Lawrence v. Saratoga Lake Railway Co.

43 N.Y. Sup. Ct. 467
CourtNew York Supreme Court
DecidedMay 15, 1885
StatusPublished

This text of 43 N.Y. Sup. Ct. 467 (Lawrence v. Saratoga Lake Railway Co.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lawrence v. Saratoga Lake Railway Co., 43 N.Y. Sup. Ct. 467 (N.Y. Super. Ct. 1885).

Opinion

Learned, P. J.:

The objection that the present plaintiffs have not the title to the land, or did not succeed to the title of Henry Lawrence, is not well taken. After his death pending the action, a stipulation was signed by defendant’s attorney that the present plaintiffs had succeeded to his interests. And on that stipulation an order was made reciting the fact of such succession and ordering the substitution. That is sufficient. Nor is the objection well taken that Henry Lawrence is not alleged or proved to have been the owner in fee. No dispute arose on that point. The defendant took possession under him and by virtue of his title, and is in possession only by virtue of his title. When called on to perform its contract it cannot retain possession and deny his title.

The objection that the defendant did not sign any contract is not valid. The contract consits of two written propositions made by Lawrence at the request of Burt (who either acted for defendant or to whom the defendant succeeded). The defendant accepted the propositions and acted upon them, entering into the premises of Lawrence by and under the same. And the defendant has proceeded to construct its track ar 1 to do many other acts, making permanent changes upon the land; so that the land cannot be restored to plaintiffs in its original condition. These facts are a ground for the enforcement of a contract, although it is not in writing. The reason is, that it would be a fraud for the vendor to permit the vendee, under a verbal contract, to make permanent improvements, and then to deprive the vendee of the land by ejectment. And rights must be mutual. If then a vendor cannot refuse performance when the vendee has entered and made improvements; conversely the vendee cannot refuse to perform in such a case, on the ground that the contract was verbal.

Again, it is true that a verbal contract, must be definite in order to [472]*472entitle either party to specific performance. An indefinite contract cannot be enforced, because the courts do not know what the parties agreed to. In the present case the contract is in writing. It is distinct and definite. The situation of the road was indicated in a map given in evidence. The circumstance that this map is not attached to the judge's decision did not prevent him from taking it into consideration, and from giving a judgment based upon the map and the other evidence.

The learned justice foimd that the defendant had neglected and refused to perform three things, which, by the terms of the contract, it was plainly bound to do. He held that damages would not adequately compensate the plaintiffs for this neglect and refusal, and that equity required that the contract should be specifically performed; that unless the whole contract could be specifically performed, no degree for specific performance of a part could be made ; that the agreements as to those three things were so indefinite and uncertain, and related to business of such a nature and continuance, that specific performance could not be adjudged. He dismissed the complaint without pi-ejudice to any action by the plaintiffs.

One of the three things was to construct and maintain a bridge over the railroad at the olu highway at Lawrence’s east line. We see nothing indefinite in this. There can be no difficulty in determining where the highway is. To insist that the railroad cannot build a bridge because they do not know whether it should be of wood, or iron, or gold, or platinum, is a poor excuse. A bridge suitable for a highway crossing is what is intended, and that is - definite enough. (Jones v. Seligman, 81 N. Y., 190.) If defendant were willing to perform its agreement, it would have no difficulty in understanding its obligations.

Another thing to be done is similar : to construct and maintain a neat and good bridge near the west end of the potato field, for an overhead drive over the railroad. It is not shown that .the situation of the potato field cannot be determined, or that there is doubt which is its west .end. Indeed, by the opinion of the learned justice it appears that the map given in evidence gave the places where the bridges were to be placed. But the defendant’s objection, is that the size and material are not specified. We .do not see why [473]*473uroof might not be given as to the size and material suitable and proper for bridges at those places, and for the purposes indicated. It is often the case that proof of surrounding circumstances is •needed to explain a contract. The learned justice, in his conclusions, holds that the defendant is bound by the provisions of the 'contract, and can only hold the land by performing its agreement, and that justice and equity requires that these provisions should be specifically performed. But 'if these provisions are so indefinite that the court cannot decide whether or not a pretended performance is a real performance, then how can the defendant be bound ? We have these two alternatives: either the agreement is so indefinite that the court cannot determine when it has been performed. In that case it is void, and the def endants must surrender up the land. Or it is definite enough for the court to decide whether it has been performed. In that case defendants should be made to perform, unless there be some reason to the contrary. Plainly the •defendant, who has taken possession of the land under this contract, cannot be permitted to say that the contract is so indefinite •that the defendant cannot perform its side of the contract, but that without performing the defendant will keep that land for which the performance of the contract was the consideration.

The third thing to be done by defendant was to erect at or near Excelsior Spring a neat and tasteful station building for the accommodation of passengers to and from said spring, which should be a regular station, and to have all regular trains stop at said station; .the name to be Excelsior Spring Station.

The same argument in regard to this building is urged by defend-ant, viz.: that the words “ a neat and tasteful station building for the accommodation of passengers to and from said spring,” are too indefinite. But it is found as a fact .that the defendant has built .station buildings for similar purposes; one about 4,000 feet east and the other about the same distance west of the spring. Would there be any difficulty on defendant’s part in building one at the plaintifE’s spring ? And would it not be easy for a court or a jury, to -decide whether a building was a fair and reasonable performance of this agreement, or was a fraud and an evasion ?

It is urged that equity will not enforce specifically a contract to build or repair. (See Story Eq., § 726, etc.: Beck v. Allison, 56 [474]*474N. Y., 366; Pomeroy’s Eq., § 1402».) Of course, the evident reason of this rule is that usually damages are a sufficient remedy.. The plaintiff can build or repair, and sue for the amount expended. Put there are instances where the reason does not exist; and where the plaintiff cannot himself build or repair; and in which damages would not be sufficient. Mr. Pomeroy, in his note, makes four-classes of exceptions; the second is where the defendant has contracted to construct some work on his own land, and the plaintiff has an interest which cannot be compensated in damages. An instance is Storer v. Great Western Railway Company (2 Y. & C., 48).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marble Co. v. Ripley
77 U.S. 339 (Supreme Court, 1870)
Bradley v. . Aldrich
40 N.Y. 504 (New York Court of Appeals, 1869)
Jones v. . Seligman
81 N.Y. 190 (New York Court of Appeals, 1880)
Beck v. . Allison
56 N.Y. 366 (New York Court of Appeals, 1874)
Morss v. Elmendorf
11 Paige Ch. 277 (New York Court of Chancery, 1844)
Stuyvesant v. Mayor of New-York
11 Paige Ch. 414 (New York Court of Chancery, 1845)
Seeley v. New York National Exchange Bank
8 Daly 400 (New York Court of Common Pleas, 1878)
Poet Clinton Railroad v. Cleveland & Toledo Railroad
13 Ohio St. 544 (Ohio Supreme Court, 1862)
Blanchard v. Detroit, Lansing & Lake Michigan Railroad
31 Mich. 43 (Michigan Supreme Court, 1875)

Cite This Page — Counsel Stack

Bluebook (online)
43 N.Y. Sup. Ct. 467, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lawrence-v-saratoga-lake-railway-co-nysupct-1885.