Landis Construction Co., LLC Versus Drp Masonry, LLC
This text of Landis Construction Co., LLC Versus Drp Masonry, LLC (Landis Construction Co., LLC Versus Drp Masonry, LLC) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
LANDIS CONSTRUCTION CO., LLC NO. 24-C-510
VERSUS FIFTH CIRCUIT
DRP MASONRY, LLC COURT OF APPEAL
STATE OF LOUISIANA
October 31, 2024
Susan Buchholz Chief Deputy Clerk
IN RE DRP MASONRY, LLC
APPLYING FOR SUPERVISORY WRIT FROM THE TWENTY-FOURTH JUDICIAL DISTRICT COURT, PARISH OF JEFFERSON, STATE OF LOUISIANA, DIRECTED TO THE HONORABLE JACQUELINE F. MALONEY, DIVISION "D", NUMBER 847-175
Panel composed of Judges Susan M. Chehardy, Stephen J. Windhorst, and Scott U. Schlegel
WRIT DENIED
Defendant-relator, DRP Masonry, LLC, seeks supervisory review of the trial court’s decision overruling its exception of prematurity. For the reasons that follow, we deny the writ application.
In October of 2022, DRP submitted a bid proposal for a total of $656,853.00 to perform masonry work as a subcontractor to plaintiff-respondent, Landis Construction. Landis, which was in the process of preparing its own bid to become the contractor on the Bacteriological and Wet Chemistry Laboratory project for Jefferson Parish, accepted DRP’s proposal. On March 1, 2023, Jefferson Parish awarded the contract to Landis, and on March 8, 2023, Landis awarded the masonry subcontract to DRP. DRP subsequently determined that the Unit Price Form that Landis had provided DRP for the bidding process contained inaccuracies. DRP therefore updated its bid proposal and asked Landis to revise the subcontract to reflect a new bid amount of $1,035,000.00. Landis responded that the inaccuracies in the Unit Price Form could be addressed in the form of a change order in the future. DRP did not sign the subcontract with Landis, and Landis awarded the job to another subcontractor, WT Construction, for $1,025,075.00.
According to DRP, WT began working on the project in June of 2023, but DRP did not officially decline to do the work until July of 2023.1 On September 15, 2023, Landis filed suit against DRP, alleging that it had detrimentally relied on
1 Landis’s Answer to Interrogatories indicate, however, that on May 23, 2023, DRP informed Landis that it intended to abandon the project. Nevertheless, on June 7, 2023, DRP submitted a revised proposal to Landis for $1,035,000.00.
24-C-510 DRP’s bid proposal and that DRP had breached the bid proposal when it refused to perform the masonry work for the original price stated. Landis’s Petition alleged that it sustained lost profits on the project and other economic harm. On April 30, 2024, Landis filed a supplemental and amended petition that pled additional facts in support of its detrimental reliance and breach of contract claims.
On May 20, 2024, DRP filed an exception of prematurity, arguing that Landis filed suit before its right to recover damages accrued. The trial court denied the exception. DRP now seeks supervisory review of that ruling.
An exception of prematurity questions whether a cause of action has matured to the point where it is ripe for judicial determination. Bayou Orthotic & Prosthetics Ctr., L.L.C. v. Morris Bart, L.L.C., 17-557 (La. App. 5 Cir. 3/28/18), 243 So.3d 1276, 1279. An action is deemed premature when it is brought before the right to enforce it has accrued. Id. (citing La. C.C.P. art. 423). Prematurity is determined by the facts existing at the time a suit is filed. Id. at 1279-80. The burden of proving prematurity is on the mover. Id. at 1280. An exception of prematurity ordinarily is reviewed for manifest error, unless the exception involves a question of law, in which case we conduct de novo review. Id.
DRP contends that while Landis’s lawsuit seeks to recover $368,222.00 in damages, the suit is premature because there are still outstanding payments to be made and change orders to be reviewed, rendering the final cost of the scope of masonry unknown. Actual damages are a requisite element of the breach of contract and detrimental reliance claims that Landis asserts. See Stipp v. MetLife Auto & Home Ins. Agency, Inc., 17-61 (La. App. 5 Cir. 8/30/17), 225 So.3d 1182, 1189, writ denied, 17-1774 (La. 12/5/17), 231 So.3d 632; Suire v. Lafayette City- Park. Consol. Gov’t, 04-1459 (La. 4/12/05), 907 So.2d 37, 59. According to DRP, because Landis may still recover its alleged damages through change orders submitted to the owner of the project (due to the discrepancies in the Unit Price Form), Landis had not sustained any damages at the time it filed suit, and the matter is premature.
In its opposition filed in the trial court, Landis argued that it sustained damages when it had to renegotiate a contract with another subcontractor for the masonry scope of work after DRP abandoned the project. Landis further argues that prescription began to run as soon as it realized that some damages had been sustained, per Harvey v. Dixie Graphics, Inc., 593 So.2d 351 (La. 1992). In Harvey, the Louisiana Supreme Court stated that although the damage suffered “must at least be actual and appreciable in quality[, …] there is no requirement that the quantum of damages be certain or that they be fully incurred, or incurred in some particular quantum, before the plaintiff has a right of action.” Id. at 354. Thus, under Harvey, prescription begins to run from the date on which the plaintiff suffered actual and appreciable damage. Landis contends that even if its damages had not been fully determined in September of 2023, the lawsuit is not premature. Moreover, Landis argued that DRP’s exception is moot, because the masonry work is now complete, Landis’s damages have been fully realized, and those damages can be proven with reasonable certainty.
On the showing made, we find no manifest error in the trial court’s denial of the exception of prematurity, nor in its apparent determination that DRP failed to meet its burden of proving that Landis had not incurred any damages at the time it filed suit on September 15, 2023. Even if the exact damages were indeterminate at
2 that time, exact damages are not required when filing a breach of contract claim and are prohibited from being pled in a tort action. La. C.C.P. art. 893; Harvey, supra. Accordingly, we deny DRP’s writ application.
Gretna, Louisiana, this 31st day of October, 2024.
SMC SJW SUS
3 SUSAN M. CHEHARDY CURTIS B. PURSELL
CHIEF JUDGE CLERK OF COURT
SUSAN S. BUCHHOLZ FREDERICKA H. WICKER CHIEF DEPUTY CLERK JUDE G. GRAVOIS MARC E. JOHNSON STEPHEN J. WINDHORST LINDA M. WISEMAN JOHN J. MOLAISON, JR. FIRST DEPUTY CLERK SCOTT U. SCHLEGEL TIMOTHY S. MARCEL FIFTH CIRCUIT MELISSA C. LEDET JUDGES 101 DERBIGNY STREET (70053) DIRECTOR OF CENTRAL STAFF POST OFFICE BOX 489 GRETNA, LOUISIANA 70054 (504) 376-1400
(504) 376-1498 FAX www.fifthcircuit.org
NOTICE OF DISPOSITION CERTIFICATE OF DELIVERY I CERTIFY THAT A COPY OF THE DISPOSITION IN THE FOREGOING MATTER HAS BEEN TRANSMITTED IN ACCORDANCE WITH UNIFORM RULES - COURT OF APPEAL, RULE 4-6 THIS DAY 10/31/2024 TO THE TRIAL JUDGE, THE TRIAL COURT CLERK OF COURT, AND AT LEAST ONE OF THE COUNSEL OF RECORD FOR EACH PARTY, AND TO EACH PARTY NOT REPRESENTED BY COUNSEL, AS LISTED BELOW:
24-C-510 E-NOTIFIED 24th Judicial District Court (Clerk) Honorable Jacqueline F. Maloney (DISTRICT JUDGE) Alexis N. Coco (Relator)
MAILED Christopher K. LeMieux (Respondent) Donald J. Anzelmo (Relator) Patrick A. Talley, III (Respondent) Attorney at Law Attorney at Law 200 Breard Street 1100 Poydras Street Monroe, LA 71201 Suite 1100 New Orleans, LA 70163
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Landis Construction Co., LLC Versus Drp Masonry, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/landis-construction-co-llc-versus-drp-masonry-llc-lactapp-2024.