Lane v. Commonwealth

954 A.2d 615, 2008 Pa. Super. 157, 2008 Pa. Super. LEXIS 1601, 2008 WL 2764595
CourtSuperior Court of Pennsylvania
DecidedJuly 17, 2008
Docket1679 EDA 2007
StatusPublished
Cited by6 cases

This text of 954 A.2d 615 (Lane v. Commonwealth) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lane v. Commonwealth, 954 A.2d 615, 2008 Pa. Super. 157, 2008 Pa. Super. LEXIS 1601, 2008 WL 2764595 (Pa. Ct. App. 2008).

Opinion

*618 OPINION BY

BOWES, J.:

¶ 1 In this appeal, Neshaminy Constructors, Inc., Appellant, seeks indemnification from James J. Anderson Construction Co., Appellee, for the verdict entered against Appellant and in favor of Andrea Lane (“Plaintiff’) in this personal injury action. Application of controlling case law to the jury’s resolution of this action compels the conclusion that Appellant is not entitled to indemnification from Appellee. We therefore affirm.

¶ 2 Plaintiff was injured on June 2, 2003, while riding a bicycle along a path in Pen-nypaek Park, Philadelphia. On the day in question, Plaintiff, a Philadelphia Police Officer, was training as a bicycle patrol officer. She testified that she temporarily left the path after her rear tire slipped to the right. She was steering her bicycle back onto the path when the front wheel hit a steel reinforcement bar that had been placed near to and partially on the path. As a result, Plaintiff was thrown from her bicycle and sustained injuries. Plaintiff left the path when her wheel slipped on an unpaved portion consisting of mud and stones.

¶ 3 The area in question was part of a construction site. The Pennsylvania Department of Transportation (“PennDOT”), which is not a party on appeal, contracted with Appellant, as general contractor, to complete road work at several areas along Interstate 95. Work on Interstate 95 Pen-nypack Bridge was part of this venture. On January 30, 2003, Appellant executed a subcontract with Appellee to perform some of the work, including work at the Penny-pack Park Bridge site.

¶ 4 Appellee had excavated in the area of the fall and then vacated the job site two to three months before the accident. While Appellee was slated to return to the area at a later time to complete its contractual obligations, Appellee was not in situ when Plaintiff was injured. Appellee returned to complete its portion of the project, which included repaving the path where Plaintiff was biking, in August 2003.

¶ 5 Plaintiff instituted this action against Appellant and Appellee, among others, alleging that they had created the conditions causing her to fall. Appellant then attempted to join Providence Steel Co., Inc. (“Providence”), which was another subcontractor on the project. Providence apparently was responsible for leaving the steel reinforcement bar on the bike path. Join-der was denied based solely on its untimeliness, and Appellant does not challenge this ruling on appeal. 1

¶ 6 After the complaint was filed, Appellant raised an indemnification cross-claim against Appellee in the event that Appellant was found liable. The trial court reserved ruling on Appellant’s right to indemnification as to Appellee, and the case proceeded to a jury. Following trial, the jury found Appellant 100% responsible for Plaintiffs injuries and exonerated Appel-lee. The jury awarded Plaintiff $3,000,000 in damages. The court then severed Appellant’s indemnification claim from the personal injury action. It subsequently concluded that Appellant was not entitled to indemnification against Appellee for Appellant’s own negligence. This appeal fob lowed.

¶'7 In this case, Appellant seeks indemnification based upon a clause in Appellee’s subcontract, which was drafted by Appellant. Initially, we note that

*619 the interpretation of any contract is a question of law and this Court’s scope of review is plenary. Moreover, we need not defer to the conclusions of the trial court and are free to draw our own inferences. In interpreting a contract, the ultimate goal is to ascertain and give effect to the intent of the parties as reasonably manifested by the language of their written agreement. When construing agreements involving clear and unambiguous terms, this Court need only examine the writing itself to give effect to the parties’ understanding. This Court must construe the contract only as written and may not modify the plain meaning under the guise of interpretation.

Nevyas v. Morgan, 921 A.2d 8, 15 (Pa.Super.2007) (quoting Curtid v. Meeting House Restaurant, Inc., 869 A.2d 516, 519 (Pa.Super.2005)). “In addition, a preferred contract interpretation ascribes under all circumstances ‘the most reasonable, probable, and natural conduct to the parties.’ ” Gaffer Insurance Co., Ltd. v. Discover Reinsurance Co., 936 A.2d 1109, 1113 (Pa.Super.2007) (quoting Midomo Co. v. Presbyterian Housing Development Co., 739 A.2d 180, 191 (Pa.Super.1999)). Further, any contractual ambiguities are construed against the drafter of the provision. Bucks Orthopaedic Surgery Associates, P.C. v. Ruth, 925 A.2d 868, 871 (Pa.Super.2007).

¶ 8 Appellant herein is seeking indemnification against Appellee for Appellant’s own negligence. In such a situation, the Perry-Ruzzi rule is implicated. In Perry v. Payne, 217 Pa. 252, 66 A. 553 (1907), Perry, the owner of a building, was found hable by a jury for a man’s death. The man died due to the negligent operation of an elevator by one of the owner’s employees. The owner sought indemnification from Payne, the contractor who had constructed the building in question. Payne had relinquished control of the building to the owner but was using the elevator as a staging platform for painting in order to complete its contractual obligations.

¶ 9 Under indemnification language in a bond procured by the contractor, the contractor was responsible for damages arising from accidents to persons passing near the work. The owner contended that the bond indemnified it against all damages arising from injuries to any person close to the work, regardless of whether the injuries were caused by the negligence of the contractor or by the owner’s own negligence.

¶ 10 Our Supreme Court declined to give the language that construction. It considered the circumstances and the parties’ objective in creating the bond instrument and concluded that the indemnification was intended to apply only to damages or losses occasioned by the contractor’s work or negligence. The court stated, “It is contrary to experience and against reason that the contractors should agree to indemnify Perry against the negligence of himself or his employees. It would make them insurers, and impose a liability upon the contractors, the extent of which would be uncertain and indefinite[.]” Id. at 555. Thus, the Perry Court concluded that a contract will not be construed to provide indemnification against a person’s own negligence unless that intent is expressly and unequivocally stated and the circumstances indicate that the contract is intended to so apply.

¶ 11 The Perry rule was reaffirmed in Ruzzi v. Butler Petroleum Co., 527 Pa.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cole, J. v. Cole, L.
Superior Court of Pennsylvania, 2018
Davies, B. v. Simon Property Group
Superior Court of Pennsylvania, 2018
Ecker, E. v. National Railroad Passenger Corp.
Superior Court of Pennsylvania, 2015
Scranton Times v. Entercom Wilkes-Barre Scranton LLC
23 Pa. D. & C.5th 517 (Lackawanna County Court of Common Pleas, 2011)
State Ex Rel. Earhart v. City of Bristol
970 S.W.2d 948 (Tennessee Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
954 A.2d 615, 2008 Pa. Super. 157, 2008 Pa. Super. LEXIS 1601, 2008 WL 2764595, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lane-v-commonwealth-pasuperct-2008.