 id., 564), and the Baubue (31 id., 468) — in every particular save one. The vessel constructed was one of a class, the “ light-draft monitors;” the contract and specifications of all were the same; the vessel in size and form was the same; the period of construction was substantially the same; the nature of the changes, alterations, and delays was the same; the increase in the cost of labor and material during the time of construction was the same; and the statute referring the case to this courtis identical in terms with the other statutes of reference.

The particular in which the case differs from the others is this: After the contract had been executed and the work had been begun the Navy Department objected to the vessel being built in Boston and insisted that it was the purpose and policy of the Department that she should be built in Portland, Me. This requirement was not expressed in the contract, or in the specifications, or in the advertisement for proposals, or in any letter or paper which has been brought to the attention of the court. The builder remonstrated, but the Department was imperative and the builder expressed his willingness to yield. About this time the-Department discovered that an instrument had been executed by the contractor and the treasurer of the Globe Works in Boston which the Department construed to be ah assignment of the contract. The matter was referred to the Attorney-General, and he gave an opinion holding that this agreement was an assignment and worked an annulment of the contract under the Act 17th July, 1862 (12 Stat. L., 596). Some correspondence ensued, in which the [255]*255builder reiterated bis willingness to construct tlie vessel at Portland, and resulted in tbe execution of a second contract . differing from tbe first only in dates.

Before tbe execution of this second contract plans and specifications had been furnished by tbe Department and work for tbe vessel bad been begun in the Globe Works in Boston, and delays bad occurred on tbe part of tbe Government. Tbe only effect of tbe second contract on the case is this, that if it be taken as fixing tbe beginning of tbe mutual obligations of tbe parties, of tbe builder to construct a vessel within eight months and of tbe employer to enable him to do so, tbe period of obligation will be postponed five months and tbe amount of damages to be recovered will be reduced from $ 13b, 187 to $36,385.

All of tbe payments that were made to tbe builder assumed to be made under tbe second contract, and tbe counsel for the claimant has conceded tb at tbe work was technically done under that contract; but tbe Department allowed and made payments for alterations which bad been ordered before tbe date of the second contract, and the case was so treated by tbe Gregory board, a naval board presided over by Admiral Gregory which examined all tbe claims of all tbe contractors and recommended allowances to them. (See 27 C. Cls. R., 422, where tbe history of tbe Gregory board is given.)

Tbe theory upon which tbe previous cases were decided was this: The court regarded tbe contract as giving to tbe builder a period of eight months within which be was bound to construct and complete tbe vessel, and to tbe Government, reciprocally, the same period of eight months within which it was not responsible under tbe statute “for any advance in tbe price of labor or material.” The “ prolonged term for completing tbe work,” in tbe opinion of tbe court, began when tbe eight months expired. In this case tbe first contract bore date tbe 2d day of June, 1863, and tbe period of construction, therefore, would have expired on tbe 2d day of February, 1864. If that was tbe day when tbe Government’s liability began for “ additional cost of labor and material” and for increased expenses, tbe claimant should recover for—

Increased cost of labor. $36,440.01
Increased cost of materials. 55,540.50
Expenses, superintendence, etc. 7,288.00
Amounting in all to. 99,268.51

[256]*256The second contract bore date November 3,1863, and consequently the period of eight months expired on the 3d day of July, 1864. If that was the day on which the liability of the Government began, the claimant should recover nothing for increased cost of labor or increased cost of material and only $5,466 for “expenses, superintendence, etc.” In either of these alternatives the claimant should also recover for an unpaid balance of changes and alterations ordered by the Navy Department, $30,919.08. The total recovery therefor on the claimant’s theory of the case should be $130,187.59 and on the defendant’s, $36,385.08.

The position taken by the counsel for the claimant is substantially that which was taken by the Gregory board, when they disregarded the date of the second contract and considered alterations and additions as if a part of the work had been done under the first. The counsel contends that it was the intention of Congress when they referred the claim to this court that the contractor should be made whole for changes and alterations ordered by the Navy Department and for damages sustained by reason of delays in the progress of the work caused by the officers of the Government, irrespective of the contract or contracts.

It is true that when this special act was passed conferring jurisdiction and declaring and limiting the liability of the United States, the claimant could not recover upon either contract. Its terms constituted a complete defense. This had been decided by the highest judicial authority in the case of the Etlah (Chouteau v. The United States, 95 U. S., 61). Congress therefore disregarded the term of the contract when they enacted this law, which is in these words:

“AIN* ACT for the relief of the administratrix of the estate of George 'W. La-wrenoo.
uJBe it enacted by the Senate and House of Representatives of the United States of America in Congress assembled. That the claims of George W. Lawrence for further compensation for the construction of the United States monitor Wassuc may be submitted by said claimant within six months after the passage of this act to the Court of Claims, under and in compliance with the rules and regulations of said court; and said court shall have jurisdiction to hear and determine and render judgment upon the same: Provided, however, That the investigation of said claim shall be made upon the following basis: The said court shall ascertain the additional cost which was necessarily [257]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chouteau v. United States
95 U.S. 61 (Supreme Court, 1877)
McKay v. United States
27 Ct. Cl. 422 (Court of Claims, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
32 Ct. Cl. 245, 1897 U.S. Ct. Cl. LEXIS 113, 1800 WL 2076, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lawrence-v-united-states-cc-1897.