Lawrence M Clarke Inc v. Kim S Draeger

CourtMichigan Court of Appeals
DecidedMarch 20, 2018
Docket336481
StatusUnpublished

This text of Lawrence M Clarke Inc v. Kim S Draeger (Lawrence M Clarke Inc v. Kim S Draeger) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lawrence M Clarke Inc v. Kim S Draeger, (Mich. Ct. App. 2018).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

LAWRENCE M. CLARKE, INC., UNPUBLISHED March 20, 2018 Plaintiff/Counter-Defendant- Appellee,

V No. 336481 Ingham Circuit Court KIM S. DRAEGER, LC No. 08-000227-CZ

Defendant-Appellant,

and

KD EQUIPMENT LEASING, INC., and AIC, INC.,

Defendants/Counter- Plaintiffs/Third-Party Plaintiffs- Appellants,

GUARANTEE COMPANY OF NORTH AMERICA USA and XL REINSURANCE AMERICA, INC.,

Third-Party Defendants-Appellees.

Before: SAWYER, P.J., and BORRELLO and SERVITTO, JJ.

PER CURIAM.

In this contractor-subcontractor dispute, defendant Kim Draeger, and two corporations he controls, KD Equipment Leasing, Inc., and AIC, Inc.,1 appeal as of right the trial court’s

1 Because of the substantial identity between the individual and corporate defendants, and the dismissal from the case of the third-party defendants, we emulate the trial court’s practice and use the singular term “defendant” to refer collectively to the defendants-appellants.

-1- judgment, on remand from this Court, awarding damages to plaintiff. We affirm in part, vacate in part, and remand for further proceedings.

I. FACTS

This case returns to this Court after an earlier decision remanded the case for further proceedings. Lawrence M Clarke, Inc v Draeger, unpublished per curiam opinion of the Court of Appeals, issued January 15, 2015 (Docket No. 316194) (“Draeger I”). This Court’s prior opinion contains the following statement of facts:

Plaintiff was the general contractor for construction of a portion of a sani- tary sewer system in Billings Township. Defendant had earlier encouraged plain- tiff to bid on the project, and provided plaintiff with a unit-price proposal cover- ing all the projected work. Plaintiff accepted the proposal and, after increasing the prices by 12 percent for its own profit, submitted it as its bid. Initially plaintiff had expected defendant, as its subcontractor, to provide all the materials and do all the work, with plaintiff contributing only some general supervision.

Defendant arranged with two subcontractors of its own to work on the pro- ject. The parties entered into a written subcontract for work to be performed by defendant in two sections of the project. Defendant and its subcontractors worked on other sections as well, but no additional subcontracts were executed. Plaintiff itself tended to some sections as well, in order to fulfill its obligations to the mu- nicipality under the general contract.

But, as the trial court summarized, “the project did not begin, progress, or end in a perfect world.” According to plaintiff’s witnesses, defendant and its sub- contractors provided less than perfect, competent, or complete work.

* * *

Plaintiff commenced action in 2008, setting forth several theories of recovery, including breach of contract and unjust enrichment. Defendants counterclaimed, alleging breach of contract and, alternatively, unjust enrichment, and initiated a third-party action for payment bond against plaintiff’s two sureties. The trial court summarized the evidence concerning deficiencies in defendant’s performance on the project, held that the individual defendant should be per- sonally responsible for the corporate defendants’ liabilities in the matter, and awarded plaintiff over $900,000 in damages, costs, and interest. The court con- cluded that the question of the existence of attendant contracts, and of per- formance under them, was “somewhat problematic,” and elected to decide the case under the theory of quantum meruit. [Draeger I, p 2.]

This Court concluded that the trial court erred by (1) resolving the case through application of the doctrine of quantum meruit, or unjust enrichment, where the court acknowledged that a written contract covered at least part of the activities at issue, (2) determining what defendant was entitled to collect on the basis of pay estimates without

-2- reference to any purported final measurements, and (3) “holding defendant responsible for the full amounts of payment bond claims that plaintiff in fact settled for lesser amounts,” but that defendant failed to show that the court otherwise miscalculated damages, or erred in deciding to pierce the corporate veil. Id., p 12.

On remand, the trial court reviewed the testimony and exhibits from the lengthy bench trial, and entertained additional oral and written arguments from the parties. The court recited that this Court called for a determination of what aspects of the parties’ relationship actually came under contract and for reevaluation of the evidence under contract law where applicable, and for use of final measurements in calculating damages by consulting Change Order 4 or better documentation for that purpose. The court further noted that this Court held that the trial court erroneously awarded plaintiff “back charges in connection with bond claims in amounts greater than what plaintiff actually paid.”

The trial court offered findings in connection with contract law, with no mention of quantum meruit or unjust enrichment. The court stated that recalculating damages under the rubric of contract law instead of quantum meruit did not eliminate the problem that only “in a perfect world damages caused by a party’s breach of the contract could be mathematically and precisely calculated,” thus underscoring the principle, as reiterated by this Court, that “[w]e do not, in the assessment of damages require a mathematical precision in situations of injury where, from the very nature of the circumstances, precision is unattainable,” and instead, “[w]e do the best we can with what we have.” Hofmann v Auto Club Ins Ass’n, 211 Mich App 55, 111; 535 NW2d 529 (1995) (quotation marks and citations omitted). On remand, the trial court concluded that plaintiff was entitled to a judgment of $696,960.99, plus statutory interest and costs.

On appeal, defendant argues that the trial court failed to follow this Court’s instructions on remand in connection with identifying final measurements, and factoring bond claims into back charges, and asks that the case again be remanded for further proceedings, this time before a different judge.

II. REMAND ORDER

Whether a tribunal complied with a remand order presents a question of law subject to review de novo. Kalamazoo v Dep’t of Corrections (After Remand), 229 Mich App 132, 134- 135; 580 NW2d 475 (1998).

A. FINAL MEASUREMENTS

An issue in the prior appeal involved the trial court’s decision to measure the work defendant completed by consulting periodic pay estimates as opposed to any documentation purporting to indicate final measurements. This Court noted that the subject construction project was conducted by way of unit price contracts, and also that plaintiff’s vice president testified that the pay estimates were in fact set forth with real care, elaborating that “[e]verybody pulled the tape measure when we had an inspector handy,” but admitting that the engineers’ final measurement was apt to differ somewhat from the total of the pay estimates and in that event payment would properly reflect the final measurement. This Court further summarized the issue as follows:

-3- Article 10 of the subcontract executed for two sections of the project covers payment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re MKK
781 N.W.2d 132 (Michigan Court of Appeals, 2009)
City of Kalamazoo v. Department of Corrections
580 N.W.2d 475 (Michigan Court of Appeals, 1998)
Parmet Homes, Inc. v. Republic Insurance
314 N.W.2d 453 (Michigan Court of Appeals, 1981)
Hofmann v. Auto Club Insurance
535 N.W.2d 529 (Michigan Court of Appeals, 1995)
Tel-Ex Plaza, Inc. v. Hardees Restaurants, Inc.
255 N.W.2d 794 (Michigan Court of Appeals, 1977)
Goodwin, Inc. v. ORSON E. COE PONTIAC, INC.
233 N.W.2d 598 (Michigan Court of Appeals, 1975)
Dawe v. Dr Reuven Bar-Levav & Associates, PC
808 N.W.2d 240 (Michigan Court of Appeals, 2010)
In re Foster Attorney Fees
894 N.W.2d 718 (Michigan Court of Appeals, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Lawrence M Clarke Inc v. Kim S Draeger, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lawrence-m-clarke-inc-v-kim-s-draeger-michctapp-2018.