Lawler v. Pepper Construction Co.

178 N.E.2d 687, 33 Ill. App. 2d 188, 1961 Ill. App. LEXIS 296
CourtAppellate Court of Illinois
DecidedNovember 15, 1961
DocketGen. 48,368
StatusPublished
Cited by24 cases

This text of 178 N.E.2d 687 (Lawler v. Pepper Construction Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lawler v. Pepper Construction Co., 178 N.E.2d 687, 33 Ill. App. 2d 188, 1961 Ill. App. LEXIS 296 (Ill. Ct. App. 1961).

Opinion

MR. JUSTICE DEMPSEY

delivered the opinion of the court.

This is an action for personal injuries arising out of the Illinois Structural Work Act, Ill Rev Stats, c 48, §§ 60-69 (1949). The verdict was for the plaintiff and the defendant has appealed on the grounds that it did not have charge of the work within the meaning of the statute, that there was no evidence of a wilful violation as required by the statute, that the verdict was against the manifest weight of the evidence, and that the court erred in admitting evidence and in refusing instructions.

The defendant, Pepper Construction Company, was a subcontractor engaged by the American Glass Company to assist it in remodeling fifteen store windows on the State Street side of the Marshall Field & Company store in Chicago. The pattern of operation was for American to remove the glass from the windows then Pepper would take out the old sashes and molding from around the windows and the transoms above the windows, and do other preparatory work. After this was done metal workers employed by American would install new sashes and other workmen would complete the job. James Lawler, the plaintiff, was one of these metal workers.

As part of its contract Pepper erected public and weather-protection barricades, four feet out on the sidewalk, around the open windows. There were two of these so that two windows could be under repair at the same time and the flow of work could be continuous. In order to do its own work, which took three days for each window, Pepper constructed a wooden scaffold within one barricade. The scaffold was dismantled as Pepper’s work on each window was completed and rebuilt within the second barricade as a new window was started. It was made of 2 x 4’s and 2 x 6’s, with a platform on top about 7 feet high consisting of 2 x 12 planks, 14 feet long. The scaffold was held together by nails and was supported on each side by a 1 x 4 brace which was nailed into the barricade.

At the end of Friday afternoon, September 29, 1950, Pepper finished a window and notified American that the sheet metal workers could proceed. The Pepper foreman testified that he instructed his carpenters to disassemble the scaffold and place the lumber inside the store window. He said he saw this done before he left the job. About 8 a. m., Saturday morning, which was the first day he was assigned to the Marshall Field project, Lawler and two other metal workers entered the barricade. They testified that the scaffold was in place so they used it as two of them had done —in the presence of Pepper’s foreman and employees —on other occasions. For three hours they frequently climbed on and off the scaffold which was made of new lumber and which seemed to them steady and secure. About 11 a. m., as they were on the platform drilling holes in an “I” beam, the scaffold suddenly swayed and then sagged at one end. The two workers who were at the ends grasped the uprights and did not fall, but Lawler, who was in the middle fell backwards as the platform planks slipped off. He landed on the sidewalk and fractured his right heel and his left ankle. Because of his pain he did not notice what caused the scaffold to give way. One of the workers said he saw a brace broken loose from the barricade; the other worker had died before the trial.

Pepper’s foreman denied seeing employees of American Glass use the scaffold; he said they had no permission to do so and that they had their own jack-ladders and planks. He testified he did not know they worked on Saturdays, but he knew they did work overtime and that there was a deadline for completing the job because of the approaching Christmas season. Although he said the scaffold was taken down before he left for home on Friday afternoon, he also said that when he returned to Field’s on Monday morning it was assembled and that one of the braces which attached to the barricade was hanging loose.

The first ground urged for reversal is that Pepper did not have charge of the work within the meaning of the statute. The pertinent portions of the Structural Work Act are as follows:

“. . . all scaffolds . . . erected or constructed by any . . . corporation . . . for the use in the . . . alteration ... of any . . . building . . . shall be erected and constructed, in a safe, suitable and proper manner, and shall be so erected and constructed, placed and operated as to give proper and adequate protection to the life and limb of any person or persons employed or engaged thereon. . . .
“Any owner, contractor, sub-contractor, foreman or other person, having charge of the . . . alteration ... of any building . . . within the provisions of this act, shall comply with all the terms thereof. . . .
“For any injury to person . . . occasioned by any wilful violations of this act, or wilful failure to comply with any of its provisions, a right of action shall accrue to the party injured. . . .”

Because it was not primarily in charge of the alteration, had completed its duties on the particular window involved and had no representative present at the time the accident occurred, and because its own evidence showed that it had constructed the scaffold for its own employees, that no one else had permission to use it and that it was taken down the day before Lawler fell, the defendant seeks to come within the interpretation given the statute in Gannon v. C., M., St. P. & P. Ry. Co., 22 Ill2d 305, 175 NE2d 785. In the Gannon case it was held that a property owner, who exercised no control over the scaffolds and ladders used in construction work on its premises and no control over the manner in which the work was done, could not be deemed to have charge of the work under the terms of the Act. However, the facts here differ widely from those in the Gannon case not only in that Pepper was a subcontractor and the defendant in Gannon was an owner, but because of Pepper’s participation in the work being done and its responsibility for and its control over the scaffold.

From the evidence the jury could have found that employees of American had used the Pepper scaffold during the course of remodeling the windows, that Pepper had left its scaffold up on Friday knowing that the metal workers would be following it on the job and that this was equivalent to an invitation to them to continue using it. Pepper was a subcontractor participating in a phase of the alteration which required a scaffold; it was the party who built the scaffold and was responsible for its safe construction and use. Under these facts Pepper had charge of the alteration within the meaning and the provisions of the Act.

The second point made by the defendant is that there was no evidence of a wilful violation as required by the statute. The jury answered affirmatively a special interrogatory submitted to them at the defendant’s request: “Was there a wilful violation of the Scaffold Act by the defendant?” The words “wilful violations” in the Act have been construed to be synonymous with the words “knowing violations.” Gannon v. C., M., St. P. & P. Ry. Co., supra; Kennerly v. Shell Oil Co., 13 Ill2d 431, 150 NE2d 134.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hansen v. Demarakis
630 N.E.2d 1202 (Appellate Court of Illinois, 1994)
Crist v. Debron Corp.
421 N.E.2d 997 (Appellate Court of Illinois, 1981)
Swager v. Couri
376 N.E.2d 456 (Appellate Court of Illinois, 1978)
Powers v. National Mirror Works
367 N.E.2d 763 (Appellate Court of Illinois, 1977)
Warren v. Meeker
302 N.E.2d 54 (Illinois Supreme Court, 1973)
Doherty v. National Casting Division, Midland-Ross Corp.
285 N.E.2d 537 (Appellate Court of Illinois, 1972)
Doherty v. NAT. CASTING DIV., MIDLAND-ROSS CORP.
285 N.E.2d 537 (Appellate Court of Illinois, 1972)
Jackson v. H. J. Frierdich & Sons, Inc.
274 N.E.2d 189 (Appellate Court of Illinois, 1971)
Herget National Bank v. Julius Zeeck
271 N.E.2d 84 (Appellate Court of Illinois, 1971)
Pantaleo v. Gamm
245 N.E.2d 618 (Appellate Court of Illinois, 1969)
McEwen v. Walsh
238 N.E.2d 616 (Appellate Court of Illinois, 1968)
City of Chicago v. Albert J. Schorsch Realty Co.
238 N.E.2d 426 (Appellate Court of Illinois, 1968)
Williams v. Brown Manufacturing Co.
236 N.E.2d 125 (Appellate Court of Illinois, 1968)
Holt v. A. L. Salzman & Sons
232 N.E.2d 537 (Appellate Court of Illinois, 1967)
Roder v. Dobbs
218 N.E.2d 873 (Appellate Court of Illinois, 1966)
Hopwood v. Thomas Hoist Co.
219 N.E.2d 76 (Appellate Court of Illinois, 1966)
Kobus v. Formfit Co.
206 N.E.2d 477 (Appellate Court of Illinois, 1965)
Kortlander v. Chicago Transit Authority
205 N.E.2d 516 (Appellate Court of Illinois, 1965)
Hoff v. Yellow Cab Co.
203 N.E.2d 8 (Appellate Court of Illinois, 1964)
City National Bank & Trust Co. v. Almond
192 N.E.2d 297 (Appellate Court of Illinois, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
178 N.E.2d 687, 33 Ill. App. 2d 188, 1961 Ill. App. LEXIS 296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lawler-v-pepper-construction-co-illappct-1961.