Larson Bros. Wholesale Grocery Co. v. City of Kansas City

224 P. 47, 115 Kan. 589, 1924 Kan. LEXIS 306
CourtSupreme Court of Kansas
DecidedMarch 8, 1924
DocketNo. 25,050
StatusPublished
Cited by15 cases

This text of 224 P. 47 (Larson Bros. Wholesale Grocery Co. v. City of Kansas City) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Larson Bros. Wholesale Grocery Co. v. City of Kansas City, 224 P. 47, 115 Kan. 589, 1924 Kan. LEXIS 306 (kan 1924).

Opinion

The opinion of the court was delivered by

Harvey, J.:

This is an action for damages against three defendants charged as joint tort-feasors. The jury answered special questions and returned a general verdict for plaintiff against all the defendants. Two defendants have appealed.

Plaintiff is a wholesale grocery company and had a warehouse at Kansas City, Kan., in the basement of which it Kept for sale and distribution a large quantity of canned goods. The basement was connected with what is known as the Ohio avenue sewer, which had been constructed by the city. Prior to the contract, soon to be mentioned, this sewer terminated at the state line on Ohio avenue and from there the sewage flowed through an open channel along the state line into the Missouri river. In April, 1917, the city of Kansas City entered into a written contract with Thomas M. Torson, a contractor, by which Torson was to continue the sewer to the Missouri river. The elevation was such that the sewage would flow into the river from the sewer at times when the water was low in the river, but when the river was at flood stage it would not do so, thereby stopping the sewer and flooding the river water into it. To avoid this, the contract provided that Torson should erect two wells at the terminus of the sewer and construct a pump house and install therein a pump of a designated capacity, sufficient to pump a certain number of cubic feet of sewage per minute against a pressure of a thirty foot head of water in the river, it being determined that was the maximum height to which the river would rise at flood time. The contract provided that:

“A thorough test of pump and motor shall be made after installation and before payment to contractor. This test shall be conducted as near as possible under actual working conditions, at which time the entire equipment [591]*591working as a complete plant shall make a performance required by specifications and satisfactory to the city engineer.”

Torson constructed the sewer and built the wells and the pump house. He contracted with the H. N. Strait Manufacturing Company to build a pump to comply with his contract with the city. The pump was built and installed. The two wells were constructed adjacent to each other, separated by a wall in which, near the bottom, was an opening, through which the sewage could pass when the river was low and which could be closed when the river would rise. To test the capacity and sufficiency of the pump and “the entire equipment working as a complete plant,” it was thought best not to wait until an actual flood in the river occurred but to “create a flood” or flood conditions, by filling the wells or one of them to the desired height and operating the pump, thus testing it under the actual working conditions it was designed to handle.

Two tests were made which, for one reason or another, were not satisfactory. The H. N. Strait Manufacturing Company then built a bulkhead and placed it in the opening between the two wells and arranged for a third test. This bulkhead was installed and the arrangements for the test made under the direction of Mr. McLaughlin, their foreman. This bulkhead was constructed of heavy timbers which could be left in place, but with a trap door to let the sewage or water through and which could be opened from the top of the well by a rope. The day for the test was set and McLaughlin notified the contractor, Torson, and he notified the city engineer and some other city officials and they were all present. They proceeded to “create a flood” by filling the well which connected directly with the sewer. The water got so high, possibly because of a delay in removing the bulkhead between the two wells or opening of the trap door therein, that it forced its way back through the sewer, thereby flooding the floor of the plaintiff’s basement with sewage to a depth varying from two inches to a foot, thus causing damage. To recover for this damage plaintiff sued the city, Torson, and the H. N. Strait Manufacturing Company. The jury returned answers to special questions as follows:

“1. Was there a contract entered into between defendant T. M. Torson and the City of Kansas City, Kansas, on the 17th day of April, 1917, whereby said Torson was to construct a 42-inch reinforced concrete sewer in the Ohio sewer district? Answer: Yes.
“2. Under said contract between defendant Torson and the city, was defendant Torson to furnish a pump as a part of the construction of said sewer? Answer: Yes.
[592]*592“3. Did defendant Torson and defendant H. N. Strait Mfg. Co. enter into . a contract whereby the H. N. Strait Mfg. Co. agreed to furnish a centrifugal pump f. o.b. H. N. Strait Manufacturing Company’s shop? Answer: Yes.
“4. Under the contract between defendant Torson and the city, was a test to be made of the pump and motor satisfactory to the city engineer? Answer: Yes.
“5. Did defendant Torson place a bulkhead in said sewer prior to the time H. N. Strait Mfg. Co. put in a bulkhead? Answer: Yes.
“6. Did the city accept the tests made at the time Torson placed the bulkheads in the sewer? Answer: No.
“7. In order to make such test as provided for under said contract, did the defendant city and Torson consent to H. N. Strait Manufacturing Company building a bulkhead and placing a bulkhead in the sewer for the purpose of making such test? Answer: Yes.
“8. Was the test as finally made, performed and executed in the presence of the representatives of the city and defendant Torson? Answer: Yes.
“9. Did the city or Torson immediately prior, to the making of such test, object to the bulkhead or the manner of its construction? Answer: No.
“10. Was the final test and preparations therefor (a) made in the presence of the representatives of the city and Torson and (b) was the test made pursuant to the contract between the city and Torson? Answer: (a) Yes. (b) Yes.
“11. Was the manner of making the test and building or placing the bulkhead in the sewer approved by the city engineer? Answer: By assenting.
“13. What was the purpose of the defendant, H. N. Strait' Mfg. Co., in testing the pump? Answer: To fulfill contract with Torson.
“14. Did the defendant Torson supervise and direct the manner in which the II. N. Strait Mfg. Co. was to make the test? Answer: No.
“15. Who do you find, from the evidence, obstructed or blocked the sewer in question? Answer: H. N. Strait with the assent of city and Torson.
“16. What do you find the fair market value of the goods in question to have been immediately before the influx of the water into the basement of the Larson Brothers Wholesale Grocery Company. Answer: $1,567.01.
“17. What do you find the fair market value of the goods in question was after the work of cleaning and overhauling had been performed by the plaintiff? Answer: $783.50.
“18. What do you find the cost to the plaintiff was, for overhauling, cleaning and relabeling the goods in question? Answer: $425.00.
“19.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Venable v. Import Volkswagen, Inc.
519 P.2d 667 (Supreme Court of Kansas, 1974)
Creten v. Chicago, Rock Island & Pacific Railroad
337 P.2d 1003 (Supreme Court of Kansas, 1959)
Applegate v. Home Oil Co.
324 P.2d 203 (Supreme Court of Kansas, 1958)
Foster v. Humburg
299 P.2d 46 (Supreme Court of Kansas, 1956)
Fitzgerald v. Thompson
204 P.2d 756 (Supreme Court of Kansas, 1949)
Acock v. Kansas City Power & Light Co.
10 P.2d 877 (Supreme Court of Kansas, 1932)
Hutchinson v. City of Lakewood
180 N.E. 643 (Ohio Supreme Court, 1932)
Carlgren v. Saindon
283 P. 620 (Supreme Court of Kansas, 1930)
Smith v. Mead Construction Co.
282 P. 708 (Supreme Court of Kansas, 1929)
Bruce ex rel. Bruce v. City of Kansas City
276 P. 284 (Supreme Court of Kansas, 1929)
Foster v. Capital Gas & Electric Co.
265 P. 81 (Supreme Court of Kansas, 1928)
Byrne v. Western Pipe & Steel Co.
253 P. 776 (California Court of Appeal, 1927)
McRae v. Missouri Pacific Railroad
225 P. 1032 (Supreme Court of Kansas, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
224 P. 47, 115 Kan. 589, 1924 Kan. LEXIS 306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/larson-bros-wholesale-grocery-co-v-city-of-kansas-city-kan-1924.