Largo v. Gregory & Cook, Inc.

7 Navajo Rptr. 111
CourtNavajo Nation Supreme Court
DecidedFebruary 17, 1995
DocketNo. A-CV-11-93
StatusPublished

This text of 7 Navajo Rptr. 111 (Largo v. Gregory & Cook, Inc.) is published on Counsel Stack Legal Research, covering Navajo Nation Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Largo v. Gregory & Cook, Inc., 7 Navajo Rptr. 111 (navajo 1995).

Opinion

OPINION

Opinion delivered by

AUSTIN, Associate Justice.

This is a direct appeal from a decision of the Navajo Nation Labor Commission. At issue is the Commission’s application of the 1990 Amendments to the Navajo Preference in Employment Act.1

I. FACTS

Gregory and Cook, Inc., (G&C) is a pipeline construction contracting company. Throughout 1991 and 1992, G&C performed construction projects within the boundaries of the Navajo Nation for both Transwestem Pipeline Company (Transwestem) and El Paso Natural Gas Company (El Paso). On January 21, 1992, G&C and El Paso entered into a Settlement Agreement with the Navajo Nation regarding work to be done on the San Juan Triangle Expansion, project 9109, for El Paso. This dispute arose under that contract.

In the Settlement Agreement, G&C agreed to fully comply with Navajo law, including the Navajo Preference in Employment Act (NPEA). In order to comply with the NPEA, G&C agreed not to hire non-Navajos to work on project 9109 within the geographical jurisdiction of the Navajo Nation, “so long as the applications of potentially qualified Navajos [had] been received.” G&C further agreed to hire a Coordinator to accept applications for employment on project 9109, to monitor the progress of those applications, and to provide the Office of Navajo Labor Relations with a weekly report on the status of every application received.

[112]*112In order to complete project 9109, G&C needed to hire welders to work on pipeline welding crews. El Paso requires each welder to possess a valid El Paso Natural Gas Company Welding Certificate to qualify to work on El Paso pipeline projects. Welding applicants for project 9109 who were not certified by El Paso were required to take and pass an El Paso welding test. Therefore, applicants who had not yet been certified by El Paso were only potentially qualified candidates for employment on project 9109 until they had been given the welding test and had been found actually qualified or actually unqualified.

Thomas Largo, Gary Miller, and Roy Largo (Petitioners) are enrolled members of the Navajo Nation. Gary Miller was hired by G&C to work as a welder on a Transwestem project in late 1991.2 On November 20 and December 20, 1991, Gary Miller took and failed the El Paso welding test. In early January, 1992, he was again hired by G&C for work on another Transwestem project. That project ended on January 26, 1992. Gary Miller then filed an application with G&C’s Coordinator for a job on project 9109.

Thomas Largo was also hired by G&C to work on the Transwestem project in early January, 1992.3 Like Gary Miller, Thomas Largo had taken and failed the El Paso welding test on November 20 and December 20, 1991. Also like Gary Miller, after the Transwestem job ended, Thomas Largo applied with G&C for a job on project 9109.

Roy Largo did not work for G&C on either Trans western project. On November 20, 1991, Roy Largo took and failed the El Paso welding test. He did not retest in December. In late January, 1992, Roy Largo also applied with G&C for a job on project 9109.

In summary, by the end of January, 1992, each of the Petitioners had properly filed an application with G&C for employment on project 9109. Because none of the Petitioners had been certified by El Paso, each waited to be given the welding test, aware that he would not be hired until he took and passed that test. Time went by, however, and the Petitioners did not receive word as to when, or if, they would be tested.

Frustrated by this lack of response, each of the Petitioners went to G&C’s yard in Farmington, New Mexico in February, 1992, in an effort to take the welding test. They were not tested. G&C began hiring welders for project 9109 in mid-February. All the welding positions were filled by March 5, 1992. Numerous non-Navajo welders were hired in February. The Petitioners’ applications were on file with G&C before hiring began, yet they were not given an opportunity to take the welding test.

The Petitioners then complained to the Office of Navajo Labor Relations, and on March 18,1992, the Petitioners were finally allowed to take the El Paso welding test. Each Petitioner passed the test. Accordingly, on March 18, 1992, all [113]*113three Petitioners became qualified to work on project 9109. G&C refused to hire them, however, because all of the welding positions on the project had been filled. Welding work on project 9109 was completed on May 5, 1992. The Petitioners had not been hired.

The Petitioners filed a formal complaint against G&C and El Paso with the Office of Navajo Labor Relations in September, 1992. The complaint alleged in part that, by not employing the Petitioners as welders on project 9109, G&C had violated the NPEA. On December 18, 1992, a hearing on the issues was held by the Navajo Nation Labor Commission (Commission).

On March 15, 1993, the Commission ruled, in part, that by failing to hire the Petitioners once they had become qualified, G&C had not given the Petitioners the employment preference mandated by Section 4(A), (C) of the NPEA. Largo, et al. v. Gregory & Cook, Inc., NNLC No. 92-006. The Commission awarded to the Petitioners, as damages, the amount of earnings that each Petitioner had lost as a result of not being employed on project 9109 from the date that he became actually qualified, until the date that the welding was completed. On April 19, 1993, the Commission denied the Petitioners’ motion for an award of attorney’s fees.

II. ISSUES

The parties raise the following issues on appeal:

1. Whether the NPEA requires employers to hold jobs open until an applicant becomes qualified, when the applicant has previously demonstrated a lack of qualification.

2. Whether the Commission erred in failing to allow G&C a credit for wages earned elsewhere by Thomas Largo when the Commission allowed such a credit for Petitioners Gary Miller and Roy Largo.

3. Whether the Commission correctly denied the Petitioners’ application for attorney’s fees.

III. DISCUSSION

A. The Requirements of the NPEA.

The first issue is whether the NPEA requires an employer to hold a job open until a Navajo applicant who has been found unqualified for the position subsequently becomes qualified. We hold that the NPEA does not require such action.

Our decision on this issue is based both upon the purposes for which the NPEA was enacted and upon the wording of the statute itself. The purposes of the NPEA, as stated in Section 2, are as follows:

1. To provide employment opportunities for the Navajo work force;
2. To provide training for the Navajo people;
3. To promote the economic development of the Navajo Nation;
[114]*1144. To lessen the Navajo Nation’s dependence upon off reservation sources of employment, income, goods and services;
5. To foster the economic self-sufficiency of Navajo families;
6. To protect the health, safety and welfare of Navajo workers; and

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
7 Navajo Rptr. 111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/largo-v-gregory-cook-inc-navajo-1995.