Las Vegas MacHine & Engineering Works, Inc. v. Roemisch

213 P.2d 319, 67 Nev. 1, 1950 Nev. LEXIS 41
CourtNevada Supreme Court
DecidedJanuary 3, 1950
Docket3590
StatusPublished
Cited by11 cases

This text of 213 P.2d 319 (Las Vegas MacHine & Engineering Works, Inc. v. Roemisch) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Las Vegas MacHine & Engineering Works, Inc. v. Roemisch, 213 P.2d 319, 67 Nev. 1, 1950 Nev. LEXIS 41 (Neb. 1950).

Opinion

OPINION

By the Court,

Badt, J.:

Does the contract entered into by these litigants make them joint adventurers and governed by the law of copartnerships, including the right of contribution to share the loss suffered by the alleged joint adventure?

It will avoid confusion to call the parties by their names — plaintiff and respondent being referred to as Roemiseh, defendant and appellant being called the Machine Works, and the third party to the contract (not a party to the suit) being called Perry. These parties on April 7, 1947 entered into the following written contract:

“Contract

“The parties whose names are signed below mutually agree to a three-way division of profits over and above all expenses incurred in the performance of a certain contract entered into between the Las Vegas Machine & Engineering Works, a Nevada Corporation, and Morrison-Knudsen Company for the erection of sheet metal roofing, walls and flashing on a building for the U. S. Gypsum Co. at Plaster City, California.

“The Las Vegas Machine & Engineering Works, Inc., assumes responsibility for performance of the contract. R. C. Perry, as consideration for his part, agrees to diligently superintend all of the construction work.

“R. H. Roemiseh participates because of services rendered in relation to the contract and to the loan to the *4 corporation, not to exceed $5,000, to assist in financing payroll and expenses.”

On April 15, 1947, Roemisch advanced $2,500 to the Machine Works and took its promissory note payable June 15, 1947, with interest at 6%. The Machine Works completed the construction contract in the latter part of January, 1948, at a loss of $16,313.56, the difference between the $84,000 it paid for labor and materials and the amount it received from Morrison-Knudsen. It never made a demand on either Roemisch or Perry for contribution for this loss, but when Roemisch sued on the note on September 17, 1948, the Machine Works, while admitting nonpayment of the note, answered and cross-complained by setting up its claim to contribution for Roemisch’s share of the loss and seeking a judgment against Roemisch therefor, after crediting the amount of the note. The trial court found that the parties had not entered into an agreement of joint adventure and rendered judgment for Roemisch on the note. The Machine Company has appealed from the judgment and from the order denying its motion for a new trial, insisting on its right to an affirmative answer to the question posed in the opening sentence of this opinion.

Roemisch, Perry and W. H. Kelsey, president of the Machine Works, all testified briefly at the trial. With Kelsey on the stand under cross-examination, Roemisch’s counsel called for the production of the contract between the Machine Works and Morrison-Knudsen, and the court remarked that it would order the production of the contract unless the information desired could be adduced by parol. After developing the fact that the Machine Works and Morrison-Knudsen were the sole parties to the contract, the matter of its production in court was dropped. The work was done pursuant to plans and specifications furnished Perry on the job. Perry took his orders from Kelsey and received his pay from the Machine Works. A special account was set up in the name of the Machine Works, and Perry had full charge of this account. Roemisch was never at the job *5 and it does not appear that he saw or had knowledge of any of the receipts under the contract, that he ever saw the contract, that he knew anything about any of the disbursements aggregating some $84,000, or that he saw any of the books or accounts. Roemisch did two things. (1) He procured, the contract. Whether he had it “in the bag” before the agreement with the Machine Works and Perry, and what means or influence he used to get it, do not definitely appear. (2) He lent $2,500 to the Machine Works and took its 60 day note. He was to be repaid with interest within 60 days — not out of any proceeds of the construction contract, not to any extent by Perry, not by the three (including himself) who were thus associated, but by the Machine Works alone. Thus, he was to be repaid within 60 days the money personally advanced to the Machine Works for the latter’s prosecution of a construction contract that required about nine and one-half months to complete.

Defendant’s position is simply this: (1) The agreement for the equal division of profits, for the performance of the construction contract by the Machine Works, for the superintendence of the job by Perry, and Roemisch’s promise to advance money to the Machine Works “to assist in financing payrolls and expenses” and his having procured the contract in the first place, constituted the contract one of joint adventure; (2) such contracts are governed by the law of partnership; (3) under our statute (the Uniform Partnership Law) all partners must contribute to the losses; and (4) — to make this logical sequence applicable — “It is not the intention of the parties, but the legal effect of the agreement which is controlling.” The fallacy of this position is that we cannot determine the rights of the parties to this contract simply by giving it a name. Nelson v. Abraham, 29 Cal.2d 745, 177 P.2d 931. As with other contracts, the intention of the parties (no rights of third parties being involved) must be determined from the instrument itself if this can be done. “There is no principle of hermeneutics of peculiar application to articles *6 of copartnership. They are construed by the ordinary rules for interpreting written contracts.” Walker v. Patterson, 166 Minn. 215, 208 N.W. 3, 7. See also Simpson v. Richmond Worsted Spinning Co., 128 Me. 22, 145 A. 250, and Fuller v. Laws, 219 Mo.App. 342, 271 S.W. 836.

The contract says simply this:

1. The profits of the construction of thd building by defendant for Morrison-Knudsen are to be equally shared by defendant, plaintiff and Perry.

2. Defendant “assumes responsibility for performance.”

3. The consideration for Perry’s getting a third of the profits is his agreement “to diligently superintend all construction work.”

4. The reason why plaintiff gets a third of the profits is that he procured the contract and agrees to lend defendant not to exceed $5,000 “to assist in financing payrolls and expenses.”

The brief testimony adduced adds the following information with reference to the foregoing: 1. There were no profits, but a loss of $16,313.56. 2. Defendant did assume full responsibility for the performance. Neither the construction contract nor the plans and specifications nor any details of the construction appeared in the evidence other than the general statement of Mr. Kelsey, president of the Machine Works, that “we carried out a contract there which calls for the sheathing and covering of all their new buildings.” This, as noted, involved the expenditure of some $84,000 for labor and materials and occupied some nine and one-half months. The site was Plaster City, California. 3. Perry superintended the job. His salary was paid by the Machine Works. He got orders from Kelsey, an officer of that corporation, who was his superior on the job and who had full control.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Decesare Vs. Blomberg
Nevada Supreme Court, 2019
Namer v. Sentinel Trust Co. (In Re AVN Corp.)
248 B.R. 540 (W.D. Tennessee, 2000)
Rhodes v. Sunshine Mining Co.
742 P.2d 417 (Idaho Supreme Court, 1987)
Dieleman v. Sendlein
670 P.2d 578 (Nevada Supreme Court, 1983)
Electronic Associates, Inc. v. Automatic Equipment Development Corp.
440 A.2d 249 (Supreme Court of Connecticut, 1981)
Central Bank, N.A. v. Baldwin
583 P.2d 1087 (Nevada Supreme Court, 1978)
Allison v. Dilsaver
387 S.W.2d 206 (Missouri Court of Appeals, 1965)
Stearns v. Williams
240 P.2d 833 (Idaho Supreme Court, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
213 P.2d 319, 67 Nev. 1, 1950 Nev. LEXIS 41, Counsel Stack Legal Research, https://law.counselstack.com/opinion/las-vegas-machine-engineering-works-inc-v-roemisch-nev-1950.