lattuca v. silver

CourtVermont Superior Court
DecidedDecember 29, 2023
Docket605-9-09 rdcv
StatusPublished

This text of lattuca v. silver (lattuca v. silver) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
lattuca v. silver, (Vt. Ct. App. 2023).

Opinion

STATE OF VERMONT

SUPERIOR COURT CIVIL DIVISION RUTLAND UNIT Docket # 605-8-09 Rdev RUSSELL LATTUCA and

ANN LATTUCA 6,

V.

THOMAS SILVER

Findings of Fact and Conclusions of Law

This matter came before the court for a court trial on November 29, 2010. Plaintiffs Russell and Ann Lattuca were present and represented by Attorney Robert McClallen. Defendant Thomas Silver represented himself. Plaintiffs had contracted with Defendant to paint their house for $13,000, and paid a deposit of $6,500.00. They claim that Defendant breached the contract, and that therefore they terminated the project.

They seek return of their deposit plus an additional amount of $4,000 based on the additional cost of $17,000 to have the work done by someone else. Defendant claims Plaintiffs breached the contract, and seeks to retain the deposit. .

Based on the credible evidence, the court finds the following facts and makes the following rulings of law.

Findings of Fact

Plaintiffs own a large Victorian house in Wallingford. Russell,Lattuca is retired. He previously worked as a project superintendent on construction projects. Thomas Silver is a painter who has owned a painting sole proprietorship for several years.

In April of 2009, upon request, Mr. Silver submitted a written proposal to Mr. Lattuca to paint the house for the fixed price of $14,900.00. The work to be performed included “scrape, seal all cracks, . . . prime and two coats of paint.” It included all paint and materials, as well as replacing any bad clapboards up to 15. It also included a guarantee for 10 years. No completion date was included.

The parties talked further in the presence of the Lattuca’s son J oseph, who works as a superintendent for Breadloaf Construction Company. The fixed price was revised.to $13,000, with “half down, $6,500.” Mr. Russell Lattuca and Mr. Silver signed the written contract on May 9, 2009. No completion date was specified. Mr. Silver declined to specify a completion date because of the possibility of intervening causes for delay.

The Lattucas raised no objection. During the conversation, Joseph Lattuca asked how long the project would take. There is conflicting evidence as to the exact answer, but there is no conflict in that both Mr. Lattuca and Mr. Silver expected that the project represented three to four weeks worth of work... The court finds that the parties left that conversation with different expectations. Mr. Lattuca expected that Mr. Silver would begin right away, and finish in 3-4 weeks. Mr. Lattuca expected that Mr. Silver and a crew would work exclusively on this project starting immediately, and that it would be completed in 3-4 weeks. Mr. Silver expected that since there was no specified completion date in the contract, and that since the Lattucas had not expressed any need for urgency, he had discretion to finish the project on his own schedule during the painting season of the next several months of summer into the fall.

Mr. Lattuca kept what he calls a daily log of project progress. He testified that he kept the notes contemporaneously based on his observations, but that is not quite accurate, because as to at least one day, he recorded events that took place when he was not there and that he learned about from others. Nonetheless, the log represents a reasonable overall history of the events, if not entirely credible as to all details.

The contract was signed on Saturday, May 9. On Monday, two workers began scraping the house. On Tuesday, two workers worked parts of the day. Mr. Silver was leaving for a prearranged week-long vacation that Mr. Lattuca knew about. On Wednesday, two workers worked from 10 to 4:30. Mr. Silver had car trouble returning from Cape Cod, and did not come to the house until the following Tuesday, and then only for 10 minutes. The next day, two workers worked from 9:30 to 4:00. The following day,. May 21, two workers were there from noon to 1:30. No one came for the next several days. During this period, the Lattucas became increasingly annoyed that Mr. Silver and his workers were not appearing for work on a regular schedule every day. Also, there were occasions when Mr. Silver said he would come on a specific day and did not.

Also during this time, a disagreement developed about the work. Mr. Lattuca wanted Mr. Silver to scrape down to bare wood, “like they are doing on the house down the street.” Mr. Silver found that the paint clung stubbornly to the house, and concluded that there was probably lead in the paint. This did not affect the job in that he could still effectively scrape the siding to do a good job of painting according to the contract. The scraping would not, however, result in removing all the paint down to the wood.

Mr. Lattuca wanted Mr. Silver to use a grinder to remove old paint as was being done on the job that was taking place down the street. Mr. Silver does not use a grinder in his work. Although he and one of his workers experimented with a grinder on one day, he found that it was taking too long and causing damage. Grinding represents a different process than scraping. It is much more expensive. An alternative for Mr. Silver to get down to bare wood was to use a sander, but then there could be a problem with lead paint. Mr. Silver is not certified for lead paint removal, and did not want to lose his license. Mr. Lattuca told him to do it anyway, and if any inspector came around, Mr. Lattuca would just tell him that Mr. Silver was a relative. Mr. Lattuca objected to doing this. Mr. Lattuca insisted that Mr. Silver use a grinder, and was upset with Mr. Silver for refusing to do so. Mr. Silver reasonably objected to doing the job with a grinder. It was a different type of process with a different cost than the scraping on which he had offered to do a fixed price contract, and he did not believe he could do it lawfully. This was unsatisfactory to Mr. Lattuca, who wanted him to use a grinder to take the paint down to the wood, as was being done down the street. Mr. Silver’s view was that such a project would be restoring a house, not scraping and painting it. Mr. Silver said he had to do the job according to the terms of the contract, which specified scraping. ©

Because of these two issues, Mr. Lattuca was frustrated with the way Mr. Silver was proceeding with the work. Prior to Memorial Day weekend (May 22-25), Mr. Lattuca said that he would check to find out if the paint was lead paint and notify Mr. Silver, and if it was, Mr. Lattuca would let Mr. Silver continue with scraping. During the week between May 25 and May 29, Mr. Silver did not hear from Mr. Lattuca. He made telephone calls, but did not get a call back from Mr. Lattuca.

On June 1, 2009, Mr. Lattuca terminated Mr. Silver for not showing up. There is conflicting testimony about whether or not Mr. Lattuca gave Mr. Silver a warning 3 days earlier. Mr. Lattuca testified that on May 29, 2009, he told Mr. Silver that he wanted to terminate him for not progressing satisfactorily with the job, but would give him another week as a last chance. Mr. Lattuca further testified that Mr. Silver said he would be there the next day (May 30), and then did not come as promised. Mr. Silver denies that such a conference took place. In any event, it is undisputed that on June 1, 2009, Mr. Lattuca told Mr. Silver he was terminating him from the work, and that Mr. Lattuca’s reason for

-the termination was that Mr. Silver was not showing up and making progress on the job.

Mr. Silver did not agree to termination. He said he wanted to complete the contract. He believed that Mr. Lattuca was just upset, and he believed that Mr. Lattuca would “get over it” and want him to continue working. On this basis, he left his ladders there for two weeks. During this period, he told Mr. Lattuca that he wanted to continue to do the contract. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peist v. Richmond
122 A. 420 (Supreme Court of Vermont, 1923)
Hydraulitall, Inc. v. Jones Inlet Marina, Inc.
71 A.D.3d 1087 (Appellate Division of the Supreme Court of New York, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
lattuca v. silver, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lattuca-v-silver-vtsuperct-2023.